1 Installation of dry levelling compound for SpeedUp and SpeedUp Eco
Fig. 1: Determine your datum and your compound level (min. 10 mm, max. 60 mm).
Fig. 3: With large flat trowel spread and flatten the compound. Fig. 4: Position the parallel guides on each of the lines and
Fig. 2: Pour lines of compound to a moderate height, the distance of the lines depending on the width of the leveling rule.
adjust according to the required height.
Danfoss Heating Solutions VICSA202
Fig. 6: During the leveling additional compound may be required.
1
Installation Guide Dry Levelling Compound for SpeedUp and SpeedUp Eco
Fig. 7: In larger rooms the leveling of the compound will have to be finished in several adjacent lines.
Fig. 9: Insulation panels serve as walk boards or walk islands and so prevent damage.
Fig. 8: Compound at the edges may have to be worked again with trowel.
Fig. 10: Once finished begin laying of the additional insulation.
Danfoss A/S Heating Solutions Haarupvaenget 11 8600 Silkeborg Denmark Phone:+45 7488 8000 Fax: +45 7488 8100 Email: ComfortControlsInternet@danfoss.com www.heating.danfoss.com
Danfoss can accept no responsibility for possible errors in catalogues, brochures and other printed material. Danfoss reserves the right to alter its products without notice. This also applies to products already on order provided that such alterations can be made without subsequential changes being necessary in specifications already agreed. All trademarks in this material are property of the respective companies. Danfoss and the Danfoss logotype are trademarks of Danfoss A/S. All rights reserved.
VICSA202 Produced by Danfoss Heating Solutions © 12/2010
Loading...