3020P electro-mechanical
24 hour timeswitch with auxiliary heating switch
Installation & User Instructions
This product complies with the following EC Directives:
Electro-Magnetic Compatibility Directive.
(EMC) (2004/108/EC)
Low Voltage Directive.
(LVD) (2006/95/EC)
Index
Installation
Product specification |
3 |
Installation |
4 |
Wiring |
5-6 |
User |
|
Your timeswitch |
7 |
Programming the unit |
7-8 |
Setting the clock |
8 |
Using the timeswitch |
9 |
Contact details |
12 |
<![endif]>INDEX
2
Installation Instructions
Please Note:
This product should only be installed by a qualified electrician or competent heating installer, and should be in accordance with the current edition of the IEEE wiring regulations.
Product specification
Specification
Power supply |
230 ± 15% Vac, 50/60Hz |
|
|
Switch action |
1 x SPST, type 1B |
|
|
Switch rating |
Max 264 Vac, 50/60Hz, 3(1)A |
|
|
Timing accuracy |
± 1 min/month |
|
|
Enclosure rating |
IP30 |
|
|
Max. ambient temperature |
55°C |
|
|
Dimensions, mm (W, H, D) |
102 x 210 x 60 |
|
|
Design standard |
EN 60730-2-7 |
|
|
Construction |
Class 1 |
|
|
Control Pollution Situation |
Degree 2 |
|
|
Rated Impulse Voltage |
2.5kV |
|
|
Ball Pressure Test |
75°C |
|
|
<![endif]>Specification
3
Installation
|
1. |
Unscrew fixings rings from selector switches, move all |
|
|
four tappets to top of dial and remove outer case. |
|
2. |
Slacken the two screws securing the plug-in module |
|
|
to backplate and separate module from backplate by |
|
|
pulling upwards. |
|
3. |
Fix backplate to wall (3 hole fixing). |
|
4. |
Referring to wiring diagrams on pages 5 and 6 make |
|
|
electrical connections as shown (as applicable). |
|
5. |
Secure cables under cable clamp. |
|
6. |
Ensure all dust and debris has been cleared away |
|
|
from the area then plug in timeswitch module and re- |
|
|
tighten the 2 retaining screws - do not overtighten. |
|
7. |
Remove cut out from bottom of outer case as required. |
|
|
Refit outer case and selector switch fixing rings. |
<![if ! IE]> <![endif]>Installation |
|
Check that outer case sits squarely on body and is not |
|
distorted by an uneven wall surface. |
|
|
|
|
|
8. |
Rotate dial clockwise through at least one complete |
|
|
revolution and check that all four tappets are clear of |
|
|
outer case aperture. |
|
9. |
Switch on mains, turn main selector switch to ‘ON’ and |
|
|
light boiler according to manufacturer’s instructions. |
|
|
Operate Heating Switch to check pump/fan. |
|
10. |
Turn main selector switch to ‘TIMED’ and rotate dial |
|
|
clockwise manually through at least one complete |
|
|
revolution to check that each tappet strikes the index |
|
|
wheel cleanly and operates the boiler/pump correctly |
|
|
according to the times set on the dial. |
4