Cooper Power Systems CA625AB Installation Manual

Effective July 2014
Distribution Transformers
Supersedes September 2011
600 A 15/25 kV class DT625 T-body installation and cable preparation instructions
S600-46-2
DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITY
The information, recommendations, descriptions and safety notations in this document are based on Eaton Corporation’s (“Eaton”) experience and judgment and may not cover all contingencies. If further information is required, an Eaton sales office should be consulted. Sale of the product shown in this literature is subject to the terms and conditions outlined in appropriate Eaton selling policies or other contractual agreement between Eaton and the purchaser.
THERE ARE NO UNDERSTANDINGS, AGREEMENTS, WARRANTIES, EXPRESSED OR IMPLIED, INCLUDING WARRANTIES OF FITNESS FOR A PARTICULAR PURPOSE OR MERCHANTABILITY, OTHER THAN THOSE SPECIFICALLY SET OUT IN ANY EXISTING CONTRACT BETWEEN THE PARTIES. ANY SUCH CONTRACT STATES THE ENTIRE OBLIGATION OF EATON. THE CONTENTS OF THIS DOCUMENT SHALL NOT BECOME PART OF OR MODIFY ANY CONTRACT BETWEEN THE PARTIES.
In no event will Eaton be responsible to the purchaser or user in contract, in tort (including negligence), strict liability or other­wise for any special, indirect, incidental or consequential damage or loss whatsoever, including but not limited to damage or loss of use of equipment, plant or power system, cost of capital, loss of power, additional expenses in the use of existing power facilities, or claims against the purchaser or user by its customers resulting from the use of the information, recom­mendations and descriptions contained herein. The information contained in this manual is subject to change without notice.
ii
600 A 15/25 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
Contents
SAFETY INFORMATION
Safety Information .............................................................................iv
PRODUCT INFORMATION
Introduction ...................................................................................1
Acceptance and Initial Inspection...................................................................1
Handling and Storage ............................................................................1
Standards .....................................................................................1
EQUIPMENT REQUIRED
Equipment Required.............................................................................2
TOOLS REQUIRED
Tools Required .................................................................................2
INSTALLATION OF CONNECTORS
Shear Bolt Installation Procedure. ..................................................................2
Compression Connector Procedure .................................................................7
Installation of DT625 T-body ......................................................................10
COMPLETING T-BODY TERMINATION
Installation of Mating Product ....................................................................11
600 A 15/25 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
iii
!
SAFETY
FOR LIFE
Eaton’s Cooper Power Systems products meet or exceed all applicable industry standards relating to product safety. We actively promote safe practices in the use and maintenance of our products through our service literature, instructional training programs, and the continuous efforts of all Eaton’s Cooper Power Systems employees involved in product design, manufacture, marketing, and service.
We strongly urge that you always follow all locally approved safety procedures and safety instructions when working around high voltage lines and equipment, and support our “Safety For Life” mission.
Safety for life
!
SAFETY
FOR LIFE
Safety information
The instructions in this manual are not intended as a substitute for proper training or adequate experience in the safe operation of the equipment described. Only competent technicians who are familiar with this equipment should install, operate, and service it.
A competent technician has these qualifications:
• Is thoroughly familiar with these instructions.
• Is trained in industry-accepted high and low-voltage safe operating practices and procedures.
• Is trained and authorized to energize, de-energize, clear, and ground power distribution equipment.
• Is trained in the care and use of protective equipment such as arc flash clothing, safety glasses, face shield, hard hat, rubber gloves, clampstick, hotstick, etc.
Following is important safety information. For safe installation and operation of this equipment, be sure to read and understand all cautions and warnings.
Hazard Statement Definitions
This manual may contain four types of hazard statements:
DANGER
Indicates an imminently hazardous situation which, if not avoided, will result in death or serious injury.
Safety instructions
Following are general caution and warning statements that apply to this equipment. Additional statements, related to specific tasks and procedures, are located throughout the manual.
DANGER
Hazardous voltage. Contact with hazardous voltage will cause death or severe personal injury. Follow all locally approved safety procedures when working around high- and low-voltage lines and equipment.
G103.3
WARNING
Before installing, operating, maintaining, or testing this equipment, carefully read and understand the contents of this manual. Improper operation, handling or maintenance can result in death, severe personal injury, and equipment damage.
G101.0
WARNING
This equipment is not intended to protect human life. Follow all locally approved procedures and safety practices when installing or operating this equipment. Failure to comply can result in death, severe personal injury and equipment damage.
G102.1
WARNING
Indicates a potentially hazardous situation which, if not avoided, could result in death or serious injury.
CAUTION
Indicates a potentially hazardous situation which, if not avoided, may result in minor or moderate injury.
CAUTION: Indicates a potentially hazardous situation which, if not avoided, may result in equipment damage only.
iv
600 A 15/25 kV Class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
Power distribution and transmission equipment must be properly selected for the intended application. It must be installed and serviced by competent personnel who have been trained and understand proper safety procedures. These instructions are written for such personnel and are not a substitute for adequate training and experience in safety procedures. Failure to properly select, install or maintain power distribution and transmission equipment can result in death, severe personal injury, and equipment damage.
WARNING
G122.3
DANGER
All associated apparatus must be de-energized during any hands-on installation or maintenance. Failure to comply will result in death, severe personal injury and equipment damage.
WARNING
The 600 A DT625 T-body is designed to be operated in accordance with normal safe operating procedures. These instructions are not intended to supersede or replace existing safety and operating procedures. The elbow connector should be installed and serviced only by personnel familiar with good safety practices and the handling of high-voltage electrical equipment.
WARNING
Optional Capacitive Test Point Operating Instructions: Use only voltage indicating instruments specifically designed for test points. Use of conventional voltage sensing devices may provide false “No Voltage” indications.
The test point must be dry and free of contaminant’s when checking for voltage. After indication is taken: clean, dry, and lubricate the test point cap with silicone grease and assemble to the test point.
The capacitive test point is not sufficiently accurate, nor is it intended for, actual voltage measurements or phasing operations.
Read this manual first
Read and understand the contents of this manual and follow all locally approved procedures and safety practices before installing or operating this equipment
Additional information
These instructions cannot cover all details or variations in the equipment, procedures, or process described nor provide directions for meeting every possible contingency during installation, operation, or maintenance. When additional information is desired to satisfy a problem not covered sufficiently for the user’s purpose, please contact your Eaton’s Cooper Power Systems sales representative.
Acceptance and initial inspection
Each deadbreak connector is completely inspected and tested at the factory. It is in good condition when accepted by the carrier for shipment. Upon receipt of a deadbreak connector, inspect it thoroughly for damage and loss of parts incurred during shipment. If damage or loss is discovered, file a claim with the carrier immediately.
Handling and storage
If the deadbreak connector is to be stored for an appreciable time before installation, provide a clean, dry storage area.
Quality standards
ISO 9001-Certified Quality Management System
A reading of no voltage from the test point should not be the only indication of a de-energized circuit obtained before touching the connector. Other procedures can include direct conductor voltage testing or grounding using a live-line tool.
Product information
Introduction
Eaton’s Cooper Power Systems 600 A 15/25 kV Class deadbreak connectors are used to terminate high­voltage underground cable to deadfront apparatus such as transformers, switches, and switchgear. They are fully shielded, submersible, and meet the requirements of the IEEE Std 386™ standard— “Separable Insulated Connector Systems”. Eaton’s Cooper Power Systems 600 A deadbreak connectors are fully interchangeable with all other manufacturers that also certify compliance with the IEEE Std 386™ standard. The DT625 is rated for 900 A when used with all copper current carrying components.
T-body
Existing Bushing
Compression
Mating 600 A
Product
Optional Test
Point
Neutral Wire
Figure 1. Line illustration of typical 15 kV BT-TAP Connector Assembly.
Connector
Cable Adapter
600 A 15/26 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
1
IMPORTANT
Installation Instructions to be used for 600 A, 15 and 25 kV Class DT625 T-body with shear bolt connector. Please see page 6 for installation instructions using a compression connector.
ote:N If concentric neutral cable is not being used,
follow cable preparation directions in shield adapter kit.
Equipment provided
DT625 T-body Kit includes:
T-body
Cable Adapter
Shear Bolt Connector
Silicone Lubricant
Instruction Sheet
Tools required
Torque Wrench
5/16” Hex Wrench for Splice Application
Cable Stripping Tools
5 mm or 8 mm Allen Wrench
Installation of connectors
Shear bolt installation procedure
Prepare the cable
Step 1.
Train cable
Position cable vertically so that it is centered between apparatus bushing and parking pocket, parallel to, and 6” (152 mm) from apparatus frontplate.
Provide adequate cable slack for cable movement between standoff bushing and apparatus bushing.
Support cable as needed to maintain position.
Cut cable to length “A” from centerline of bushing. (Refer to Fig ure 3 and Table 1 for “A” length.
6"
(152 mm)
"A"
(See Table 1)
Bushing
Figure 2. Strip back dimensions.
Cable
Figure 3. Line illustration for cable training.
B
C
D A
2
600 A 15/25 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
Table 1. Shear Bolt Stripback Dimensions
Connector
Code S1 S3 S4
Allen Wrench (mm) 5 8 8
Length Variable Measurement Name Tolerance
Centering Ring
with or without in (mm)
A Bushing to Cable (+/-0.25) 2.00
(50.8)
B Jacket (+/-0.25) 12.00
(304.8)
C Insulation Shield (+/-0.125) 9.38
(238.2)
D Conductor (+/-0.125) 2.75
(69.85)
E Cable Adapter Check Maximum 7.25
(184.1)
Table 2. Conductor Size and Type
Compression Connector Shear Bolt Connector Sizing
Concentric or Compressed
AWG or kcmil mm
No Connector 00 3/0 3/0 3/0
#2 35 1 - 11 4/0 4/0 4/0
#1 - 1/0 50 12 250 250 250
1/0 50 2/0 70 13 - - 350
2/0 70 3/0 - 14 350 350 -
3/0 - 4/0 95 15 500 500 500
4/0 95 250 120 16 600 600 600
250 120 300 - 17 - - 700
300 - 350 - 18 700 700 -
350 - 400 185 19 750 750 750
400 185 450 - 20 - 800 800
450 - 500 240 21 - - 900
Compact or Solid
AWG or
2
kcmil mm
Compression Conductor
2
Code
AWG or Kcmil
Concentric Compressed Compact min max
2.00 (50.8)
12.00 (304.8)
9.38 (238.2)
3.38 (85.85)
7.25 (184.1)
2.00 (50.8)
12.00 (304.8)
9.38 (238.2)
4.00 (101.6)
7.25 (184.1)
2
mm Stranded & Compressed
Shear Bolt Conductor Code
Shear Bolt Catalog Number
95 150 S1 CDT630SB150
185 300 S3 CDT630SB300
400 S4 CDT630SB400
600 A 15/26 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
3
Step 2.
Remove concentric neutral wires or jacket
ote:N Care should be taken to not cut or score the
neutral conductors when cutting the cable jacket.
Measure reference length “B” from end of cable. (Refer to Figure 4 and Table 1 to determine variable “B” length.
For jacketed neutral cable, remove jacket to “B”
dimension.
For unjacketed neutral cable, bind neutral wires using
three (3) wraps of tape at “B” dimension.
Pull back concentric neutral wires. Allow enough extra concentric neutral wires to connect to ground after installation and allow movement to insulated standoff bushing.
Bushing
"A"
(See Table 1)
"B"
(See Table 1)
Cable
Step 4.
Put tape marker in place
Measure 1” (25 mm) from end of insulation shield. (Refer to Figure 5.)
Wrap two turns of tape to serve as marker for cable adapter location.
Tape Marker
1"
(25 mm)
Insulation Shield
Insulation
"C"
(See Table 1)
Figure 5. Line illustration of cable stripback.
Step 5.
Remove conductor insulation
ote:N Do not pencil cable.
Remove insulation exposing bare conductor to length of “D”. (Refer to Figure 6 and Table 1 to determine variable “D” length.)
ote:N Do not unwind conductor strands.
Concentric Neutral
Wires
Figure 4. Line illustration of removing concentric neutral wires.
Step 3.
Remove insulation shield
Remove insulation shield length “C” from end of cable. (Refer to Figure 5 and Table 1 to determine variable “C” length.)
ote:N Do not cut or nick insulation.
"D"
(See Table 1)
Tape Marker
Insulation
Bare Conductor
Figure 6. Line illustration of bare conductor length.
Step 6.
Bevel insulation
Remove sharp edge of insulation by beveling at a 45° angle for approximately .25” (6 mm). (Refer to Figure 7.)
Bevel
Insulation
.25"
(6 mm)
Figure 7. Line illustration of insulation bevel.
4
600 A 15/25 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
Step 7.
Clean insulation
ote:N Do not apply solvent directly to cable.
Clean insulation thoroughly with solvent dampened rag, wiping from conductor end toward insulation shield. (Refer to Figure 8.)
Ensure that all traces of conductive residue are re moved.
Wipe Insulation
Wiping Direction
Figure 8. Line illustration of insulation cleaning.
Straight
Insulation
Straight
Cable
Insulation
Shield
Tape
Marker
Cable
Not Straight
Major OD flared out
bulge
Not Straight
Step 8.
Lubricate and install cable adapter
Lubricate exposed cable insulation.
Lubricate inside of cable adapter.
Slide small end of cable adapter over cable using twisting motion until small end is flush with tape marker. (Refer to Figure 9.)
After sliding the cable adapter into position make sure that no bulge is present (see Figure 10).
Lubricate Insulation
Tape Marker
Lubricate
Cable Adapter
Figure 9. Line illustration of insulation cable adapter.
WARNING
Equipment Damage/Personal Injury. Improperly positioned cable adapter may result in equipment damage or personal injury.
Correct Positioning
Incorrec t Posit ioning
Figure 10. Cross sectional view of cable adapter positioning.
Bolt 2
Bolt 3
Start with Bolt 1
Bolt 1
Figure 11. Mechanical lug tightening sequence.
600 A 15/26 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
5
Step 9.
Install shear bolt connector
ote:N Refer to the separate installation instructions
supplied with the shear bolt connector.
If the lug is supplied with centering sleeves, check the chart supplied with the lug and determine if a sleeve is required and what the correct color would be.
Wire brush conductor (aluminum only).
Immediately insert the conductor completely into the barrel of the lug and rotate connector to distribute inhibitor.
Align flats of connector and apparatus bushing for minimum conductor strain.
ote:N Connector must be fully seated on cable conductor.
With an Allen hex key as specified in Table 1 screw in bolt No. 1 until it breaks off smoothly. Proceed with bolt No. 2 in a similar way. If the lug has more than two (2) bolts, continue with bolt No. 3 and bolt No. 4, (not shown in Figure 11). See Figure 11 for tightening sequences.
Once all the bolts have broken off, smooth any rough edges with a file and install the covering caps. Carefully clean off any filings.
Wipe excess inhibitor from connector and adapter surfaces.
Step 10.
Check di men sions
Check length from end of com pres sion con nec tor to top of cable adapter.
Length should be no longer than “E” dimension. (Re fer to Fig ure 12 and Table 1.)
Install BOL-T T-body with mating parts
Step 11.
Install DT625 T-body
Clean and lubricate outside of cable adapter with lubricant supplied.
Clean and lubricate inside of T-body with lubricant sup­plied.
ote:N If test point T-body is used, insure test point is
opposite front plate side of T-body.
Without moving the cable adapter, slide T-body onto cable adapter until compression connector eye is centered in 600 A interfaces. (Refer to Figure 13.)
ote:N The end of the cable adapter must line up with
the top edge of the tape marker after T-body assembly. Refer to Figure 10.
Remove tape marker from cable.
600 A Interfaces
Test Point on Accessible Side
T-body
Apparatus Bushing
Lubricate
Cable Adapter
Tape Marker
Concent ric Neutral Wires
"E"
See Table 1
Tape Marker
Shear Bolt Connector
Cable Adapter
Concent ric Neutral Wires
Figure 12. Line illustration for dimensional check.
6
600 A 15/25 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
Figure 13. Line illustration of BOL-T T-body installation.
Go to Step 12, page 11 to complete T-body termination.
Compression connector procedure
Equipment provided
DT625 T-body Kit includes:
T-body
Cable Adapter
Silicone Lubricant
Instruction Sheet
Tools required
Torque Wrench
5/16” Hex Wrench for Splice Application
Cable Stripping Tools
Cable preparation
Step 1
Train cable
Position cable vertically so that it is centered between apparatus bushing and parking pocket, parallel to and 6” (152 mm) from apparatus frontplate.
Provide adequate cable slack for cable movement between standoff bushing and apparatus bushing.
Support cable as needed to maintain position.
Cut cable 1.75” (45 mm) from centerline of bushing. Refer to Figure 14.
Step 2
Remove concentric neutral wires or jacket
ote:N Care should be taken to not cut or score the
neutral conductors when cutting the cable jacket.
Measure 12.75” (324 mm) from end of cable. Refer to Figure 15.
• For jacketed neutral cable, remove jacket to 12.75” dimension.
For unjacketed neutral cable, bind neutral wires using
three (3) wraps of tape at 12.75” dimension.
Pull back concentric neutral wires. Allow enough extra concentric neutral wires to connect to ground after installation and allow movement to insulated standoff bushing.
Bushing
1.75” ± .25”
(45 mm ± 7 mm)
12.75” ± .25”
(324 mm ± 7 mm)
Cable
Concent ric Neutral Wires
Figure 15. Line illustration of removing concentric neutral wires.
6”
(152 mm)
1.75” ± .25”
(45 mm ± 7 mm)
Existing Bushing
Cable
Figure 14. Line illustration for cable training.
600 A 15/26 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
Step 3
Remove insulation shield
Remove insulation shield length 9.75” (248 mm) from end of cable. Refer to Figure 16.
Do not cut or nick insulation.
Step 4
Put tape marker in place
Measure 1” (25 mm) from end of insulation shield. Refer to Figure 16.
Wrap two turns of tape to serve as marker for cable adapter location.
Tape Marker
1"
(25 mm)
Insulation Shield
Insulation
9.75"
(248 mm ± 3 mm)
Figure 16. Line illustration of cable stripback.
7
Step 5
Remove conductor insulation
ote:N Do not pencil cable.
Remove insulation exposing bare conductor to length of
4.38” (111 mm). Refer to Figure 17.
ote:N Do not unwind conductor strands.
4.38" ± .13"
(111 mm ± 3 mm)
Step 7.
Clean insulation
ote:N Do not apply solvent directly to cable.
Clean insulation thoroughly with solvent dampened rag, wiping from conductor end toward insulation shield. Refer to Figure 19.
Ensure that all traces of conductive residue are re moved.
Wipe Insulation
Tape Marker
Insulation
Bare Conductor
Figure 17. Line illustration of bare conductor length.
Step 6.
Bevel insulation
Remove sharp edge of insulation by beveling at a 45° angle for approximately .25” (6 mm). Refer to Figure 18.
Bevel
Insulation
.25"
(6 mm)
Figure 18. Line illustration of insulation bevel.
Wiping Direction
Figure 19. Line illustration of insulation cleaning.
Step 8.
Lubricate and install cable adapter
Lubricate exposed cable insulation.
Lubricate inside of cable adapter.
Slide small end of cable adapter over cable using twisting motion until small end is flush with tape marker. Refer to Figure 20.
After sliding the cable adapter into position make sure that no bulge is present. Refer to Figure 21.
Lubricate Insulation
Tape Marker
Cable Adapter
Lubricate
Figure 20. Line illustration of insulation cable adapter.
WARNING
Equipment Damage/Personal Injury. Improperly positioned cable adapter may result in equipment damage or personal injury.
8
600 A 15/25 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
Correct Positioning
Straight
Cable Insulation
Straight
Cable Insulation Shield
Tape Marker
Incorrec t Posit ioning
Not Straight
Not Straight
Major OD flared out
bulge
Step 9.
Install compression connector
ote:N Refer to the chart supplied with the crimp
connector for tool and die to be used.
Wire brush conductor (aluminum only).
Remove protective cap from compression connector.
Insert conductor completely into compression connector and rotate connector to distribute inhibitor.
ote:N Connector must be fully seated on cable conductor.
Align flats of connector and apparatus bushing for minimum conductor strain.
Make first crimp 1/2” (13 mm) below shoulder of compression connector. (Refer to Figure 22).
Rotate each successive crimp 90° on compression connector and allow 1/8” (3 mm) between crimps.
Wipe excess inhibitor from connector and adapter surfaces.
Bushing
ShoulderTo o l
Figure 21. Cross sectional view of cable adapter positioning.
Crimping Area
Cable Adapter
Figure 22. Line illustration of crimping area.
600 A 15/26 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
9
Step 10.
Check di men sions
Check length from end of com pres sion con nec tor to top of cable adapter.
Length should be be tween 6.50-7.25” (165 - 184 mm). Re fer to Fig ure 23.
6.50-7.25"
(165-184 mm)
Compression Connector
Cable Adapter
Install BOL-T T-body with mating parts
Step 11.
Install DT625 T-body
Clean and lubricate outside of cable adapter with lubricant supplied.
Clean and lubricate inside of T-body with lubricant supplied.
ote:N If test point T-body is used, insure test point is
opposite front plate side of T-body.
Without moving the cable adapter, slide T-body onto cable adapter until compression connector eye is centered in 600 A interfaces. Refer to Figure 24.
ote:N The end of the cable adapter must line up with
the top edge of the tape marker after T-body assembly. Refer to Figure 21.
Remove tape marker from cable.
Tape Marker
Concent ric Neutral Wires
Figure 23. Line illustration for dimensional check.
600 A Interfaces
Test Point on Accessible Side
T-body
Apparatus Bushing
Lubricate
Cable Adapter
Tape Marker
Concent ric Neutral Wires
Figure 24. Line illustration of BOL-T T-body installation.
Go to Step 12, page 11 to complete T-body termination.
10
600 A 15/25 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
Competing T-body termination
Step 12.
Install mating product and drain wire
Install mating product and drain wire according to the instruction sheet supplied with the mating product.
Figure 25. Typical mating products (from left to right) apparatus bushing, insulated plug, connector plug, T-OP II LRTP, and BT-TAP BLRTP.
600 A 15/26 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com
11
!
SAFETY
FOR LIFE
Eaton
1000 Eaton Boulevard Cleveland, OH 44122 United States Eaton.com
Eaton’s Cooper Power Systems Business
2300 Badger Drive Waukesha, WI 53188 cooperpower.com
© 2014 Eaton All Rights Reserved Printed in USA Publication No. S600462 Rev 3 (Replaces S600462 Rev 2)
Eaton, Cooper Power Systems, T-OP, BOL-T, and BT-TAP are valuable trademarks of Eaton, in the U.S. and other countries. You are not permitted to use these trademarks without the prior written consent of Eaton. IEEE Std 386™ standard is a trademark of the Institute of Electrical and Electronics Engineers, Inc., (IEEE). This publication/ product is not endorsed or approved by the IEEE.
For Eaton’s Cooper Power Systems deadbreak connector product information call 1-877-277-4636 or visit: www.cooperpower.com.
Loading...