WARNING
IMPORTANT SAFETY INFORMATION - READ, FOLLOW, AND SAVE ALL SAFETY AND INSTALLATION

Before starting any work ensure that all sources of power are turned OFF. All work must meet local/national electrical codes and be performed by a certified electrician.

Follow product label information and instructions before installing fixture. Retain installation instructions for future reference.

of fire, electrical shock,
Risk
cuts and or other casualty hazards. This product must be installed in accordance with the applicable installation code by a person familiar with the construction and operation of the product and the hazards involved. Cooper Lighting Solutions assumes no responsibility for claims brought about by improper or careless installation or handling of this product.

Risk of burn. Disconnect power and allow fixture to cool before changing bulb or handling fixture.

Replace lamp only with correct wattage and type of lamp marked on label. DO NOT exceed the maximum wattage listed on the fixture label.

To prevent wiring damage or abrasion, do not expose wiring to edges of sheet metal or any sharp objects.
INSTRUCTIONS.
NOTICE
If supply wires are located within 3 inches of driver/ballast, use wire rated for at least 90°C (194°F). Not e: Not all option available. Please consult your Cooper Lighting Solutions representative for availability. Specification and
dimension subject to change without notice.
2
ADE141262 www.cooperlighting.com
Installation Instruc tions – T-Bar
INSTALLATION
Standard Interface (Connection at Ceiling) Aircraft Cable Mounting AC-_-T1
Mount Details
Plenum Rated Tie
Flex Conduit & Connector (By Others)
4” Square Outlet Box 1 1/2” Deep (By Others)
NPT Lock Nut
Tied Off to Structure(By Others)
1/2” NPT Fitting
T-Bar Clip
Strap (By Others)
Cover Plate (By Others)
1/4-20 Bolt
J-Box Clip
T-Bar
1/4”-20 Stud
10. Feed power cord through canopy and J-Box, then install metal strain relief.
11. Attach wires ensuring all connections are properly matched.
12. Cover J-Box using appropriate cover plate.
Figure 2.
Power
5” Canopy
Aircraft Cable Coupler
Aircraft Cable
Snap Bushing
Power Cord
ote:N T-Bar Clip Must be Tied Off to Structure
Figure 1.
Power
Fixture Installation Sequence
1. Layout mounting locations. (Figure 1.)
2. Ensure that power feed is at the UL end of the fixture. ote:N Power feed: to be installed to local/national
electrical codes by a Certified Electrician.
3. Install T-bar clip to T-bar and tie back to structure.
4. Place canopy and caddy clip stud and attach aircraft
cable.
5. At the end of the 4x4 square outlet box break KO in
corner and secure 1/2” NPT fitting to box.
6. Clip J-Box Clip to T-Bar.
7. Secure J-Box to J-Box Clip using 1/4”-20 bolt.
8. Secure snap bushing to canopy and align up to NPT
fitting.
9. Install solid or flexible conduit from power source to
1/2” cable fitting and secure to tie wire using Plenum Rated Tie Strap.
Figure 3.
Figure 5.
Non-Power
Options
9/16” T-Bar (T9) Slot T-Bar (TS) This Option Provides a T-Bar Clip for 9/16” Wide T-Bar.
Figure 4.
Curly Cord (AK): SJT - 18/3 or SJT - 18/4 Curly Cord
Figure 6. Figure 7.
2’’ Canopy
Non-Power
This Option Provides a T-Bar Clip for 9/16”x 5/16” Slotted T-Bar.
Installation
ADE141262 www.cooperlighting.com
Instructions – T-Bar
3
Installation Instruc tions – T-Bar
Aircraft Cables Sit in .368’’ from the End of the Fixture
Mounting Points Equal Fixture Lengths 4’, 8’ or 12’
Power Feed
First Section
Figure 8.
Mounts Locations
** Tegular Ceiling Interface (Connection at Ceiling) Aircraft Cable Mounting AC-_-T1
Mount Details
Plenum Rated Tie
Flex Conduit & Connector (By Others)
4” Square Outlet Box 1 1/2” Deep (By Others)
NPT Lock Nut
Tied Off to Structure (By Others)
1/2” NPT Fitting
T-Bar Clip
1/4” Washer Used Only in Tegular* Ceiling Tile Application
Aircraft Cable Coupler
Aircraft Cable
Strap (By Others)
Cover Plate (By Others)
1/4-20 Bolt
J-Box Clip
T-Bar
1/4”-20 Stud
1/4”-20 Nut Used Only in Deep Tegular* Ceiling Tile Application
5” Canopy
Snap Bushing
Power Cord
Mounting Points Equal Fixture Lengths 4’, 8’ or 12’
***Consecutive Section
***For Continuous Rows See Joining Sheet
ote:N For Tegular Ceiling Tile applications use (2) 1/4”
washers (supplied) for spacing between the canopy and the ceiling tile.
ote:N For Deep Tegular Ceiling Tile applications use 1/4”-20
nut (supplied) for spacing between the canopy and the ceiling.
5. At the end of the 4x4 square outlet box break KO in corner and secure 1/2” NPT fitting to box.
6. Clip J-Box Clip to T-Bar.
7. Secure J-Box to J-Box Clip using 1/4”-20 bolt.
8. Secure snap bushing to canopy and align up to NPT fitting.
9. Install solid or flexible conduit from power source to 1/2” cable fitting and secure to tie wire using Plenum Rated Tie Strap.
10. Feed power cord through canopy and J-Box, then install metal strain relief.
11. Attach wires ensuring all connections are properly matched.
12. Cover J-Box using appropriate cover plate.
** All tegular installs must consult factory. Depth of tegular tile will dictate length of 1/4”-20 stud and a 1/4-20” nut may be required. Depth of tegular tile is required upon sign-off.
Tegular Depth: ________________________
ote:N T-Bar Clip Must be Tied Off to Structure
Figure 9.
Power
Fixture Installation Sequence
1. Layout mounting locations. (Figure 9.)
2. Ensure that power feed is at the UL end of the fixture. ote:N Power feed: to be installed to local/national
electrical codes by a Certified Electrician.
3. Install T-bar clip to T-bar and tie back to structure.
4. Place canopy and caddy clip stud and attach aircraft
cable.
Installation Instructions – T-Bar
4
ADE141262
Figure 10.
www.cooperlighting.com
Power Tegular**
Figure 11.
Non-Power Tegular**
Installation Instruc tions – T-Bar
Curly Cord (AK): SJT - 18/3 or SJT - 18/4 Curly Cord
Figure 12.
Figure 14.
Power Deep Tegular**
2” Canopy
Non-Power
Figure 13.
1/4”-20 Nut Used Only in Deep Tegular Ceiling Tile applications
Non-Power Deep Tegular**
1/4” Washer Used Only in Tegular Ceiling Tile application
Figure 15.
Options
9/16” T-Bar (T9) Slot T-Bar (TS) This Option Provides a T-Bar Clip for 9/16” Wide T-Bar.
Figure 16. Figure 17.
****Standard Stud Lengths are 3/4”. If Deep Tegular Tile Installation is Required, A 1-1/2” Stud will be Provided.
Aircraft Cables Sit in .368’’ from the End of the Fixture
Mounting Points Equal Fixture Lengths 4’, 8’ or 12’
Power Feed
First Section
***For Continuous Rows See Joining Sheet
Mounting Points Equal Fixture Lengths 4’, 8’ or 12’
***Consecutive Section
This Option Provides a T-Bar Clip for 9/16”x 5/16” Slotted T-Bar.