Traditional coaxial trunk and distribution cables require considerable attention to the preparation of the cable end
for proper connectorization. Critical to that end preparation is the proper removal of dielectric and bonding compound from the conductors.
The normal process for this requires the craftsman to first core the cable and then clean the center conductor in a
second step. CommScope’s new P3
conductor cleaning step by enabling a clean coring process in which the center conductor is cleaned of dielectric
and bonding compound during the coring process.
These cables meet and exceed all ANSI/SCTE, EN50117, IEC and Cenelec testing methods for trunk, feeder, and
distribution cables.
®
with ACT® and QR® with ACT® cables virtually eliminate the center
Below is an example of a
traditional P3
®
Cable:
Residual dielectric and bonding compound on conductor after coring
Below is an example of
®
with ACT®:
P3
Conductor clean of dielectric and
bonding compounds after coring
1.2 Introduction
P3 Design Details and Advantages
Advanced Coring Technology
®
P3® with ACT® and QR® with ACT
cables were developed to address a question that has been clearly
®
stated and often repeated by the craftsmen, engineers, and technical operations managers of the
broadband industry.
Why must a hardline cable be so difficult and problematic to properly core and prep?
Before the introduction of ACT cables, craftsmen struggled with the cleaning of the center conductor. To remove
the remaining dielectric and bonding compound craftsmen have:
ACT cables not only eliminate all of these issues, but also significantly reduce the time needed to core and prep
the cable end and make connectorization easier. This is accomplished through the development of an advanced
technology bonding agent coupled with CommScope’s consistent manufacturing capabilities. This patent pending
formulation leverages the shearing action produced by every coring tool enabling most tools to produce a one
pass coring operation leaving the conductors clean of dielectric and bonding compounds. Tools and craft skill
may affect the clean coring capabilities.
P3 with ACT and QR with ACT cables are expected to provide system operators with a reduction in truck rolls
and labor cost for trunk and distribution plant. This reduction of truck rolls and labor cost is achieved through
consistent clean coring. Ensuring that this critical step in the connectorization process is done right the first time
every time eliminating many of the issues associated with poor connectorization, thus reducing the need to return
to troubled locations to make corrective changes.
Introduction 1.3
ACT® - Advanced Coring Technology
P3® - Traditional Reliability
P3 is the standard by which all coaxial cables are measured.
The P3 center conductor is copper-clad aluminum for superior RF transmission.
The P3 dielectric is a closed-cell polyethylene that is compressed during the swaging
process. Compression provides superior bending. The closed-cell nature of the dielectric permits
an impressively high velocity of propagation of 87%.
The P3 shield, a solid and robust aluminum construction, provides 100% RF protection and
solid mechanical performance.
Migra-Heal
before moisture can seep in and cause corrosion.
P3 and Service –
the two names
associated with
®
, CommScope’s special underjacket compound, helps fill in jacket damage
The P3 jacket is a tough medium-density polyethylene
compound designed to resist the effects of sun, moisture
most often
and temperature extremes. CableGuard
resistant jacket, is also available.
CommScope
Steel armor is available for added protection.
®
, a unique crush
1.4 Introduction
QR Design Details and Advantages
QR® - Superior Design and Construction
QR’s patented design combines several elements to achieve its unparalleled combination of superior
performance in a smaller, less expensive cable.
The QR center conductor is copper-clad aluminum for superior RF transmission and is
generally larger than the conductors found in competitive cable of similar outer diameter.
The QR dielectric is a closed-cell polyethylene that is compressed during the swaging process. Compression allows the dielectric to actively press against the shield and help heal small
dents. The closed-cell nature of the dielectric permits an impressively high velocity of propagation of 88%.
The QR shield is formed through a unique, high efficiency
process where a precision tape is continuously roll-formed
around the core and is then welded by RF induction. This results
in a contaminant-free seam which is stronger than the
surrounding material. We verify seam integrity with a core and
cone test, where a cored sample is flared to a diameter well
beyond even the most extreme installed usage.
conductor combine
best performing
Thin shield,
compressed
dielectric and
a larger center
to make QR the
coax available
Migra-Heal
helps fill in jacket damage before moisture can seep in and cause corrosion.
The QR jacket is a tough medium-density polyethylene compound designed to resist the
effects of sun, moisture and temperature extremes.
Double jacketing, in which two independent jackets are separated by polypropylene tape, is
also available.
Steel armor is available for added protection.
®
, CommScope’s special underjacket compound,
anywhere
Introduction 1.5
MC2 Design Details and Advantages
®
2
MC
- Supporting Legacy Plant
MC2 is offered to sustain plants designed and built around this cable.
2
The MC
The MC
center conductor is copper clad aluminum
2
dielectric is an air disk structure, often referred to as bamboo cable, it provides for
low attenuation values.
The MC
Migra-Heal
2
shield is a roll formed aluminum tape welded by RF induction.
®
, CommScope’s special under jacket compound, helps fill in jacket damage
before moisture can seep in and cause corrosion.
The MC
2
jacket is a tough medium-density polyethylene compound.
Steel armor is available for added protection.
2.1 Handling and Testing
Inspection
Inspecting and Unloading CommScope Cables
Trouble-free unloading begins with letting your CommScope Customer Service Representative know of any
special packaging or delivery requirements (no shipping dock available, call before delivery, etc.). CommScope
will make every reasonable effort to comply with your shipping needs.
When the shipment arrives, inspect every reel and pallet of material for damage as it is unloaded. Suspect cable
should be set aside for a more detailed inspection before the shipping documents are signed.
Damage can occur during the unloading process. Coaxial cable can be damaged
by dropping the reels or pallets, or improper handling of reels with a forklift.
CommScope
makes every ef-
fort to assure
Stacked cable must be carefully unstacked to prevent cable damage and possible
injury. CommScope drivers are experienced in handling and unstacking the cable
without injury or damage. A Cargomaster crane is useful in unstacking and
unloading cable with or without a dock.
Common carriers are only required to move the cable to the back of the truck for
unloading. If a common carrier driver cannot unstack the cable, the driver should
be instructed to return to the shipping terminal where equipment exists to unstack
the cable. The cable can be reloaded onto the truck on rolling edge.
If any cable damage is visible or suspected and if it is decided to accept the shipment, note the damage and the
reel number on ALL copies of the bill of lading.
If the damage is too extensive to accept the shipment, advise the carrier’s driver that the shipment is being refused
because of the damage. Immediately notify CommScope’s Customer Service Department so that arrangements
can be made for a replacement shipment.
that QR and P3
cables arrive in
the same 100%
ready-to-install
condition as
when they left
the factory.
Handling and Testing 2.2
Unloading
Unloading CommScope Cable
Unloading at a Dock
Use a pallet jack or forklift to remove all cable on pallets.
Remove any blocking materials for the individual rows of
cable and roll the reels onto the dock. If the back of the
trailer and dock are not at the same height, use an
appropriate loading ramp to compensate for the
difference.
Unloading without a Dock
If you use a ramp, it should be strong enough to support
the weight of the unloading personnel and the heaviest
cable reels. The ramp should have raised sides to prevent
the cable reels from rolling off the sides of the ramp.
The ramp should be long enough to allow control of the
momentum of the cable as it rolls down the ramp. A pulley
system connected to the sides of the truck and to a shaft
passing through the center of the reels can help control
the momentum of the rolling reels. With this method, two
workers can usually control movement of the heaviest reel.
If you use a Cargomaster crane, unstack and move the
cable to the ground at the rear of the truck.
DO NOT drop reels off the back of the truck
onto a stack of tires, onto the ground or any
other surface. The impact may injure personnel and
damage the cable. Always use ample personnel to safely
unload shipments of cable.
Shipping weights lbs/kft (kg/km)
QR 320 JCA, JCASS 63 (94)
QR 540 JCA, JCASS 120 (179)
QR 715 JCA, JCASS 205 (305)
QR 860 JCA, JCASS 291 (433)
P3 500 CA 97 (143)
P3 500 JCA 120 (179)
P3 500 JCASS 123 (183)
P3 625 CA 158 (235)
P3 625 JCA 182 (271)
P3 625 JCASS 185 (275)
P3 750 CA 237 (353)
P3 750 JCA 272 (405)
P3 750 JCASS 275 (409)
P3 875 CA 295 (439)
P3 875 JCA 336 (500)
P3 875 JCASS 342 (509)
MO500CB 78 (116)
MO500CU 106 (158)
MO500CJ 111 (165)
MO650CB 112 (167)
MO650CU 147 (219)
MO650CJ 153 (228)
MO750CB 164 (244)
MO750CU 206 (307)
MO750CJ 213 (317)
2.3 Handling and Testing
Storing and Stacking Reels
Storage and Stacking CommScope Reels
CommScope cable can be stored indoors or outdoors, and the cable may be stacked on flange or stored upright
on the rolling edge. Use a forklift or some type of overhead hoist to stack cable.
When cable is stored outside, the ground should be somewhat level and have good drainage to reduce the
possibility of deterioration of the reel flanges. CommScope’s reel recycling program only accepts reels in good
condition.
Reels which are stored on the rolling edge should be
aligned flange to flange to prevent possible damage to
the cable once the protective cover has been removed.
Stacking CommScope Cable
When CommScope cable is moved, shipped, or stored,
use this table to ensure that maximum stacking heights
are not exceeded. Consideration must be given to the
maximum height as well as the total weight of the stack.
To allow the use of a pallet jack or forklift, place boards
between each layer and a pallet on the ground under
the bottom reel. Exceeding the recommended storage
and loading heights may damage the cable due to
flange deflection.
QR Cable
Storage Height Loading Height
QR 540 5 Reels 3 Reels
QR 715 5 Reels 3 Reels
QR 860 5 Reels 3 Reels
P3 Cable
Storage Height Loading Height
P3 500 6 Reels 4 Reels
P3 625 6 Reels 4 Reels
P3 750 5 Reels 3 Reels
P3 875 5 Reels 3 Reels
MC
Storage Height Loading Height
MO500 6 Reels 4 Reels
MO650 6 Reels 4 Reels
MO750 5 Reels 3 Reels
Maximum Maximum
Maximum Maximum
Maximum Maximum
2
Cable
Handling and Testing 2.4
Storing and Stacking Reels
Testing CommScope Cables
While testing reels of CommScope cables after delivery is not required, testing prior to, during and after
construction will identify any degradation in the performance of the cable caused during installation.
There are three phases in CommScope cable testing:
1) Visual inspection for shipping damage
2) Pre-installation testing, which occurs immediately after delivery of the cable, and
3) Post-installation/final acceptance testing, which occurs just prior to activation.
Post-installation testing is accomplished as part of system activation and as proof of performance.
Broadband frequency response (sweep) testing is included as a part of the activation process.
Pre-Installation Testing
Pre-installation testing of CommScope cable typically consists of SRL and
impedance/TDR (Time Domain Reflectometer) tests, with the TDR test being
the quickest way to discover cable damage. These pre-installation checks can
be jointly conducted by the system operator and the construction group in
order to preclude future difficulties if a cable is damaged during construction.
CommScope cable is
extensively tested
Every reel of
prior to shipment
for attenuation,
Structural Return
Attenuation (insertion loss) tests are seldom conducted after shipment, but can
be easily performed during pre-installation testing. Testing for attenuation by
conventional methods is extremely difficult after installation due to the physical
placement of the cable over substantial distances.
Loss (SRL) and
impedance with
certified test
reports available
at your request
Post Installation - Final Acceptance Testing
SRL and TDR tests can be performed after installation if required. The results should be compared to the
pre-installation test.
2.5 Handling and Testing
Impedance/TDR Testing
Impedance/TDR (Time Domain Reflectometer) Testing
Impedance testing using a TDR is a quick and straightforward method for finding the distance from the test point
to any fault (shown as an impedance mismatch) in the cable.
Impedance tests should be made from both ends of the cable to ensure finding the correct distance to fault. The
correct velocity of propagation (Vp) for the test is essential - an incorrect Vp will cause a proportional
measurement error in the distance to the fault. The Vp for QR cable is 88%. The Vp for P3 cable is 87%.
Impedance tests should be done per the standards set forth in SCTE-TP-006. Impedance testing will require a
time domain reflectometer (TDR). Methods of operation will vary for each TDR; however, these are general
guidelines for using one:
1) Set the velocity of propagation for 88% for QR or 87% for P3,and the impedance reference for
75 ohms.
2) Adjust the display for a sharp, clear baseline, and position the leading edge to a convenient
starting point or graticule.
3) Set the pulse width as recommended by the TDR manufacturer.
4) Attach the test lead (coaxial cable test leads are preferred) to the cable under test.
Connectors should match the impedance of the tested cable.
5) Adjust the display and control settings to show the entire length of the cable. The control settings
can be adjusted to allow precise measurement of the distance to any impedance mismatch.
Operator proficiency and equipment capability are critical factors in making consistent and
precise measurements.
End-to-end impedance tests are very beneficial in an evaluation of post-installation plant
performance. The TDR traces should be kept with the as-built drawings along with the reel
numbers of the installed cable.
Aerial Installation 3.1
Overview
Aerial Installation of CommScope Cable
There are two cable types built specifically for aerial installation:
QR/P3 JCAthe standard construction, available in five sizes for trunk and feeder installation,
to be lashed to a strand or support wire, and
QR/P3 JCAM standard construction with a messenger extruded in place in a figure-8 design.
The two preferred methods for installation are the back-pull/stationary reel method and the drive-off/moving reel
method. Circumstances at the construction site and equipment/manpower availability will dictate which
placement method will be used.
The back-pull/stationary reel method is the usual method of cable
placement. The cable is run from the reel up to the strand, pulled by a block that only
travels forward and is held aloft by cable blocks. Cable is then cut and expansion
loops formed - lashing takes place after the cable is pulled.
are particularly
deformation in
QR cables
resistant to
cable geometry
The drive-off/moving reel method may realize some manpower and time
savings in cable placement and lash-up. In it, the cable is attached to the strand and
payed-off a reel moving away from it. The cable is lashed as it is being pulled - cuts
and expansion loops are made during lashing.
due to their
highly flexible
during
installation
construction
Regardless of the installation method, mechanical stress is of great concern during
cable placement. Like other coaxial cables, QR can be damaged by exceeding the maximum allowable pulling
tension or the minimum allowable bending radii. Fortunately, QR’s highly flexible construction permits lower than
normal pull tensions and tighter bends, almost completely eliminating the chance of cable installation
deformation.
Make sure all down guys at corners and dead ends are installed and tensioned prior to
cable placement.
3.2 Aerial Installation
Pulling Tension
Pulling Tension
Pulling tension for CommScope cables are shown in this chart. JCAM cables should be pulled by the messenger,
where the maximum pulling tension is limited by its minimum breaking strength. Cables are available with a .109
in (3mm) messenger rated at 1800 lbs (818 kgf), .188 in (5 mm) messenger rated at 3900 lbs (1769 kgf)
.250 in (6 mm) messenger rated at 6650 lbs (3022 kgf).
or
Cable Max. Pulling Tension
lbs / kgf
QR 320 120 (54.5)
QR 540 220 (100)
QR 715 340 (154)
QR 860 450 (204)
P3 500 300 (136)
P3 625 475 (216)
P3 750 675 (306)
P3 875 875 (397)
MO500 270 (123)
MO650 360 (164)
MO750 500 (227)
NEVER EXCEED THE MAXIMUM PULLING TENSION.
Excessive forces applied to the cable will cause the cable to permanently
elongate. Good construction techniques and proper tension monitoring
equipment are essential. The highly flexible nature of QR cable makes it
very difficult to exceed the maximum pulling tension.
During cable placement, attention should be given to the number and
placement of cable blocks. The amount of sag between the blocks and
the amount of bending at the block affects the pulling tension.
Tail loading is the tension in the cable caused by the mass of the cable
on the reel and reel brakes. Tail loading is controlled by two methods.
It can be minimized by using minimal braking during the pay-off of the
cable from the reel - at times, no braking is preferred. Tail loading can
also be minimized by rotating the reel in the direction of pay-off.
Break-away swivels should be placed on each cable to ensure that the
maximum allowable tension for that specific cable type is not exceeded. The swivel is placed between the cable
puller and pulling grip. A break-away swivel is required for each cable.
QR’s flexible
Dynamometers are used to measure the dynamic tension in the cable. These devices
allow continuous review of the tension and accordingly a realization can be made
of any sudden increase in pulling tension. Sudden increases in pulling tension can
be caused by many factors such as a cable falling from a block or a cable binding
against pole-line hardware.
construction
means less
pulling effort
is required
Aerial Installation 3.3
Bending Radii
Bending Radii
Cables are often routed around corners during cable placement and pulling tension
must be increased to apply adequate force to the cable to bend the cable around the
corner. Tension is directly related to the flexibility of cable - and flexibility is QR’s greatest
strength.
Minimum
Cable Bending Radii
in/cm
QR 320 3 (7.6)
QR 540 4 (10.2)
QR 540 armored 6.5 (16.5)
QR 715 5 (12.7)
QR 715 armored 7.5 (19.1)
QR 860 7 (17.8)
QR 860 armored 9.5 (24.1)
P3 500 standard (jacketed) 6.0 (15.2)
P3 500 bonded (jacketed) 3.5 (8.9)
P3 625 standard (jacketed) 7.0 (17.8)
P3 625 bonded (jacketed) 4.5 (11.4)
P3 750 standard (jacketed) 8.0 (20.3)
P3 750 bonded (jacketed) 6.0 (15.2)
P3 875 standard (jacketed) 9.0 (22.9)
P3 875 bonded (jacketed) 7.0 (17.8)
MO500 6.0 (15.2)
MO650 7.0 (17.8)
MO750 8 (20.3)
CommScope’s specified minimum
bending radius is the static (unloaded)
bending radius of the cable. This is the
minimum radius to which the cable can
be bent without electrically or mechanically degrading the
performance of the cable. Bending the cable in this manner is
usually only done during splicing or final forming. This is also the
radius allowed for storage purposes.
Always review the specifications for the appropriate
bend radii. If you do not exceed the minimum bend
radius nor exceed the maximum
pulling tension, you should have a
successful installation.
The bending radii of cables during the
construction process are controlled by
construction techniques and equipment.
Corner blocks and set-up chutes have
large radii and low friction surfaces that
minimally contribute to the overall
increase in pulling tension.
QR cable’s
shield
construction
permits the
tightest bend
radius in the
industry
3.4 Aerial Installation
Espansion Loops
Expansion Loops
As temperature rises and falls, coaxial cable will expand/contract at almost twice the rate of strand. Expansion
loops allow the cable to move to allow for stress caused by thermal changes and strand creep. They are critical
to cable life. A typical loop will use no more than an extra 2 - 3 inches (5 - 8 cm) of cable.
Loops are formed using mechanical benders or bender boards. CommScope strongly recommends the
use of mechanical benders for consistently-formed loops.
When to place expansion loops
Loops are formed prior to lashing in the back-pull method and during lashing in the
drive-off method. In either case, it is recommended that you keep the bender in place
as the cable is being lashed. Remove the bender only after the cable has been lashed
to the strand.
QR expansion
loops will last
2 - 3 times
longer than
those of
conventional
Where to place expansion loops
Form one expansion loop at each pole, on the input/output of every active device and
at every tap. Form two loops at a pole where the span length exceeds 150 feet
(45 meters), on street/RR crossings and in spans with little to no midspan sag.
If you are running multiple cables, do not bind them together in the same loop.
An expansion loop is supported on the strand by a
strap fitted with a spacer that separates the cable from
the strand. The strap should be no more than
hand-tightened.
The cable must be permitted to move within
the loop or the cable may buckle and fail.
Place the bug nut 4” from the end of the loop and place the spacer and strap on the span side of the loop
behind the bug nut. (See diagram.) Note: the end of the loop is at the end of the loop forming tool.
Pole Side
coaxial cable
Span Side
Aerial Installation 3.5
Forming Expansion Loops
Expansion Loops - Forming
Two different sizes of expansion loops are currently used.
For sizes < 625, use a mechanical bender to form a
12-inch flat bottom loop.
This bender produces a minimum 6” (15 cm) deep
43 in (1.1 m)
11 in (28 cm) radii
6 in (15 cm)
loop with a 12” (30 cm) flat bottom.
12 in (30 cm)
For sizes > 700, use a mechanical bender to form a 15-inch flat bottom loop.
This bender produces a minimum 6” (15 cm)
deep loop with a 15” (38 cm) flat bottom.
If you are installing smaller cables with the larger
sizes, it is recommended that you use the larger
loop on all cables.
50 in (1.27 m)
14.8 in (38 cm) radii
6 in (15 cm)
15 in (38 cm)
Forming the Loop
Attach the mechanical bender to the strand at the appropriate location. Place the cable in the bender and form
the loop according to the manufacturer’s directions. Carefully inspect the cable for any damage due to
misalignment of the bender.
DO NOT REMOVE THE BENDER until after the cable has been lashed at least 50’ (15 meters) or to the next
pole, as tensions imposed during lashing may deform the loop. Once the cable is lashed and the lash wire tied
off, you may remove the bender. Double lashing is recommended for two or more cables.
Attach straps and spacers. Do not overtighten the straps.
3.6 Aerial Installation
Styles of Expansion Loops
Expansion Loops - Various Configurations
These are several examples of common expansion loop configurations.
Straight pole
Mid-span crossover
Angled pole
Aerial Installation 3.7
Styles of Expansion Loops
Expansion Loops - Various Configurations
These are several examples of common expansion loop configurations.
Double dead-end
Line pole dead-end
3.8 Aerial Installation
Back-Pull/Stationary Reel Set-Up
Installation - Back-Pull/Stationery Reel Set-Up
Set-Up Chute Placement
The set-up chute should be positioned on the first pole of the cable route or attached to the strand at the first
pole. Placement of the set-up chute should keep the cable from rubbing on the reel or pole. Either a 45° or 90°
corner block may be used as a set-up chute.
Trailer Set-Up
The trailer should be positioned in-line with the strand and twice the distance of the set-up chute to the ground
from the chute. This prevents the cable from rubbing on the pole or reel or binding on the chute.
If the trailer cannot be positioned there, move the set-up chute and cable trailer to an adjacent pole.
The cable should pay-off the top of the cable reel. The pay-off of the cable from the reel should cause a
downward force at the hitch of the trailer.
Chock the trailer wheels. Adjust the reel brakes as needed. Place protective barriers and cones as needed to
protect pedestrians.
2 x height of chute
height
of chute
set-up chute
cable blocks are
lifted into place
as the puller
passes
Aerial Installation 3.9
Back-Pull/Stationary Reel Block Placement
Back-Pull/Stationery Reel - Puller Set-Up and Block Placement
Cable Puller Set-Up
Place an appropriate cable grip on each cable. Secure the grip to the cable with tape to keep the cable from
backing out of the grip should the pulling tension be relaxed.
Place a breakaway swivel between the pulling grip and the cable puller. An in-line dynamometer may be placed
there instead or along with the breakaway swivel.
Place the cable puller on the strand and close the puller gates to secure the puller to the strand.
Attach a pulling line to the cable puller. Pull the cable puller along the strand by hand or by winch (see next page
for winching notes). Place cable blocks to support the cable as it is pulled. The cable puller has an internal brake
which prevents the cable puller from moving backward on the strand when the pulling tension is released.
Do not overspin the reel - keep the cable wraps tight.
Cable Block/Corner Block Placement
Use a cable block lifter/lay-up stick to place cable blocks on the strand every 30 - 50 feet (9 - 15 meters).
Place corner blocks at all corners greater than 30° in the pole line. NEVER pull cable over the end rollers of
corner blocks as they will flatten and deform the cable.
At corners less than 30°, cable blocks can be placed on the strand several feet from and on each side of the
pole/line hardware. The cable blocks should allow the cable to move through the corner without undue bending
or drag.
3.10 Aerial Installation
Back-Pull/Stationary Reel Passing the Pole
Back-Pull/Stationery Reel - Passing the Pole and Winching
Passing the Cable Puller at Poles
Pull the cable puller to the pole and release the tension in the pulling line. Pass the cable across the pole face
and the pole/line hardware, and attach the cable puller back to the strand. Place cable blocks on each side of
the pole.
At corner block locations, pass the cable puller to the opposite side of the pole and route the cables through the
corner block.
Cable Tails
A cable tail at least 3 feet (1 meter) in length should be left at the first and last poles and at all splicing locations.
More tail may be needed depending on the splicing that must be done or the size and location of the expansion
loop that will be made. Cap the end of the cables and tie them gently but securely to the strand. MAKE EVERY
EFFORT TO AVOID DAMAGE AT THE CABLE TAILS.
Power Winching Methods
Power winching a pull line to install CommScope cable is a method often used
when the poleline is obstructed or is in extremely rough terrain because the pull
line can be placed without tension concerns. In winching, the pull line is placed
in the cable puller and run along the strand. Once the pull line is run, it is
attached to the cable.
Carefully tension the pull line and begin pulling. Adjust the reel brakes to
prevent undue pulling tension. Real-time tension monitoring is required. Radio
communication between the lineman observing the pull-out and the winch
operator is required. Intermediate cable handling may be required as the
pulling grips approach cable and corner blocks.
QR’s long
lengths, typically
3700 ft (1.1km)
and superb
flexibility
lend itself to
power winching
and longer lengths
are available
Aerial Installation 3.11
Back-Pull/Stationary Reel Expansion Loops and Lashing
Back-Pull/Stationery Reel - Making Expansion Loops and Lashing
Make Your Expansion Loop Prior to Lashing
If an expansion loop is called for (see Aerial Installation/3.4), attach the mechanical bender to the strand and
form the loop per the manufacturer’s directions. Do not remove the bender until at least 50 ft (15
meters) of the cable has been lashed.
Attach the Lashing Wire Clamp
Place the lasher on the strand. Wrap the lashing wire twice around the strand
in the same direction as the twist in the strand and in the lay of the strand.
Pass the lashing wire between the washers of the lashing wire clamp without
overlapping the wire. Wrap the wire around the clamp to the post on the
opposite side of the clamp and wrap it twice around the post. Cut the wire
and tuck it between the halves of the lashing wire clamp. Use
appropriate-sized spacers to prevent the cable from rubbing against the pole
hardware. NOTE: it is essential that double lashing be used with two or more
cables, all trunk cables and at street and RR crossings.
Place the cable within the lasher. A cable positioner may be arranged ahead of the lasher for extra guidance as
the lasher is pulled toward the reel. Pull the lasher toward the reel with a wire or rope.
It is important to minimize the sag on cables as they enter the lasher. Leave the cable blocks in place until the
lasher is close enough to support the cable. As the lasher approaches cable blocks, either remove them with a
cable block lifter or push the cable blocks to the next pole by utilizing a cable block pusher.
pull the lasher toward the reel
keep the bender in
push along or remove cable
blocks as lasher approaches
place while lashing
the first 50 ft (15 m)
3.12 Aerial Installation
Back-Pull/Stationary Reel Passing the Lasher
Back-Pull/Stationery Reel - Passing the Lasher at the Pole
Passing the Lasher at the Pole
Pull the lasher toward the pole to be passed. Attach a lashing wire clamp to the strand. Remove the lasher from
the strand and move it across the pole-face to the strand and cable on the opposite side of the pole.
Put the cable into the lasher. Close the gates to prevent the lasher from being pulled backward along the strand.
Cut the lashing wire from the lasher and secure the lashing wire to the lashing wire clamp. Make sure that the
lashing wire does not loosen from around the cable.
Attach appropriate straps and spacers as needed. At the back end of the lasher, attach a lashing wire clamp to
the strand about to be lashed. Attach the lashing wire to the clamp. Continue lashing as before.
Carefully rotate the cable reel to take up any excess cable slack prior to lashing each section.
Remember not to lash the cable too tightly. Coaxial cable must be permitted to contract and
expand along the strand or the cable may buckle and fail.
Aerial Installation 3.13
Drive-Off/Moving Reel Set-Up
Drive-Off/Moving Reel Set-Up and Lashing
Trailer Set-Up
Pay the cable off the top of the reel rotating toward the rear of the cable trailer. Use minimal reel braking.
Attaching the Lasher, Set-Up Chute and Cable
Attach a lashing wire clamp to the strand (see Aerial Installation/3.11) far enough from the initial pole to
accommodate a required expansion loop or equipment. Place the lasher on the strand and attach the lashing
wire to the lashing wire clamp.
Position the set-up chute in front of the lasher and attach it to the lasher with a block pusher (or shotgun). Attach
the pull line to the set-up chute or lasher.
Thread the cable through the set-up chute and place the cable in the lasher. Leave sufficient cable tail to
accommodate a loop, splice or equipment. Close the lasher gates.
The cable should move only through the chute. If the pole-line is offset from the reel, observe the cable closely as
it moves through the chute. Cable reel offset may cause the cable to drag on the reel flange and the cable in the
chute to bind.
lasher and set-up chute
are connected with a shuttle
watch set-up chute and
reel for potential binding
cable is pulled and
lashed at the same time
reel pays off
the top
3.14 Aerial Installation
Drive-Off/Moving Reel Expansion Loops
Drive-Off/Moving Reel - Expansion Loops/Passing the Pole
Form the Expansion Loops
Stop the lasher about 6 feet/1.8 meters from the pole. If an expansion loop is required, attach the mechanical
bender to the strand in the appropriate position (see Aerial Installation/3.4).
If you are cutting the cable, make sure to leave enough cable tail to accommodate any splicing, equipment or
expansion loops.
Passing the Pole
Attach a lashing wire clamp far enough from the pole to accommodate an expansion loop or equipment. Open
the lasher gates. Disconnect the set-up chute, pusher and lasher and pass them across the pole-face. Place them
on the unlashed strand far enough from the pole to accommodate an expansion loop or equipment and
reassemble them.
Close the lasher gates. The lasher cannot be pulled backward along the strand while the gates to the lasher are
closed. Cut the lashing wire and secure it to the lashing wire clamp. Make sure that the lashing wire does not
loosen from around the cable.
Attach another lashing wire clamp to the strand on the unlashed side of the pole allowing enough distance for an
expansion loop or equipment. Connect the wire from the lasher to the new clamp.
Place the cable in the set-up chute and the lasher.
Rotate the cable reel to take up any excess slack. Continue until the installation is complete.
pull the lasher toward the reel
watch the set-up
keep the bender in
place while lashing
the first 50 ft (15 m)
chute for possible
binding
Aerial Installation 3.15
Overlashing
Installation - Overlashing Existing Cable
Overlash Cable Placement
Overlashing cables onto existing cable plant is similar to installing cable onto new strand. However, there are
some unique aspects:
A sag and tension analysis should be performed to see if the new cable load will overwhelm the strand.
Use special overlash cable puller blocks and continuously maintain and monitor the pulling line tension. Overlash
cable pullers do not have a strand brake and will be pulled backward on the span by the tension in the cables
being pulled.
Use cable blocks designed specifically for overlash applications. Place them onto the cable bundle with a cable
block lifter and lift the cable with a cable lifter. During lashing, remove the cable blocks from the cable bundle
with a cable block lifter. DO NOT PUSH THE CABLE BLOCKS in front of the lasher as that may damage existing
cables.
Remove all straps and spacers from the existing cable bundle during lash-up. New straps and spacers may be
required - check the old ones carefully to see if they need replacing.
4.1 Integrated Messenger Installation
Overview
Integrated Messenger Installation
The most cost effective and reliable coaxial installation is possible today by using CommScope’s integrated
messenger products. Both our flagship QR
®
and traditional P3® products are available in integrated messenger
designs, built to increase your aerial plant reliability while greatly reducing your installed costs.
How Do We Increase Your Plant Reliability?
Integrated messenger plant is not susceptible to the same expansion and contraction concerns as lashed plant.
The cable web binds the coaxial cable to the strand, so the two expand and contract as a unit. This is beneficial
to the installer, since integrated messenger coaxial plant does not require the installation of expansion loops.
The expansion loop, once removed, is also removed as a failure point.
Aerially installed coaxial cable is subject to many forces. These forces are developed due to wind and ice loading,
materials expansion and contraction, and the cables own weight. Correctly installed cable will survive the brunt of
these forces for years. Vibration and wind effects can strain the cable at pole passings, but by simply separating
the cable from the strand at the pole attachment, radial cracks can be eliminated.
Integrated Messenger Installation 4.2
Down Guys
Down Guys
All down guys must be placed prior to
tensioning the self-supporting cable.
Where grounding of down guys is
required, it will be necessary to bond the
down-guy to the strand.
4.3 Integrated Messenger Installation
Hardware and Block Placement
Hardware and Block Placement
Extension brackets, strand clamps and roller blocks should be in place prior to cable placement for each method
described.
The C strand suspension clamp (shown at right) is used on jacketed strand. It is a
three-bolt clamp with serpentine grooves to prevent slippage of the jacketed strand
through the clamp. The suspension clamp must be a type recommended for the size of
strand used. It must be placed so the strand groove is below the suspension bolt.
Place a cable chute on the first pole using a B or C frame without the swivel bracket.
Strand
Suspension Clamp
Use a bolt through the chute mounting
bracket in place of the swivel bracket on
the B or C frame.
B FrameC Frame
Set-up Chute
Place a pole mount block or equivalent on all in line poles. Blocks and frames listed previously may also be used.
Use a multiple roller block for
45 and 90 degree angles.
Place a non-metallic pull line in the roller
90˚block
blocks.
Integrated Messenger Installation 4.4
Moving Reel Method
Moving Reel Method
The moving reel method of placing
self-supporting cable is used where
a cable reel can be moved along
side the pole line and there are no
obstructions to prevent the cable
the cable is
attached by the
messenger to
the pole
from being raised into position.
Loading the Cable Reel
Load the cable reel so the cable is payed-out from the top of the reel. Use one of the blocks and frames pictured
on page 4.3 for this placement method. If trees or other obstructions restrict the use of this method for a few
sections close to either end of the run, proceed as follows. Pull the cable beyond
the obstruction and lift into place. Resume the moving reel method once the
obstruction is cleared. Where it is necessary to clear street or driveways use a
Strand Puller attached to the pole with a sling. Do not remove the strand puller until
the cable has been pulled to final sag at the dead ends or tensioning locations.
Note: The cable and strand must be separated before using a strand puller to
prevent damage to the cable. A strand dead end or wire vise may be used to pull
IM cable with.
pole mount
block supports
the cable
cable is lifted
into place on
the block
reel pays off
over the top
Caution: Do not use J Hooks to place IM cable. Coaxial cable should never be pulled over placing hooks.
Placing the Cable in Blocks
If a bucket truck is not available, the cable should be raised into place using a cable-lifting tool.
Do not tension cable around cable blocks. Tension should only be applied from corner poles outward.
4.5 Integrated Messenger Installation
Stationary Reel Method
Stationary Reel Method
When self-supporting cable will be placed from a stationary reel, all strand hardware,
cable blocks, frames, and down-guys must be in place.
pole mount block
supports the cable
cable is lifted into
place on the block
do not pull cable
downward over the small
pole mount block
cable is
pulled by hand
or bucket truck
reel pays off
over the top
set-up chute
Loading the Reel Trailer
Load the cable reel onto the trailer so the cable is payed-out from the top of the reel.
Positioning the Reel Trailer
When using the back pull or stationary reel method of placement the trailer should be placed back from the pole
two times the distance of the attachment height. The center of the cable reel should be as near inline with the
strand line as possible to prevent the cable from rubbing the reel flanges. Also, locate the trailer so the cable will
not rub the pole face as it is being pulled. For a straight pull, the reel can be set-up at either end. However, it is
advisable to pull in the same direction as traffic flow. The cable reel should always be located at the end nearest a
45/90-degree pull to reduce tension.
Pulling the Cable
Prepare self-supporting cable for pulling by separating the strand and
cable with a web-slitting tool. Remove the jacket from the strand.
Removal length will depend on the length of the strand grip or pulling
device. Place the pulling grip of choice on the strand and then tape the
cable to the grip. Tape the cable end in a taper so it will not lodge on the
rollers or attachments.
Ripley Cablematic - MWS-xxx
Integrated Messenger Installation 4.6
Stationary Reel Method
Attach a swivel between the grip and pull line. Pull by the messenger only! Start each pull very slow to remove
slack in the pull line and cable. Never start with a sudden jerk, as this will damage the cable at the blocks. While
pulling, monitor the cable for binding in the blocks/rollers, and rubbing against the poles. Use cable reel brakes
as necessary. During the placing
operation do not exceed the maximum
rated pulling tension of the steel. After the
cable has been placed, tension should
be applied to the strand only. Follow
clearance guidelines found in the current
NESC Rules 250-252. Use SpanMaster
Note: When placing above or between existing plant, match sag.
Cable and Strand Separation
Use CableGuard
or strap and spacers
Note: Prior to placing the strand in the clamps, the cable
and strand must be separated using the MWS-xxx tool.
Ripley Cablematic - MWS-xxx
4.7 Integrated Messenger Installation
Stationary Reel Method
Tensioning
The length of self-supporting cable that can be tensioned at one time will depend on several factors such as
corners, span length, changes in grade, and maximum pulling tension. However, lengths up to 1000 feet can
generally be tensioned satisfactorily in straight sections of pole line. Use a chain hoist, strand puller, and sling to
remove slack and tension the strand. The strand puller can be used over jacketed steel.
Note: Strand and cable at corner poles and grade changes should be in the clamps or dead ended prior to
tension being applied.
When the span/s are tensioned and sagged, move from pole to pole separating the steel and cable prior to
clamp placement.
Caution: To prevent damage to the cable, separate the cable and steel before using a strand puller. The pin
attaching the safety chain will cause severe damage to the cable.
A tensiometer may be used to monitor tension on the strand. The tensiometer is placed between the hoist and
strand puller so the tension can be read directly from the scale as the cable is being sagged. This method is very
useful on long lengths to prevent undue stress on the steel. See steel strand specifications table in section 4.6.
Caution: Permanent down guys should be in place at the first, last, and any intermediate poles before tensioning
to final sag to prevent unbalanced loads.
All spans should be tensioned and placed in clamps during the workday. Do not leave the cable
suspended in roller blocks from one workday to the next.
Integrated Messenger Installation 4.8
Dead Ending
Dead Ending
Self-supporting cable is dead-ended at the first, last, and corner poles. For stranded steel attach with a
Strand-Dead End (Preform), for solid steel messengers use a wire vise. Sufficient cable and strand separation will
be required at dead-end poles to allow for splicing if necessary.
Note: A corner pole is defined as having an angle of 30° or greater from the pole line.
The strand must be dead-ended or false dead-ended at corner poles in both directions. If the strand continuity is
broken, bonding will be required at this time.
Note: It is not necessary to cut the strand if B false dead ends are used.
Dead End
(minimum 12 inches)
Strand-Dead End
4.9 Integrated Messenger Installation
Cable and Strand Separation
Cable and Strand Separation
Note: At the time of tensioning the cable and strand must be separated before making permanent attachment.
When a Strand Vise or Strand Grip is used
on IM at dead-end locations, the cable, and
strand must be separated in the web. The web
should be slit to a point 6 inches beyond the
far end of the vise or strand grip.
Note: Do not use a utility knife for slitting the
web on IM Cables.
Remove the poly jacket from the steel and
attach the grip. Make sure the sag is correct
before cutting the excess steel.
Note: It is not necessary to remove the tar
flooding from the steel if present.
Use cable guard or spacers at all
hardware locations.
Dead End
Integrated Messenger Installation 4.10
Pole Attachment
Pole Attachment
After the self-supporting cable has been placed and properly tensioned, it must be attached permanently.
Any twist (360° rotation) in the IM cable should be removed at this time.
The “C” Cable Clamp can be used for attaching the jacketed strand on QR. This is a 3-bolt clamp with
serpentine grooves to prevent slippage of the jacketed strand. Install the clamp after the web has been slit.
4.11 Integrated Messenger Installation
Splicing
Splicing
Separating Cable and Strand
Measure from the clamp center bolt out 24 inches plus the width of the device plus another 24 inches beyond
the device. Mark the cable at these locations for separation. Consult your company methods and procedures for
equipment placement prior to installation.
Use the appropriate size web slitting tool to separate the steel and cable.
Separation for Splice
Note: 6” straight cable behind connector
Note: 12” to bend
Note: 24” without expansion loop
Temporarily hang the device on the strand and cut the cable center of the device or if the device location was
marked cut in the center.
Note: Do not remove any cable at this time.
Expansion loops are optional. An expansion loop will provide excess cable for future terminations.
Integrated Messenger Installation 4.12
Splicing
A minimum of 24 inches separation is required at each pole
passed. Measure from the clamp center bolt twelve inches
from each side.
Web Removal
The web must be removed on QR products leaving a
smooth round cable for splicing. Note: Do NOT use a knife. Prior to removing any cable, remove the web. The
web on QR can be removed the length of the separation or
2 inches beyond the shrink tube length.
Ripley-Cablematic MWSS-xxx
Cable Transition
Attach the device to the strand with main body of
connectors installed. Make the cable transition into the
device. A minimum of 6 inches of straight cable must
be maintained behind the connector to allow for
splicing and flexing.
Minimum Separation at
Pole Passing
Note: Seperation
is required to
prevent cable
cracking
Cable Transition
Note: Start on the span side.Note: Web removed before splicing cable
When hand forming the transition into the equipment, do not exceed minimum bend specification.
5.1 Underground Installation
Overview
Underground Installation of CommScope Cable
There are several cable types built specifically for underground installation:
QR / P3 JCASS / MOCJ
QR 2J(MA)CASS with twin polyethylene jackets separated by a tough polypropylene tape for extra
resistance to cut-through
P3 CableGuard
QR / P3 JACASS / MOCG
®
ConQuest
Cable-in-Conduit direct burial. Please consult our Conduit Applications and Construction
Manual.
The three methods for direct burial are vibratory plowing, trenching and boring.
Vibratory Plowing is the most popular method. A plow with a special blade slices
through the ground. The cable runs through a tube in the blade and is placed as the
plow moves forward. Since no dirt is displaced, vibratory plowing is much less intrusive
than trenching.
CommScope cable pre-installed in a tough high-density polyethylene conduit for
with Migra-Heal® flooding compound between the shield and jacket
®
with crush resistant air pockets built in
with twin polyethylene jackets separated by corrugated chrome plated steel armor
QR pulls
through
ducts with
less effort
than any
Trenching involves digging or plowing a trench, placing the cable in it and then
burying it.
other
coaxial
cable
Boring (directional and conventional) digs or punches a hole in the earth, usually from
one trench to another. It is an excellent method for crossing areas that cannot be plowed (such as paved roads or
railroad tracks) if they cannot be traversed aerially. Cable is then pulled through the hole.
CommScope cable may also be pulled through existing underground conduit or ductwork. As with
aerial installation, careful attention must be paid to not exceeding the maximum pulling force or the minimum
bend radius.
Underground Installation 5.2
Pulling Tension
Pulling Tension
Pulling tension for CommScope cable types are shown in this chart.
Cable Max. Pulling Tension
lbs / kgf
QR 320 120 (54.5)
QR 540 220 (100)
QR 715 340 (154)
QR 860 450 (204)
P3 500 300 (136)
P3 625 475 (216)
P3 750 675 (306)
P3 875 875 (397)
MO500 270 (123)
MO650 360 (164)
MO750 500 (227)
NEVER EXCEED THE MAXIMUM PULLING TENSION.
Excessive forces applied to the cable will cause the cable to permanently
elongate. Good construction techniques and proper tension monitoring
equipment are essential. The highly flexible nature of QR cable makes it
very difficult to exceed the maximum pulling tension.
Tail loading is the tension in the cable caused by the mass of the cable
on the reel and reel brakes. Tail loading is controlled by two methods.
It can be minimized by using minimal braking during the pay-off of the
cable from the reel - at times, no braking is preferred. Tail loading can
also be minimized by rotating the reel in the direction of pay-off.
Break-away swivels should be placed on each cable to ensure that the maximum
allowable tension for that specific cable type is not exceeded. The swivel is placed
between the cable puller and pulling grip. A break-away swivel is required for each
cable being pulled.
Dynamometers are used to measure the dynamic tension in the cable. These
devices allow continuous review of the tension and accordingly a realization can be
made of any sudden increase in pulling tension.
QR’s flexible
construction
means
longer runs
and more
45°/90° bends
are possible
5.3 Underground Installation
Bending Radii
Bending Radii
Cables are often routed around corners during cable placement and pulling tension
must be increased to apply adequate force to the cable to bend the cable around
the corner. Tension is directly related to the flexibility of cable - and flexibility is QR’s
greatest strength.
CommScope’s specified minimum bending radius is the static (unloaded) bending
radius of the cable. This is the minimum radius to which the cable can be bent
without electrically or mechanically degrading the performance of the cable. Bending
the cable in this manner is usually only done during splicing or final forming. This is
also the radius allowed for storage.
Minimum
Cable Bending Radii
in/cm
QR 320 3 (7.6)
QR 540 4 (10.2)
QR 540 armored 6.5 (16.5)
QR 715 5 (12.7)
QR 715 armored 7.5 (19.1)
QR 860 7 (17.8)
QR 860 armored 9.5 (24.1)
P3 500 standard (jacketed) 6.0 (15.2)
P3 500 bonded (jacketed) 3.5 (8.9)
P3 625 standard (jacketed) 7.0 (17.8)
P3 625 bonded (jacketed) 4.5 (11.4)
P3 750 standard (jacketed) 8.0 (20.3)
P3 750 bonded (jacketed) 6.0 (15.2)
P3 875 standard (jacketed) 9.0 (22.9)
P3 875 bonded (jacketed) 7.0 (17.8)
MO500 6.0 (15.2)
MO650 7.0 (17.8)
MO750 8.0 (20.3)
Always review the specifications for the appropriate
bend radii. If you do not exceed the minimum bend
radius nor exceed the maximum pulling tension, you
should have a successful installation.
The bending radii of cables
during the construction process
are controlled by the radii of the
bends in duct or conduit as well
as construction techniques and
equipment.
QR’s shield
construction
permits the
tightest bend
radius in the
industry
Underground Installation 5.4
Vibratory Plowing
Underground Installation - Vibratory Plowing
Vibratory plowing offers substantial productivity gains over other direct burial methods. A tractor moves slowly
forward as a vibrating blade splits the earth and places the cable at the required depth. Because terrain and soil
types vary, contact your plow manufacturer for their equipment recommendation. We strongly recommend a
professionally engineered single or double feed tube plow blade with a tube at least 1/2 inch (1.3 cm) larger
than the largest cable size and a radius of 12 in (30 cm) or larger. At minimum, an operator and a helper/feeder
are needed for a plowing installation.
Dig a trench deep enough and at least twice the length of the plow blade/chute for the plow blade to enter it
comfortably. A similar trench should be dug at the other end of the installation. The cable may pay-off from the
front of the tractor or from a stationary cable reel.
In the tractor method, make sure the reel is not run into objects that may damage the cable. Pay the cable over
the top of the reel. Do not use reel brakes.
In the stationary reel method, pull the cable end from the reel to the ending trench. Use safety cones to mark and
protect the cable from pedestrian and vehicle traffic.
Cap or tape the cable end. Remove the back plate from the blade and inspect the feed tube for burrs, rough
surfaces and sharp edges. Clean out any dirt or rocks. Carefully place the cable in the feeder tube. Reattach the
back plate.
Carefully pull enough cable through the blade to allow for splicing, etc. Have someone hold the cable end to
keep it from being pulled as the tractor initially moves forward. Start the vibrator after forward movement begins.
Have the blade in solid contact with the earth before applying full RPM. DO NOT VIBRATE IN PLACE FOR
MORE THAN 30 SECONDS.
A worker must manually guide the cable into the plow blade.
5.5 Underground Installation
Vibratory Plow Movement
Underground Installation - Vibratory Plow Movement
Handling obstructions
If obstructions (tree roots, large rocks, etc.) are encountered, disengage the transmission, turn the engine off and
then disengage the clutch. NEVER BACK THE PLOW WITH CABLE IN THE FEED TUBE. This will damage the
cable and pack dirt into the feed tube.
Carefully dig a pit behind the blade. Remove the cable, then remove the obstruction. Replace the cable and
proceed with the installation.
Although aggressively steering and lifting/lowering the blade are considered poor practice, these techniques can
be used as long as extreme caution is exercised.
Turning
Gentle turns can be made over a distance of 5 - 8 feet (1.5 - 2.4 meters). Never turn the blade unless the tractor
is moving forward. Some manufacturers make steerable blades.
Lifting the blade
If absolutely necessary (for instance, avoiding a buried utility line), the blade can be gradually raised at a rate of 8
inches (20 cm) over a 5 foot (1.5 meter) run. Lower the blade at the same rate once the underground hazard has
been passed. Do not raise the blade to ground level with cable in the feed tube.
Underground Installation 5.6
Trenching
Trenching
Trenching is accomplished with specialized trenching tractors which cut the trench and remove the soil in a
single action. A trench can be used to place multiple cables over long or short distances. Detailed equipment
operation and excavation procedures are specified by the construction equipment manufacturer.
All bores and crossings should be installed prior to the start of the trenching process.
Excavate the trench to the desired depth. Remove all rocks and large stones from the bottom of the trench to
prevent damage to the cable. Push some clean fill into the trench to cushion the cable as it is installed in the
trench.
Supplemental trenches should be made to all offset enclosure locations. Trench intersections should be
excavated to provide adequate space to make sweeping bends in the cable/conduit.
Place the cable trailers or cable reels in line with the trench to prevent any unnecessary bending of the cable.
Pay the cable off the bottom of the reel.
When routing cables to enclosure locations, leave adequate cable lengths for splicing. Bend the cables
carefully around corners and upward at enclosure locations. Cap the cable as needed.
Bury warning tape above the cable during the back-fill process.
Fill the trench and compact it as required. Tamp or flood the trench to provide compaction that will prevent the
trench from receding.
5.7 Underground Installation
Boring and Ductwork
Boring and Conduit Installations
Conventional Bores
Mechanical boring machines may be utilized to push a drill stem to make an adequate cable passage.
Pneumatically driven pistons may be used as well. Conduit should be placed to support the tunnel wall and allow
cable placement.
Directional Bores
Directional boring is accomplished by using a steerable drill stem. The depth and direction of the boring can be
controlled by the equipment operator. Very long bore lengths can be accomplished by using directional boring
devices.
Subsurface crossings are generally accomplished by digging a trench on each side of the crossing to allow the
guiding and retrieval of the drill stem. Detailed equipment operation and excavation procedures are specified by
the construction equipment manufacturer.
Generally, try to keep the bore as straight as possible. The hole may be enlarged by using reamers. Conduit
should be installed at strategic locations (i.e. street crossings).
After the bore is complete, attach the cable to the drill stem with the appropriate cable grip and swivel. Pull the
drill stem/cable through the bore. Longer pulls will require tension monitoring.
Underground Installation 5.8
Conduit
Installing CommScope Cable into Conduit
Cable can be pulled in new or existing conduit. New conduit should be installed in as straight a path as
possible - undulations in the conduit system increase pulling tensions due to sidewall pressure. Existing conduit
systems generally require some maintenance prior to placing cables into the conduit. Use a rodding machine to
remove unwanted debris and water from the conduit.
A cable route survey will dictate the cable placement scheme which should account for the difficulty of the pull,
manpower and equipment availability.
The curve radii in the conduit systems should be large enough to prevent excessive pulling tension due to
sidewall friction. Very small radius bends may prevent even a cable as flexible as QR from being successfully
pulled.
Blowing or Jetting Cable
This process uses a combination of air pressure and a small drive to push the cable through a conduit. It is most
effective when placing a single cable. Since the cable is not pulled, pulling tension is not a concern.
Position the reel so that pay-off is from the top and is in as straight a line as possible with the entrance to the
duct. A small caterpillar drive pushes 150 - 200 feet (45 - 60 meters) of cable into the conduit. Air is then
forced into the conduit and the jetting action helps propel the cable with minimum effort.
With this method, a flexible cable like QR 860 can be pushed through 7 - 8 90° sweeps over a 1500 foot (450
meter) distance of 2 inch (5 cm) rigid PVC conduit.
6.1 Connectorization
ACT® - Advanced Coring Technology
Coaxial BondingOptimizing Preparation and Connectorization
Hardline coaxial cables have been used in the broadband industry
for decades. During these years many refinements were made to
these cables to produce the optimal cable electrical and
mechanical performance. Today, with a better knowledge of
processes and recent advancements in material, cables are again
being further optimized.
•EnhancedMechanicalPerformance
•Meets/ExceedsANSI/SCTE,EN50117,IECand
Cenelec Specifications
•FullyBackwardCompatible
•IdenticalElectricalPerformance
•PatentPending
Introduction
Coaxial cables have several interface areas between metals and plastics. Each of these interfaces offers a unique
set of issues to the user and manufacturer, all related to the bonding of the plastics to the metals. It is bonding that
enhances the mechanical performance of a coaxial cable; enabling improved bend performance, core retention,
and inhibiting moisture migration.
Just as essential as the cable’s mechanical performance is the ability to properly prepare and connectorize a cable.
There must be a balance to achieve both with optimal results. This paper will provide an understanding of what
trade-offs are made when going to the extremes in bonding, preparation performance, and the optimal zone for a
cable to be in.
Connectorization 6.2
ACT® - Advanced Coring Technology
Industry Standards
To assure a cable’s performance for the user, the industry has adopted standardized test methods and
minimum specifications for defining the bond characteristics of coaxial cable.
As a starting point, the SCTE in its “Specification for Trunk, Feeder and Distribution Coaxial Cable” [ANSI/SCTE
15 2001] specifies minimum bond strength between the dielectric and the center conductor defined as “Dielectric
Shear Adhesion”. The bond strength values vary with cable size, with larger cables having higher bond strength
requirements then smaller cables.
Bond Strength
Cable Type Miminum Pound Force
P3
500 60
625 80
750 90
875 86
As an example, a P3 500 cable size has a minimum
bond strength requirement of 60 lbs, while a P3 750
cable size has a requirement of 90 lbs.
Additional important attributes of the bond are
identified in this specification. First, a “Dielectric
Shrinkback” requirement in which the shrinkback of
the dielectric shall shrink no more than 0.250 inches
QR
540 68
715 90
860 96
ANSI/SCTE 15 2001 - Table 10.0
(6.35 mm) from both ends of the sample following
test procedure ASTM D 4565. Second, is the “Cable
Static Minimum Bend” tested following ANSI/SCTE
39 2001.
Typical bond strengths of today’s cables well exceed these minimum requirements, being as much as 100% above
that specified by ANSI/SCTE. Such a conservative approach is understandable given that there was no cost
penalty to create a bond that performed at such a high level, and that operating at that level eliminated any
potential for poor performance due to low bond strength. With excessively high bond strengths, controlling the
consistency of the cable’s quality is less demanding. The negative impact of this for the cable’s user is a difficult
preparation and connectorization process.
At the other end of the spectrum are poorly bonded cables that do not meet the specified ANSI/SCTE
requirements. The typical cause of low bond strength is attributed to the inability to control a consistent
manufacturing process. The negative impact of this for the cable’s user is poor core retention, moisture migration,
and poor bend performance (kinks easily).
6.3 Connectorization
ACT® - Advanced Coring Technology
There is an operating range, though, in between these two extremes of performance that facilitates a dielectric
bond that will cleanly break away from the center conductor without sacrificing the mechanical aspects of the cable.
CommScope has developed, ACT (Advanced Coring
Technology), a patent-pending bonding technology that
operates in this window between the extremes. As shown in
the chart in Figure 1, it exceeds the SCTE requirements for
bond strength and provides for a clean and easy removal of
the bonding material.
With this technology, the force exerted by the coring tool is
sufficient to cause the dielectric to break away from the center
conductor, leaving a clean conductor that typically does not
require a second dielectric removal step. The tool and the
craftsman can influence this enhanced performance
characteristic of the cable, making a one step coring highly
repeatable.
TABLE 1 – CABLE PERFORMANCE WITH ACT.
In addition to bond strength, the bonding agent also
maintains the other key performance criteria of the cable as
called out in the SCTE specification. Some of those criteria are
listed in Table 1.
Overall this solution provides all of the benefits of water
migration deterrence, corrosion prevention, and mechanical
performance while eliminating the performance risks
associated with center conductor dielectric removal.
Measure
Requirement
Center Conductor Bond Strength4
Center Conductor Corrosion4
Water Penetration4
Air Transmission4
Dielectric Shrink Back4
Velocity of Propagation4
Passes SCTE
Attenuation4
Summary
The bond strength in cable is critical to the mechanical
TABLE 1 – CABLE PERFORMANCE WITH ACT.
performance of the cable. However, bonding affects more than
just the cable’s mechanical characteristics, it also impacts the facilitation of cable preparation and
connectorization. Finding the balance of bond strength and craft friendliness is accomplished by the development of an
advanced technology bonding agent and coupling it with CommScope’s consistent manufacturing process controls.
This achievement enables the cable to mechanically behave the way it needs to and makes the preparation easier.
Connectorization 6.4
ACT® - Advanced Coring Technology
Cable Preparation with ACT
®
P3® with ACTTM and QR® with ACTTM cables were developed to address a question that has been clearly stated and
often repeated by the craftsmen, engineers, and technical operations managers of the broadband industry.
Why must a hardline cable be so difficult and problematic to properly core and prep?
Introduction
Traditional coaxial trunk and distribution cables require considerable attention to the preparation of the
cable end for proper connectorization. Critical to that end, preparation is the proper removal of dielectric
and bonding compound from the conductors.
The normal process requires the craftsman to first core
the cable and then clean the center conductor in a second step.
CommScope’s new patent pending P3
conductor cleaning step by enabling a clean coring process in which the center conductor is cleaned of dielectric
and bonding compound during the coring process.
With this technology, the force exerted by the coring tool is sufficient to cause the dielectric to break away from the
center conductor, leaving a clean conductor that typically does not require a second dielectric removal step. The
tool and the craftsman can influence this enhanced performance characteristic of the cable.
®
with ACT® and QR® with ACT® cables virtually eliminate the center
These cables meet and exceed all ANSI/SCTE, EN50117, IEC and Cenelec testing methods for trunk, feeder, and
distribution cables.
This paper is intended to provide the craftsman with the understanding of how the cable is different and how to
optimally prepare cable with Advanced Coring Technology
®
.
6.5 Connectorization
ACT® - Advanced Coring Technology
What Makes ACT So Different?
Typical bond strengths of today’s cables well exceed the minimum requirements, being as much as 100% above
that specified by ANSI/SCTE.
At the other end of the spectrum are poorly bonded cables that do not meet the specified ANSI/SCTE,
EN50117, IEC and Celelec requirements.
There is an operating range, though, in between these two extremes of performance that facilitates a dielectric
bond that will cleanly break away from the center conductor without sacrificing the mechanical aspects
of the cable.
CommScope has developed ACT, a patent-pending bonding technology that operates in this window between
the extremes. As shown in the chart in Figure 1 (on page 6.3), it exceeds the SCTE requirements for bond
strength and provides for a clean and easy removal of the bonding material.
In addition to bond strength, the bonding agent also maintains the other key performance criteria of the cable as
called out in the SCTE specification. Some of those criteria are listed in Table 1 on page 6.3.
Overall this solution provides all of the benefits of water migration deterrence, corrosion prevention, and
mechanical performance while eliminating the performance risks associated with center conductor dielectric removal.
Connectorization 6.6
ACT® - Advanced Coring Technology
Getting a Clean Core
To take advantage of an ACT cable’s unique clean coring capabilities there are a couple of simple “Best Practice”
procedures that the splicer must understand and put into practice.
•DrillCoring– To enable the tool to optimize its shear
ing force while coring:
- Keep the RPM’s below 450 (low speed)
- Apply slightly more forward pressure than usual for about the first ¼ inch of the core, then resume normal
forward pressure
- Some will find it easier to “trigger” the drill in short 1-2 second bursts for about the first ¼ inch of the core,
replicating a hand core action, rather than controlling a constant low drill speed
•HandCoring– While not the preferred method of most splicers, it does provide a consistent clean core
operation without any special needs.
Most standard tools are able to provide the proper shearing force necessary to facilitate a clean core. However, a
splicer may find that they have a tool that does not provide a consistent clean core. In the event that this occurs,
ACT cables enable the splicer to easily remove the remaining bonding compound and dielectric with a traditional
center conductor cleaning tool. This removal is accomplished with greater ease than was ever possible with
traditional cables.
Summary
The bond strength in cable is critical to the mechanical performance
of the cable. However, bonding affects more than just the cable’s
mechanical characteristics, it also impacts the facilitation of cable
preparation and connectorization. Finding the balance of bond
strength and craft friendliness is accomplished by the development
of an advanced technology bonding agent and coupling it with
CommScope’s consistent manufacturing process controls. This
achievement enables the cable to mechanically behave the way it
needs to and makes the preparation easier.
With some simple “best practice” procedures, a splicer will find it
easy to consistently achieve a one step clean core.
Below is an example of
traditional P3
Residual dielectric and
bonding compound on
conductor after coring
®
cable
Below is an example of
®
cable with ACT
P3
Conductor clean of dielectric
and bonding compounds
after coring
®
6.7 Connectorization
Overview of P3 Connectorization
P3® Connectorization
Use the right tools: a P3 coring tool, a P3 jacket stripper, a file, center conductor cleaning tool, wrenches
sized for the connectors (adjustable wrenches are fine) and cable cutters. A hi-torque, low-speed drill or a ratchet
are optional, but will speed the process. Wearing safety glasses and gloves are recommended.
Prepare the cable by using the cable cutters to trim the cable to a smooth, round end.
Remove the jacket using a P3 jacket removal tool. This tool rotates around the cable and removes jacket
material without scoring the aluminum. A knife is not recommended for this process.
Remove any MigraHeal
Remove the proper amount of shield and dielectric with the P3 coring tool. Slide the cable into the
tool until it stops. With slight forward pressure, twist the coring tool (either by hand or mechanically with the
ratchet or drill) so that the blade begins to strip and core the cable. Continue to turn the coring tool until the
proper trim dimensions are achieved. Clean the dielectric and shield residue from the tool.
Clean the center conductor by using a non-metallic cleaning tool. Score the coating on the center
conductor at the shield and scrape it toward the end of the conductor. The conductor is clean if the copper is
bright and shiny. DO NOT USE A KNIFE or other metal tool as it may damage the copper cladding.
®
compound that may be on the shield.
Slide the shrink tubing (highly recommended) over the cable end, then attach the
connector according to the manufacturer’s instructions. Place and shrink the boot. Note: if you are using a
heat-shrink boot, apply the flame carefully. Overuse of the torch may melt the jacket and dielectric.
Connectorization 6.8
Overview ofo QR Connectorization
QR® Connectorization
QR coring/stripping tools are designed for craft-friendliness and speed of operation. All QR connectors and tools
are manufactured to meet CommScope specifications, therefore any QR tool can be used to prepare the
proper-sized QR cable for any manufacturer’s connector.
Use the right tools: a QR coring tool, a file, center conductor cleaning tool, wrenches sized for the
connectors (adjustable wrenches are fine) and cable cutters. A hi-torque, low-speed drill or a ratchet are optional,
but will speed the process. Wearing safety glasses and gloves are recommended.
Prepare the cable by using the cable cutters to trim the cable to a smooth, round end.
Remove the proper amount of shield and dielectric with the QR coring tool. Slide the cable into the
tool until it stops. With slight forward pressure, twist the coring tool (either by hand or mechanically with the
ratchet or drill) so that the blade begins to strip and core the cable. Continue to turn the coring tool until it spins
freely - the tool has a preset stop that requires no adjustment. Clean the dielectric and shield residue from the
tool.
Clean the center conductor by using a non-metallic cleaning tool. Score the coating on the center
conductor at the shield and scrape it toward the end of the conductor. The conductor is clean if the copper is
bright and shiny. DO NOT USE A KNIFE or other metal tool as it may damage the copper cladding.
Remove the correct amount of jacket with the QR jacket removing tool. Slide the cable into the tool until
the cable stops. Turn the tool clockwise to strip the jacket. Continue turning until it spins freely - the tool has a
preset stop that requires no adjustment. Remove any Migra-Heal
®
compound that may be on the
shield.
Slide the shrink tubing (highly recommended) over the cable end, then attach the
connector according to the manufacturer’s instructions. Place and shrink the boot. Note: if you are using a
heat-shrink boot, apply the flame carefully. Overuse of the torch may melt the jacket and dielectric.
6.9 Connectorization
Overview of MC2 Connectorization
®
2
MC
Connectorization
Use the right tools: a MC2 jacket stripper, a file, center conductor cleaning tool, wrenches sized for the connectors
(adjustable wrenches are fine) and cable cutters. A hi-torque, low-speed drill or a ratchet are optional, but will
speed the process.
Wearing safety glasses and gloves are recommended.
Prepare the cable by using the cable cutters to trim the cable to a smooth, round end. It is important to cut
the cable so that one of the cable’s discs is flus the end of the final cable cut, this is
necessary to prevent the center conductor from becoming misaligned in the coring tool.
Remove the jacket using an MC
2
jacket removal tool. This tool rotates round the cable and removes jacket
material without scoring the aluminum. A knife is not recommended for this process. Remove any MigraHeal
compound that may be on the shield.
Remove the proper amount of shield and dielectric with the MC
2
coring tool. Slide the cable into the tool until it
stops. With slight forward pressure, twist the coring tool (either by hand or mechanically with the ratchet or drill) so
that the blade begins to strip and core the cable. Continue to turn the coring tool until the proper trim dimensions
are achieved. Clean the dielectric and shield residue from the tool.
Clean the center conductor by using a non-metallic cleaning tool. Score the coating on the center conductor at
the shield and scrape it toward the end of the conductor. The conductor is clean if the copper is bright and shiny.
DO NOT USE A KNIFE or other metal tool as it may damage the copper cladding.
Slide the shrink tubing (highly recommended) over the cable end, then attach the connector according to the
manufacturer’s instructions. Place and shrink the boot. Note: if you are using a heat-shrink boot, apply the flame
carefully. Overuse of the torch may melt the jacket and dielectric.
Plant Maintenance 7.1
Overview
Plant Maintenance
CommScope Cable actually requires very little maintenance once installed. However, periodic inspection may
reveal small problems that can be corrected before they become large ones.
Aerial Trunk and Distribution Cable and Connectors
Worn or broken lashing wire can create serious performance problems, such as wind-caused deformation
which can impact the characteristic impedance of the cable. Loose lashing can also be the cause of jacket
abrasion which can cause water to migrate through the cable and lead to its mechanical breakdown. If this
sort of damage is detected, CommScope recommends that the entire span be replaced.
Replacing damaged connectors is best done with an extension connector. This is done because there is rarely
any excess cable in the span. While it is tempting to use some of the cable in the expansion loop, to do so
would degrade the loop and cause premature failure of the span.
Underground Trunk and Distribution Cable
Check the plant periodically for signs of physical damage or any exposed shielding. Use a TDR to see if there
is any sign of degraded performance at the point of suspected damage. Cover and protect any exposed
shield. Replace any damaged cable.
8.1 Appendix
Introduction
Construction Safety Issues
Construction of a broadband cable system requires a substantial amount of manpower, tools and equipment.
Underground and aerial construction will expose the manpower, tools and equipment to hazards, dependent on
field conditions and circumstances.
The Occupational Safety and Health Administration (OSHA) defines a qualified employee as “any worker who
by reason of training and experience has demonstrated his ability to safely perform his duties.” Only a qualified
employee should be assigned duties that could cause harm or potential harm to the construction crew, general
public, cable plant, and other utilities.
This manual cannot identify the many hazards that exist in the construction
environment, nor can it dictate the caution required with all of the tools, equipment
and field conditions. CommScope continues this manual with the assumption that the
construction personnel performing the work are qualified employees.
Three sets of national codes and standards apply to the construction of cable
systems. Section 1910.268 of the OSHA Safety and Health Standards applies to
work in telecommunications centers and field installations. The National Electric Code
(NEC) applies to building utilization wiring, i.e. inside plant construction. The NEC applies specifically, but is not
limited to, plant that is within or on public and private buildings or other structures. The National Electric Safety
Code (NESC), generally applies to outside plant construction.
The ability
to recognize
and avoid
hazards is
required of all
construction
personnel
Municipal, state, county, and local codes are often applied to the construction of cable systems or work that
involves their respective properties and right-of-ways. Pole Lease Agreements often stipulate specific practices
related to safety.
These codes, regulations, and specified practices should be investigated, interpreted, communicated and
observed.
Appendix 8.2
OSHA and NEC Standards
Occupational Safety and Health Administration (OSHA) Standards
OSHA Standards were established in 1970 to help ensure workplace safety. The Standards are federal
regulations that are intended to enable employers and employees to recognize, understand, and control hazards
in the workplace. Standards have been established for general industry while some sections of the Standards are
dedicated to specific industries such as telecommunications.
The generally applicable OSHA standards are found in:
Title 29 CFR Parts 1901.1 to 1910.441 General Industry, (OSHA), Order No. 869-019-00111-5
Excavations (OSHA 2226), Order No. 029-01600125-5
Underground Construction (Tunneling) (OSHA 3115)
Stairways and Ladders (OSHA 3124)
Copies of OSHA standards can be obtained from:
Superintendent of Documents
U.S. Government Printing Office
Washington, DC 20402
(202) 783-3238
National Electric Code (NEC) standards
The NEC typically identifies the construction techniques and materials necessary in building wiring requirements,
i.e., inside plant construction, of fiber optic or coaxial cable systems. The NEC has been developed by the
National Fire Protection Association’s (NFPA’s) National Electric Code committee. Committee members are
professionals from the electrical industry. The NEC addresses safety from fire and electrocution. The NEC has
been adopted by the American National Standards Institute (ANSI).
Copies of NEC standards can be obtained from:
National Fire Protection Association
1 Batterymarch Park/P.O. Box 9146
Quincy, MA 02269-3555
(800) 344-3555
8.3 Appendix
NEC and Other Ratings
NEC Articles 820
NEC article 820 deals with broadband coaxial cable. Traditional coax networks carry a low-voltage radio
frequency (RF) signal. The voltage is so low that it is not considered dangerous. NEC article 820 is written with
fire safety, not voltage, in mind.
Look for the cable rating on the jacket. The cable ratings are:
Plenum-rated cables, designed for use in plenums, ducts and air handling
spaces, carry the strictest NEC rating.
Riser-rated cables are used in vertical shafts that penetrate more than one
floor.
General purpose-rated cables may be used in locations other than plenums
or risers.
Residential-rated cables are for use in one, two and multi-family dwellings
and in raceways.
Buried cables are for use underground alone or in conduit. This rating only
concerns NEC 830 applications.
Appendix 8.4
NESC Standards and Construction Grades
National Electric Safety Code (NESC) Standards and Construction Grades
The NESC defines grades of construction on the basis of strength requirements for reasons of safety. Section 24
of the NESC identifies construction grades B (the highest), C, D and N (the lowest).
Grade D construction typically applies to broadband coaxial cable and fiber optic cable. Construction grades B
or C may be applicable dependent on the situations that exist. If more than one grade of construction applies to
a situation, the higher grade will apply. A qualified engineer should evaluate required construction and dictate
the grade of construction. The strength requirements for the various grades of construction are defined within
Section 26 of the NESC.
The NESC typically identifies the construction techniques and materials necessary in outside plant construction
of electric supply or communication cable systems. The NESC is an American National Standard that has been
written by a group of professionals that are concerned about the Standard’s scope and provisions. The NESC
has been adopted by the American National Standards Institute (ANSI). All references to the NESC in this
manual are from the 2002 edition.
Special attention should be given to NESC Table 232-1, Vertical Clearance of Wires, Conductors, and Cables
Above Ground, Roadway, Rail, or Water Surfaces which is reproduced in part on the next page.
Copies of NESC standards can be obtained from:
IEEE Service Center
445 Hoes Lane/P.O. Box 1331
Piscataway, NJ 08855-1331
(800) 678-4333
8.5 Appendix
Wire Clearance
NESC Table 232-1/Vertical Clearance of Wires
This chart shows the clearances required for a coaxial cable, isolated communication conductors and cable,
messengers and surge-protected wire meeting NESC Rule 230C1, depending on the type of surface it is above.
For a complete listing, please contact the NESC at the address on previous page.
Roads, streets, and other areas subject to truck traffic 15.5 (4.7)
Driveways, parking lots and alleys 15.5 (4.7)
Other land traversed by vehicles,
such as cultivated, grazing, forest, orchard, etc. 15.5 (4.7)
Spaces and ways subject to pedestrians or restricted traffic only 9.5 (2.9)
Water areas not suitable for sailboating or where sailboating is prohibited 14.0 (4.0)
Water areas suitable for sailboating with an unobstructed surface area of:
Less than 20 acres 17.5 (5.3)
Over 20 to 200 acres 25.5 (7.8)
Over 200 to 2000 acres 31.5 (9.6)
Over 2000 acres 37.5 (11.4)
Land adjoining water areas posted for rigging or launching sailboats with an
unobstructed surface area of:
Less than 20 acres 22.5 (6.8)
Over 20 to 200 acres 30.5 (9.3)
Over 200 to 2000 acres 36.5 (11.1)
Over 2000 acres 42.5 (12.9)
Appendix 8.6
Pole Lease Agreements and Other Codes
Pole Lease Agreements and Other Codes and Regulations
Pole Lease Agreements
Cable system operators often enter into contractual agreements with the owners of utility poles. The pole
owners are municipalities, telephone companies, and power companies. There are often specific safety practices
that are specified in the contract. These safety practices may be more restrictive than other codes and standards.
The contractual agreements should be investigated for safety requirements. The requirements should be interpreted, communicated and accordingly observed.
State, Local, and Municipal Codes
State, local and municipal codes may also apply to the construction of the cable
system. These codes will vary by location. These codes will have to be identified
and applied as required on a location specific basis.
Governing Code or Regulation
The more restrictive code or regulation must always be practiced.
The most
restrictive code
or regulation
is the one
that must
be practiced
8.7 Appendix
Equipment/Benders
Equipment/Benders and Dynamometers
Mechanical Bender
Uses a mechanical wrenching action to bend
expansion loops into QR cable prior to lashing
or during splicing. Mechanical benders are
preferred to bender boards due to the
consistency of their bends.
For cables .625 or smaller, expansion loops
should be formed with a bender that makes a
12” flat bottom loop that is 6” deep.
For cables larger than .625, expansion loops should be formed with a bender that makes a 15” flat bottom
loop that is 6” deep.
Breakaway Swivel
Used to prevent excessive pulling tension. It is designed
to break should it exceed a pre-set tension limit.
Appendix 8.8
Equipment/Blocks
Equipment/Blocks
Multiple Cable Block
Used to support multiple
cables in independent
rollers. Multiple cable
blocks make a cable
positioner unnecessary
when lashing multiple
cables.
Single Roller Block
Typically used to support
a single cable prior to
lashing and may be used
when cables are lashed
directly to strand or in
overlash applications.
In new strand situations,
single roller blocks may be
locked onto the strand. In
overlash applications, this
block should not be pushed
in front of the lasher.
Pole Mount
Cable Block
Used to install
self-support cable and
is attached to the pole
hardware to support the
cable as it is pulled out.
Economy Block
Used to support a single
cable prior to lashing
and, depending on the
actual block, may be
used when cables are
lashed directly to strand
or in overlash
applications.
8.9 Appendix
Equipment/Blocks, Chutes and Brackets
Equipment/Blocks, Chutes and Brackets
90° Corner Block
Used to route cables through inside or outside corners up to 90°.
It minimizes drag on the cable in corners and ensures that the
minimum bend radius of the cable is not exceeded. Requires
specialized mounting hardware depending on the specific use of
the equipment.
45° Corner Block
Used to route cables through inside or outside corners up to 45°.
It minimizes drag on the cable in corners and ensures that the
minimum bend radius of the cable is not exceeded. 45° corner
blocks may be used as a set-up chute to guide cables from the
cable trailer or a reel stand. Requires specialized mounting
hardware depending on the specific use of the equipment.
Set-Up Chute
A set-up chute is used to guide cables from the cable trailer or
reel stand. This equipment requires specialized mounting
hardware depending on the specific use of the equipment.
Set-Up Bracket
This bracket is used to support 45°
and 90° corner blocks or set-up chutes
at mid-span.
Appendix 8.10
Equipment/Lashers, Pullers, Positioners and Guides
Equipment/Lashers, Pullers, Positioners and Guides
Cable Lasher
Used to lash cable
directly to installed
strand or cable
bundles. Lashers are
somewhat specific to
cable and strand size
- improper lasher size or
adjustment may damage
cables.
Multiple Cable Puller
Allows multiple cables to be pulled into place
when lashing
cables directly
to strand. It’s
equipped with a
strand brake to
prevent sagging of cables as the pulling tension
is released. Allows pulled cables to independently swivel.
Overlash Cable Puller
Allows multiple cables to be pulled into place in
overlash applications.
Allows pulled cables
to independently
swivel.
Cable Block Pusher (or Shotgun or Shuttle)
Used to push equipment ahead of a pulled lasher.
Cable Positioner (or Magic Box)
Pushed in front of a lasher
by a cable block pusher
to uniformly position multiple cables that are being
lashed.
Cable Guide
Used to guide the cable into the lasher in drive-off
applications. Can be used for new strand or overlash
applications. The guide may
be pushed in front of the
lasher with a cable block
pusher, pulled in front of the
lasher or physically attached
to the lasher, dependent on
the cable guide type.
8.11 Appendix
Equipment/Lifting Tools land Brakes
Equipment/Lifting Tools and Brakes
Lay-up Stick
A fiberglass stick used to lift cable blocks and cables into place utilizing appropriate lay-up stick heads.
Cable Lifter (or Lay-up Stick Head)
Used in conjunction with a lay-up stick to lift cables into place. The lifter
ensures that the cables being lifted are not damaged by exceeding
minimum bend radii.
Cable Block Lifter
Used in conjunction with a lay-up stick to place assorted cable blocks
mid-span.
Wire Raising Tool
Used in conjunction with a lay-up stick to lift cable blocks and strand.
Strand Brake
This device is selectively placed at pole hardware locations to prevent
dangerous strand sag while strand is being installed. The strand brake
allows the strand that is being pulled into place to move in only one
direction, which is the direction of the strand pull. Use of strand brakes in
conjunction with reel brakes effectively limits the amounts of strand sag
between poles during strand installation.
Broadband Resource CenterTM 9.1
Broadband Resource Center...
Your One Stop Source for Cable Information
Responsive support and literally years of deployment experience make CommScope a unique build-out partner
capable of walking you through broadband logistics each step of the way. To design and maintain high-speed,
complex networks you’ll need advanced levels of expertise. We realize that getting your technical personnel prepared
to ascertain system requirements, understand engineering issues, select and install cable is not an insignificant hurdle.
CommScope’s Broadband Resource Center exists to help you overcome
these obstacles. Our staff has skill sets from the RF, telephony, optical
and Internet worlds. We have a menu of services to help you develop
technical competence and leadership within your own staff.
Building a reliable, future-proof broadband network requires not only
the best technology, but also experience and assistance in deploying that
technology. CommScope’s Broadband Resource Center stands ready
to assist you in your goal – the timely and cost effective deployment of
state-of-the-art broadband services.
Our management and technical staff represents over a century of combined experience in coaxial, fiber optic and
copper cable engineering and deployment. Members of CommScope’s Broadband Resource Center team hold several
patents and have been published in a variety of industry publications.
Active In Your Industry
Our employees are involved in industry trade groups such as Society of Cable
Telecommunications Engineers (SCTE), National Cable Television Association
(NCTA), Women In Cable and Telecommunications (WICT), Custom Electronics
Design and Installation Association (CEDIA) and Home Builders Association of
America (HBA).
9.2 Broadband Resource Center
Technical Services & Tools
Access to the Broadband Resource Center affords access to the a wide array of services and tools:
For more information about our Broadband Resource Center or for information on products,
please contact us by phone at 1-866-333-3272 or send us an e-mail at brc@commscope.com.
Disclaimer
Legal Disclaimer
THIS MANUAL IS PROVIDED FOR GUIDANCE PURPOSES ONLY AND SHOULD NOT BE USED OR IN ANY WAY
RELIED UPON WITHOUT CONSULTATION WITH AND SUPERVISION OF EXPERIENCED CONSTRUCTION
PERSONNEL, ENGINEERS OR NETWORK DESIGN SPECIALISTS. COMMSCOPE MAKES NO REPRESENTATIONS
OR WARRANTIES OF ANY KIND, EXPRESS OR IMPLIED, INCLUDING ANY REPRESENTATION OR WARRANTY
REGARDING THE QUALITY, CONTENT, COMPLETENESS, SUITABILITY, ADEQUACY OR ACCURACY OF THE DATA
CONTAINED HEREIN. COMMSCOPE IS UNDER NO OBLIGATION TO ISSUE ANY UPGRADES OR UPDATES OR
NOTIFY CUSTOMERS/USERS OF THIS MANUAL THAT CHANGES HAVE BEEN MADE TO THIS MANUAL. THE USER
OF THIS MANUAL ASSUMES ALL RISKS ASSOCIATED WITH SUCH USE, AND COMMSCOPE HEREBY DISCLAIMS
ANY AND ALL LIABILITY FOR DAMAGES OF ANY KIND RESULTING FROM SUCH USE.