Clenergy PV-ezRack SolarTerrace III Planning And Installation Manual

18/20 Duerdin St Tel: +61 3 9017 6688 Clayton VIC 3168, Australia Fax: +61 3 9017 6668 www.clenergy.com.au Email: sales@clenergy.com.au
PV-ezRack® SolarTerrace III
Planning and Installation Guide
Complying with AS/NZS1170.2:2011
Contents
1 Introduction 2
2 Installation Tools & Components 3
3 Installation Guide 5
4 Service 11
1. Introduction
18/20 Duerdin St Tel: +61 3 9017 6688 Clayton VIC 3168, Australia Fax: +61 3 9017 6668 www.clenergy.com.au Email: sales@clenergy.com.au
Clenergy PV-ezRack® SolarTerrace III is a pre-assembled ground mount
system suitable for large scale commercial and utility scale installations. PV-
ezRack SolarTerrace III has been developed to fit any PV module. The
innovative and patented SolarTerrace III T-Rails simplify and improve the
accuracy of the installation. Using high quality engineered components
SolarTerrace III®™ saves developers and installers, time and money when
delivering large scale projects.
Please review this manual thoroughly before installing your SolarTerrace III
system. This manual provides (1) supporting documentation for building permit
applications relating to PV-ezRack SolarTerrace III Mounting system, and (2)
planning and installation instructions for SolarTerrace III.
SolarTerrace III parts, when installed in accordance with this guide, will be
structurally adequate and will meet the AS/NZS 1170 standards. During the
installation and especially when working on the roof inform yourself about the
appropriate safety regulations, and please also pay attention to the relevant
regulations of your local region. Please check that you are using the current
version of the installation manual by contacting Clenergy Australia by email on
sales@clenergy.com.au, or your local representative.
The installer is solely responsible for:
Complying with all applicable local or national building codes, including
any that may supersede this manual;
Ensuring that PV-ezRack and other products are appropriate for the
particular installation and the installation environment;
Using only PV-ezRack parts and installer-supplied parts as specified by
PV-ezRack (substitution of parts may void the warranty and invalidate the
letter of certification on page 2);
How to recycle: according to the local relative statute. How to disassemble: Reverse installation process. Ensure that there are no less than two professionals working on panel
installation.
Ensure the installation of relative electrical equipment is performed by
professional electrician.
Ensuring safe installation of all electrical aspects of the PV array.
2. Installation Tools & Components
2.1 Installation Tools
Allen Key
18/20 Duerdin St Tel: +61 3 9017 6688 Clayton VIC 3168, Australia Fax: +61 3 9017 6668 www.clenergy.com.au Email: sales@clenergy.com.au
Power Tool Adjustable Spanner String
2.2 Component List
Overview of system components
End Clamp
Inter Clamp
T-Rail
Rail Clamp
Splice for T Rail
Assembly Support
2.3 System Components
1) End Clamp
2) Inter Clamp
3) T Rail
4) Rail Clamp
5) BackBase
6) Front Base
7) T Rail Splice
8) Truss support
18/20 Duerdin St Tel: +61 3 9017 6688 Clayton VIC 3168, Australia Fax: +61 3 9017 6668 www.clenergy.com.au Email: sales@clenergy.com.au
2.4 Installation Planning
Clenergy PV-ezRack SolarTerrace III is compatible for panels up to 1800mm long.
Design for panels 1800mm long
Design for panels 1580mm long
Minimum spacing between 2 legs:
18/20 Duerdin St Tel: +61 3 9017 6688 Clayton VIC 3168, Australia Fax: +61 3 9017 6668 www.clenergy.com.au Email: sales@clenergy.com.au
STIII Panels Up To 1.80m
Wind Zone
Region A
Region B
Region C
Region D
Wind Speed(m/s)
41
48
56
66
Leg Spacing(m)
3100
2800
2200
1500
Footing design:
We recommend using M10 Grade 5.8 Carbon Steel anchor studs with Ramset
Chemset REO502 chemical injection anchoring system. Minimum anchor
embedment depth of 90mm with concrete strength of 25MPa. For concrete
specifications see STIII engineering certificate.
L
18/20 Duerdin St Tel: +61 3 9017 6688 Clayton VIC 3168, Australia Fax: +61 3 9017 6668 www.clenergy.com.au Email: sale s@clenergy.com.au
18/20 Duerdin St Tel: +61 3 9017 6688 Clayton VIC 3168, Australia Fax: +61 3 9017 6668 www.clenergy.com.au Email: sales@clenergy.com.au
3. Installation Process
3.1 Installing the single Truss Support
3.1.1 Unfold the folded Truss support then Bolt the enforcement tube to the bottom of the back leg. Fasten the bolts and nuts pre-assembled to secure the structure.
3.1.2 Connect the front and rear legs to the bolts pre­installed on the ground or screw the legs using anchor screws.
3.1.3 Make sure the other connections on the components are tighten.
PV-ezRack Solar Terrace III_Planing and Installation Guide_V1.2 (Rev 1) Page 8 of 11
18/20 Duerdin St Tel: +61 3 9017 6688 Clayton VIC 3168, Australia Fax: +61 3 9017 6668 www.clenergy.com.au Email: sales@clenergy.com.au
3.1.4 According to the planning, repeat the above operation. Note that the all Tri-Groove Beam must be in the same line.
3.2 Installing the T Rails
3.2.1 Before installing the T Rails, mark the position of the rails on the beam. Note: Clenergy will preassemble the bottom rail clamp when supplying the product for large projects.
3.2.2 Before installing the T Rails to the Tri-groove beam, make sure the rail is long enough, otherwise connect the T rails using T rail splice.
It’s recommended to connect the rails before installing them on the Tri-groove Beam
PV-ezRack Solar Terrace III_Planing and Installation Guide_V1.2 (Rev 1) Page 9 of 11
18/20 Duerdin St Tel: +61 3 9017 6688 Clayton VIC 3168, Australia Fax: +61 3 9017 6668 www.clenergy.com.au Email: sales@clenergy.com.au
3.2.3 Install the rails according to 3.2.1.
3.2.3 Mark the panel array perimeter and attach T Rail to Tri­groove Beam with one T Rail Clamp on each side.
3.2.4 Install the other rails. Note: The end of the rails
must line up.
PV-ezRack Solar Terrace III_Planing and Installation Guide_V1.2 (Rev 1) Page 10 of 11
18/20 Duerdin St Tel: +61 3 9017 6688 Clayton VIC 3168, Australia Fax: +61 3 9017 6668 www.clenergy.com.au Email: sales@clenergy.com.au
3.3 Installating PV panels
3.3.1 Install the panels by using patented Clenergy End Clamps and Inter Clamps. Clenergy recommends 750-1000mm rail overhang at the end of the array. It can be maximum 50% of the spacing between the STIII supports.
3.3.2 Install the second row of panels making sure to leave an 18mm gap between the two rows.
3.3.3 Now the installation is completed.
PV-ezRack Solar Terrace III_Planing and Installation Guide_V1.2 (Rev 1) Page 11 of 11
18/20 Duerdin St Tel: +61 3 9017 6688 Clayton VIC 3168, Australia Fax: +61 3 9017 6668 www.clenergy.com.au Email: sales@clenergy.com.au
10 Years Standard Warranty Terms and Conditions 20 Year Designed Service Life
Clenergy international co. Ltd warrants to the original purchaser (“Purchaser”) of product(s) that it manufactures (“Product”) at the original installation site that the
Product shall be free from defects in material and workmanship for a period of ten (10) years, except for the anodised finish, which finish shall be free from visible peeling, or cracking or chalking under normal atmospheric conditions for a period of five (5) years, from the earlier of 1) the date the installation of the Product is completed, or 2) 30 days after the purchase of the Product by the original Purchaser (“Finish Warranty”). The Finish Warranty does not apply to any foreign residue deposited on the finish. All installations in corrosive atmospheric conditions are excluded. The Finish Warranty is VOID if the practices specified by AAMA 609 & 610-02 – “Cleaning and Maintenance for Architecturally Finished Aluminium” (www.aamanet.org) are not followed by Purchaser. This Warranty does not cover damage to the Product that occurs during its shipment, storage, or installation. This Warranty shall be VOID if installation of the Product is not performed in
accordance with Clenergy’s written installation instructions, or if the Product has been
modified, repaired, or reworked in a manner not previously authorized by Clenergy IN WRITING, or if the Product is installed in an environment for which it was not designed. Clenergy shall not be liable for consequential, contingent or incidental damages arising out of the use of the Product by Purchaser under any circumstances. If within the specified Warranty periods the Product shall be reasonably proven to be defective, then Clenergy shall repair or replace the defective Product, or any part
thereof, in Clenergy’s sole discretion. Such repair or replacement shall completely
satisfy and discharge all of Clenergy’s liability with respect to this limited Warranty. Under no circumstances shall Clenergy be liable for special, indirect or consequential damages arising out of or related to use by Purchaser of the Product. Manufacturers of related items, such as PV modules and flashings, may provide written