Nitrogen Generator NiGen GC Nigen MICRO
11
4.
Installation
4.1.
Installation area requirements
4.1.1.
Environment
The area where the generator is installed must meet the requirements listed under
par. 3.2.7.
m
in particular, check if ventilation is adequate. Do not install the generator into a closed cabinet with insufficient ventilation.
In regards to ventilation, refer to
par. 2.2.
4.2.
Generator positioning
4.2.1.
Packaging removal
• Open the packaging from the top
• remove the box containing the accessories
• lift the generator by grasping its side handles (two people are needed for this
operation) and set it momentarily on a flat surface
• remove the support base and place it on the desk where you plan to install the
generator.
e
It is recommended to store the packaging to ensure adequate protection when
moved in the future.
If the generator is to be installed on the tower see the attached.
4.2.2.
Positioning
Position the generator on its support base (two people are needed for this operation).
m
Ensure a clearance of at least 20cm at the rear of the generator. There
must be no potential sources of sparks in this clearance at the rear of
the generator, such as: flames, electrical contacts, hot surfaces, moving parts that can generate sparks, etc.
m
To not decrease ventilation efficiency, also ensure a clearance of at least 20cm at the front of the generator.
The generatore must be positioned on the apposite base, following foregoing instructions:
• place the base in the installation site (you can adjust the plastic feet to the desired height);