The first thing an installer physically does once onsite is to check to see that all equipment and materials
have arrived, as well as to make sure all necessary documents and forms are available.
6.2 BWX 8415 Basestation Radio Unit (RU) Installation
6.2.1 Overview
CautionOnly trained and qualified personnel should be allowed to install, replace, or service this
equipment. Statement 1030
OL-19519-01
Caution- Refer installation and service to qualified service personnel only. No user serviceable parts inside.
- Installation must be done in accordance with the instructions contained in this manual.
- Read these instructions before installing.
- Save these instructions.
Warning
Installation of the equipment must comply with local and national electrical codes.
The Radio Unit (RU) is a lightweight unit that connects easily with the Antenna Unit (AU) to form the
complete BWX 8415 Basestaion (BS). All customer accessible connectors will be located on the bottom
of the RU (
Note that the circuit cards inside the BS are not field replaceable. Therefore, if a severe fault occurs, the
entire unit is removed and replaced. The design intent is to cut down on the time it takes to troubleshoot
or otherwise have a field support person onsite.
Figure 6-1).
BWX 8415 Basestation Installation and Commissioning Guide
Statement 1074
6-1
6.2.1 Overview
Chapter 6 Installation
PRELIMINARY
Figure 6-1BWX 8415 RU Connectors
Warning
DC Power
DC Power
DC Power
(RTN/RTN/-48V/-48V/GND)
(RTN/RTN/-48V/-48V/GND)
(RTN/RTN/-48V/-48V/GND)
Fiber-optic Port
Fiber-optic Port
Fiber-optic Port
( Amphenol Connector)
( Amphenol Connector)
( Amphenol Connector)
The fiber-optic port, console port (RJ-45 connector), GPS antenna port, and the DC power connections
(two -48V, 2 RTN, and one GND) are located on the bottom of the RU.
At no time should a field person remove the RU’s cover or otherwise open the unit. In fact, doing so
may void the warranty.
Console Port
Console Port
Console Port
(RJ-45, Engineering use only)
(RJ-45, Engineering use only)
(RJ-45, Engineering use only)
GPS Antenna Port
GPS Antenna Port
GPS Antenna Port
(Type N, female)
(Type N, female)
(Type N, female)
6-2
BWX 8415 Basestation Installation and Commissioning Guide
OL-19519-01
Chapter 6 Installation
6.2.2 BWX 8415 Basestation Radio Unit Field Testing
PRELIMINARY
6.2.2 BWX 8415 Basestation Radio Unit Field Testing
THIS SECTION WAS WRITTEN/DEVELOPED, BASED ON THE FIELD TEST KIT LIST OF
MATERIALS AND VERBAL DESCRIPTIONS OF HOW THE FIELD TEST KIT IS INTENDED
TO BE USED. ONCE THE FIELD TEST KIT IS DEVELOPED, THIS SECTION WILL BE
UPDATED TO REFLECT THE ACTUAL EQUIPMENT.
It is recommended that the RU be tested, to ensure that the unit is functioning properly, prior to
installation into the AU. Perform the following steps to connect the RU to the Field Test kit and test the
RU.
Step 1Connect the RU to the Fan/Cal Board assembly. Refer to Figure 6-2.
- Connect the RU to the fans/cooling system
- Connect the RU to the Cal board (using the 9 RF cables included in the Field Test kit)
- Connect the GPS antenna to the GPS Antenna port on the bottom of the RU.
Figure 6-2RU to Fan/Cal Board Assembly Connection
Step 2Connect a ground cable to the RU ground. Tighten the nuts to 48in. lbs. (5.4 Nm). Refer to Figure 6-3.
Step 3Connect the DC power cable leads (2 RTN and 2 -48V) to the RU. Tighten the nuts to 48in. lbs.
(5.4 Nm). Refer to Figure 6-3.
Figure 6-3Ground Cable and DC Power Cable Connections
Step 4Connect an RJ-45-to-DB-9 serial cable to the Console port on the RU and to the Field Technician’s
laptop PC.
- Using a terminal application (such as TeraTerm or Hyperterminal), set the following port
parameters:
Baud Rate: 9600
Data: 8 bit
Parity: None
Stop: 1 bit
Flow Control: None
OL-19519-01
Step 5Power up the RU by connecting the DC power cable to a DC power source (48V power supply).
NoteOnce the RU is powered up, it will begin to boot. The boot process can be monitored from the terminal
application on the laptop PC.
Step 6Modify the bootline parameters as necessary. (MORE DETAILS ONCE FIELD TEST KIT IS
AVAILABLE)
BWX 8415 Basestation Installation and Commissioning Guide
6-3
6.2.3 Install the Radio Unit
Step 7Once the bootup is completed, perform a calibration to verify the RU is functioning properly. (MORE
DETAILS ONCE FIELD TEST KIT IS AVAILABLE)
Step 8After the calibration has been completed successfully, power down the RU. Disconnect the RU from the
DC power source.
Step 9Disconnect the ground cable and DC power leads from the RU.
Step 10Disconnect the RF cables and GPS cable from the RU.
Step 11Disconnect the fans/cooling system.
6.2.3 Install the Radio Unit
Chapter 6 Installation
PRELIMINARY
Warning
Do not work on the system or connect or disconnect cables during periods of lightning activity.
Statement 1001
Warning
Step 1Remove the two lower faceplate covers on the back of the AU, to access the RF calibration board and
Ensure that the power to the RU unit is OFF before installing the unit into the AU.
CautionDo not attempt to insert the RU into the AU without removing the lower faceplate covers. These faceplate
covers have a mechanical interlock pin, which inserts into the RU, and if the faceplate covers are not
removed when inserting the RU, damage could occur to the RU and the mechanical interlock pins.
Step 2Insert the RU into the AU, as shown in Figure 6-5.
BWX 8415 Basestation Installation and Commissioning Guide
OL-19519-01
Chapter 6 Installation
6.2.3 Install the Radio Unit
PRELIMINARY
Figure 6-5Inserting the RU into the AU
Step 3Connect the RF cables and the Cal cable, coming from the RF calibration board, to the RF connectors
and Cal connector on the RU unit.
Step 4Replace the faceplate covers. Be sure to insert the pin on the faceplate covers into the mechanical
interlock holes on the AU and RU units, these holes should align when the RU is inserted into the AU.
CautionEnsure that the faceplate covers are properly secured to prevent water from leaking into the unit.
Step 5Install the lower manifold.
CautionEnsure that the lower manifold is properly secured to ensure that the air flow for the heat exchangers is
contained within the unit.
Step 6Install the I/O cable cover. (It is not necessary to completely tighten these covers at this time. The covers
are being installed to prevent them from swinging while the BWX 8415 Basestation is being hoisted.)
Step 7Once installed, proceed to the next section of this Guide.
NoteTo remove the RU, after it has been installed, refer to Appendix F, “Radio Unit Removal”.
OL-19519-01
BWX 8415 Basestation Installation and Commissioning Guide
6-5
Loading...
+ 11 hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.