CIAT Ereba He Series Instruction Manual

10195
05 - 2019
Instruction manual
EREBA He
Heat Pumps
Inverter Reversible Air-to-Water
CONTENTS
ACRONYMS AND LEGEND .................................................................................5
Acronyms .......................................................................................................................5
Control Configuration Legend ..........................................................................................5
Standard installation Legend ...........................................................................................6
1 - INTRODUCTION ..............................................................................................7
1.1 - Introduction ..............................................................................................................7
1.2 - Safety.......................................................................................................................7
1.3 - Preliminary checks ..................................................................................................13
1.4 - Dimensions and clearance for EREBA He units ......................................................14
1.5 - Physical data and electrical data of EREBA He units ..............................................16
1.6 - Accessories ............................................................................................................18
2 - INSTALLATION OF UNIT ...............................................................................19
2.1 - General ...................................................................................................................19
2.2 - Moving and placing the unit ....................................................................................19
2.3 - Water connections ..................................................................................................21
2.4 - Electrical connections .............................................................................................26
2.5 - Water flow rate control ............................................................................................28
2.6 - Commissioning modes ...........................................................................................32
2.7 - Check before start the unit ......................................................................................32
3 - INSTALLATION OF SYSTEM .........................................................................33
3.1 - General customer electrical connection on terminal block ......................................33
3.2 - First step of configuration: Setting the time and day ................................................34
3.3 - Second step of configuration: Parameter menu ......................................................35
3.4 - Installation with electrical booster heaters ..............................................................36
3.5 - Installation with DHW production ............................................................................39
3.6 - Installation with boiler ..............................................................................................43
3.7 - Installation with DHW and pool heating production, boiler and buffer tank ..............46
3.8 - Master / Slave installation .......................................................................................49
3.9 - Unit with remote user interface................................................................................54
3.10 - Additional OAT sensor ..........................................................................................56
3.11 - IAT sensor .............................................................................................................56
4 - OPERATION ...................................................................................................58
4.1 - Unit range - EREBA He ...........................................................................................58
4.2 - Operating modes ...................................................................................................58
4.3 - Major system components ......................................................................................72
EREBA He
EN-2
CONTENTS
5 - MAINTENANCE ..............................................................................................75
5.1 - Standard maintenance ............................................................................................75
5.2 - Tightening torques for the main electrical connections ...........................................77
5.3 - Air heat exchanger ..................................................................................................77
5.4 - Water heat exchanger maintenance ........................................................................77
5.5 - Unit maintenance ....................................................................................................77
5.6 - Refrigerant volume ..................................................................................................77
5.7 - Characteristics of R-410A .......................................................................................78
6 - ALARM DESCRIPTION ..................................................................................79
6.1 - Inverter board alarm codes (only for 11-15 kW 1Ph or 3Ph units) ...........................79
6.2 - Alarm listing ............................................................................................................80
7 - PARAMETERS OVERVIEW ............................................................................83
7.1 - Parameters list ........................................................................................................83
7.2 - Description of customized DI/DO configurations .....................................................90
8 - START-UP CHECKLIST FOR EREBA He HEAT PUMPS (USE FOR JOB FILE) .. 91
8.1 - General information ................................................................................................91
8.2 - Available options and accessories ..........................................................................91
8.3 - Checks before start of unit ......................................................................................92
8.4 - Checks during operation of unit ..............................................................................92
8.5 - Maintenance checks ...............................................................................................93
TABLES CONTENT
Table 1: Minimum and maximum wire section (per phase) for connection to EREBA He
units ..................................................................................................................27
Table 2: Steps to clean, purge, and define a flow rate for hydraulic circuit .......................29
Table 3:
Table 4: Different operating modes .................................................................................59
Table 5: Possible switches to install on system ...............................................................60
Table 6: Different configurations of pump .......................................................................68
Table 7: Different control logic for main pump .................................................................69
Table 8: Different control logic for additional pump ..........................................................69
Table 9: Alarms listing .....................................................................................................80
Actions in WUI parameter menu or Service tools to activate the cleaning purge and
control of flow rate for hydraulic circuit ...................................................................... 29
GRAPHICS CONTENT
Graphic 1: Available static pressure for 5 to 15 kW units with hydraulic module ..............31
EN-3
EREBA He
FIGURES CONTENT
Figure 1: Transport configuration .....................................................................................19
Figure 2: Offloading configuration ...................................................................................19
Figure 3 : How to remove front panel for 11 & 15 kW units ..............................................20
Figure 4 : How to remove front panel for 5 & 7 kW units ..................................................20
Figure 5 : Opening cable knockouts ................................................................................21
Figure 6: Water connection on unit ..................................................................................23
Figure 7: Typical diagram of the hydraulic circuit with the hydraulic module ....................24
Figure 8: Hydraulic module equipped with variable speed single pump low available pressure
with expansion tank ........................................................................................25
Figure 9: Power connection with Main Switch .................................................................26
Figure 10: Customer electrical connection on terminal block .........................................33
Figure 11: Password screen ............................................................................................35
Figure 12: Standard installation with electrical booster heaters.......................................37
Figure 13: Electrical connection on terminal block for electrical booster heaters ............38
Figure 14: Standard installation with DHW production ....................................................40
Figure 15: Electrical connection on terminal block for DHW production ..........................41
Figure 16: Standard installation with boiler ......................................................................44
Figure 17: Electrical connection on terminal block for boiler............................................45
Figure 18: Standard installation with DHW production, pool heating production ans space
heating (floor heating or radiator/fan coils) .....................................................47
Figure 19: Electrical connection on terminal block for DHW, speace heating, pool heating
production and boiler ......................................................................................48
Figure 20: Standard installation with Master / Slave (example with 3 slaves) ..................50
Figure 21: Electrical connection on terminal block for Master / Slave installation ............51
Figure 22: WUI screen for Slave 1 ...................................................................................54
Figure 23: Electrical connection of remote interface .......................................................54
Figure 24: Electrical connection of additional OAT sensor and IAT sensor ......................56
Figure 25: Winter position for unit with hydraulic module .................................................65
Figure 26: Operation of booster and backup ...................................................................69
Figure 27: Activation and configuration for drying mode .................................................71
EREBA He
EN-4
ACRONYMS AND LEGEND
Acronyms
IAT
BPHE
CHWS
DHW
EHS
EWT
FCU
LWT
NHC
OAT
PMV
SHC
TR
UFC
UFH
WUI
Control Configuration Legend
Indoor Air Temperature
Brazed Plate Heat Exchanger
Chiller Water System
Domestic Hot Water
Electric Heater Stage
Entering Water Temperature
Fan Coil Unit
Leaving Water Temperature
New Hydraulic Control (refer to wiring diagram 'Main control card')
Outdoor Air Temperature
Pulse Modulating Valve
Space Heating / Cooling Control
Refrigerant Temperature
Underfloor Cooling
Underfloor Heating
User Interface (Wall-mounted User Interface)
Number of parameter
Steps Table Par. Designation Description Range Default Ex. Unit
Different steps to be done to configure the unit
Possible to configure by direct access on WUI. Refer to WUI end user Manual.
Check to be done
Advanced Configuration Level (for basic operation no need to modify the setting)
Name of the table to be used in Customer Com. Bus
Name of parameter to be used in Customer Com. Bus
Description of different value which can take the parameter
Range of parameter
Value by Default of parameter
Value given in example and adapted at the described case
Unit of parameter
EN-5
EREBA He
ACRONYMS AND LEGEND
Standard installation Legend
Label Symbol Designation Notes
-
-
-
-
-
-
Acc
Acc
Add EXP-T
- Boiler Boiler used to boost or backup the heat pump for comfort
EH1 & EH2
EH3
EH3
Device Field supplied
Accessory Field mounted
Option Factory mounted
Balancing valve
Stop valve Field supplied
Automatic Air vent
Additional expansion tank
Electrical Heater (1 or 2)
DHW-Electrical Heater Backup (1 stage)
Field supplied Balancing to adjust the water flow rate
Field supplied Automatic air vent(s) on highest position in the loop
Field supplied Additional expansion tank depending the total water in the loop contend - taking in account the expansion tank (XXL) embedded in hydraulic module
Electrical heaters up to two with a max. stages up to 3 Used to boost or backup the heat pump for comfort
Domestic Hot Water Electrical Heater - one stage used to backup DHW (when condtions are out of heat pump map)
DHW-T
DHW-S
DHW-V
add_pmp
De-Coupling
Tank
Backup-EH
-
HTSS
B
AB
EH1 EH2
HTSS
T>Tmax
Domestic Hot Water - Tank Field supplied
Domestic Hot Water - Sensor
A
Domestic Hot Water - Valve or Diverting valve
Additional Water Pump
De-Coupling Tank
Backup electrical heater
Flexible
High Temperature Safety Switch
Accessory to mount on top of the DHW-Tank Measure DHW-Temperature
Accessory to be field mounted, it will position the valve to send either to comfort loop or DHW-T, the processed water
Field Supplied, it is used for comfort loop as a secondary loop
Field Supplied, it is used to connect different water loop rates as well as to receive the boiler loop
Field Supplied, it is used for comfort loop as a Booster Heater (HP+EH) or Backup (EH only) when HP is out of the map.
Field supply, it is used to lower vibrations transmissions if necessary
Field supplied, use to stop system when UFH max, water temperature is triggered
EREBA He
EN-6
1 - INTRODUCTION
1.1 - Introduction
Prior to the initial start-up of the EREBA He units, the people involved should be thoroughly familiar with these instructions and technical data for the installation.
This appliance can be used by children aged from 8 years and above and persons with reduced physical, sensory or mental capabilities or lack of experience and knowledge if they have been given supervision or instruction concerning use of
The EREBA He outdoor systems are designed to provide a very high level of
the appliance in a safe way and understand the hazards involved.
safety and reliability making installation, start-up, operation and maintenance easier and more secure. They will provide safe and reliable service when operated within their application range.
They are designed for an operating life of 15 years by assuming a 75% utilisation factor; that is approximately 100,000 operating hours.
The procedures in this manual are arranged in the sequence required for machine installation, start-up, operation and maintenance.
Children shall not play with the appliance. Cleaning and user maintenance shall not be made by children without supervision.
Do not remove the pallet or the packaging
until the unit is in its nal position. These
units can be moved with a fork lift truck, as long as the forks are positioned in the right place and direction on the unit.
The units can also be lifted with slings (refer to Figure 1 and 2).
Use slings with the correct capacity, and always follow the lifting instructions on the
certied drawings supplied for the unit.
Be sure you understand and follow the procedures and safety precautions contained in the instructions supplied with the machine, as well as those listed in this guide, such as: protective clothing such as gloves, safety glasses, safety shoes and appropriate tools, and suitable qualifications (electrical, air conditioning, local legislation).
To find out, if these products comply with European directives (machine safety, low voltage, electromagnetic compatibility, equipment under pressure, etc.) check the declarations of conformity for these products.
Safety is only guaranteed, if these instructions are carefully followed. If this is not the case, there is a risk of material deterioration and injuries to personnel.
DO NOT COVER ANY PROTECTION DEVICES.
This applies to fuse plugs and relief valves (if used) in the refrigerant or heat transfer medium circuits. Check if the original protection plugs are still present at the valve outlets. These plugs are generally made of plastic and should not be used. If they are still present, please remove them. Install devices at the valve outlets or
1.2 - Safety
1.2.1 - Installation safety considerations
After the unit has been received, and before it is started up, it must be inspected for damage. Check that the refrigerant circuits are intact, especially that no components or pipes have shifted or been damaged (e.g. following a
drain piping that prevent the penetration of foreign bodies (dust, building debris, etc.) and atmospheric agents (water can form rust or ice). These devices, as well as the drain piping, must not impair operation and not lead to a pressure drop that is higher than 10% of the control pressure.
shock). If in doubt, carry out a leak tightness check. If damage is detected upon receipt and before signature, immediately file a claim with the shipping company.
EN-7
EREBA He
1 - INTRODUCTION
Control:
When the unit is subjected to re, the uid may then be decomposed into toxic residues when subjected to the ame :
- Stay away from the unit.
- Set up warnings and
recommendations for personnel in charge to stop the fire.
components are given on the nameplate or in the required documentation, supplied with the products.
The units are intended to be stored and operate in an environment where the ambient temperature must not be less than the lowest allowable temperature indicated on the nameplate.
- Fire extinguishers appropriate to
the system and the refrigerant type must be easily accessible.
Do not introduce signicant static or
dynamic pressure with regard to the operating pressures used during operation
All precautions concerning handling of refrigerant must be observed in accordance
or for tests in the refrigerant circuit or in the
heat exchange circuits.
with local regulations.
NOTES:
Accumulation of refrigerant in an enclosed
space can displace oxygen and cause asphyxiation or explosions.
Monitoring during operation, re-
qualication, re-testing, exemption from
retesting:
Inhalation of high concentrations of vapour is harmful and may cause heart irregularities, unconsciousness, or death. Vapour is heavier than air and reduces the
amount of oxygen available for breathing.
These products cause eye and skin irritation. Decomposition products can be hazardous.
Short-circuit power
This equipment complies with EN 61000­3-12 provided that the short-circuit power Ssc is greater than or equal to 1,6 MVA at the interface point between the user’s supply and the public system. It is the responsibility of the installer or user of the equipment to ensure, by consultation with the distribution network operator if necessary, that the equipment is connected only to a supply with a short-circuit power Ssc greater than or equal to 1,6 MVA.
1.2.2 - Equipment and components under pressure
These products incorporate equipment or components under pressure, produced by manufacturers. We recommend that you consult your appropriate national trade association or the owner of the equipment or components under pressure (declaration, re-qualification, retesting, etc.). The characteristics of this equipment/these
● Follow local regulations on the monitoring of pressure-containing equipment.
● The user or the operator is usually requested to create and maintain a monitoring and maintenance register.
● In absence of regulation or in addition to the regulations, follow the guidance in ISO 5149.
● Follow the local professional
recommendations, whenever they exist.
● Regularly monitor the surface of the components to detect cavernous corrosion. To do this check an uninsulated part of the pressure vessel or at a joint in the insulation.
● Regularly check for possible presence of impurities (e.g. silicon grains) in the heat
exchange fluids. These impurities can
cause wear and/or pitting corrosion.
Filter the heat exchange fluid.
● The reports of the periodical checks by the user or the operator must be included in the monitoring and maintenance register.
EREBA He
EN-8
1 - INTRODUCTION
Repair:
Any repair or modication of a pressure
vessel is prohibited. Only the replacement of the vessel by
an original part from the manufacturer is allowed. In this case, the replacement must
be carried out by a qualied technician. The
replacement of the vessel must be entered in the monitoring and maintenance register.
Recycling: The pressure equipment can be recycled in
whole or in part. After use they may contain
protective clothing. Never work on a unit that is still energized.
Never work on any of the electrical components, until the general power supply to the unit has been cut.
If any maintenance operations are carried out on the unit, lock the power supply circuit in the open position and secure the machine upstream with a padlock.
If the work is interrupted, always ensure that all circuits are still de-energized before
resuming the work. refrigerant vapours and oil residue. Some parts are painted.
1.2.3 - Maintenance safety considerations
Professional technicians working on the electric or refrigeration components must be authorized, trained and fully qualified to do so.
All refrigerant circuit work must be carried out by a trained person, fully qualified to work on these units. He must have been trained and be familiar with the equipment and the installation. All welding operations must be carried out by qualified specialists.
The units use high-pressure R-410A refrigerant (the unit operating pressure is above 40 bar, the pressure at 35°C air temperature is 50% higher than for R-22). Special equipment must be used when working on the refrigerant circuit (pressure gauge, charge transfer, etc.).
Do not clean the unit with hot water or steam. This may cause a pressure increase of the refrigerant.
Any manipulation (opening or closing) of a shut-off valve must be carried out
by a qualied and authorised technician,
observing applicable standards (e.g. during draining operations). The unit must be switched off while this is done.
Even if the unit has been switched off, the power circuit remains energized, unless the unit or customer circuit disconnect switch is open. Refer to the wiring diagram for further details. Attach appropriate safety labels. When working in a fan area,
specically if the grilles have to be
removed, isolate the power supply to the fans to prevent their operation.
The variable frequency drives
(VFD) tted to the units have circuit
capacitors whose discharge time is
ve (5) minutes after disconnecting
the power supply. Therefore, after disconnecting the
power supply of the control box, wait
for 5 minutes before access it. Before any intervention, verify that
there is no voltage present at any accessible conducting parts of the power circuit.
Moreover be careful of contact with zones at hot temperature inside
the unit, which can exist after the
operation of unit (refrigerant and electronic parts).
During any handling, maintenance and
service operations the qualied technician
working on the unit must be equipped with safety gloves, safety glasses, shoes and
EN-9
EREBA He
1 - INTRODUCTION
It is recommended to install an indicating device to show if part of the refrigerant has leaked from the valve.
The presence of oil at the outlet orice
is a useful indicator that refrigerant
has leaked. Keep this orice clean to
ensure that any leaks are obvious. The calibration of a valve that has leaked is generally lower than its original calibration. The new calibration may affect the operating range. To avoid nuisance tripping or leaks, replace or re-calibrate the valve.
OPERATING CHECKS:
● IMPORTANT INFORMATION REGARDING THE REFRIGERANT USED:
This product contains uorinated
greenhouse gas covered by the Kyoto protocol.
Refrigerant type: R-410A
6. The gas recovery for recycling, regeneration or destruction is at customer charge.
7. Periodic leak tests have to be carried out by the customer or by third parties. The EU regulation set the periodicity here after:
System WITHOUT leakage detection
System WITH leakage detection
Refrigerant charge/circuit (CO
equivalent)
2
R134A (GWP 1430)
R407C (GWP 1774)
R410A (GWP 2088)
HFO’s: R1234ze
Refrigerant charge/
Circuit (kg)
(1) From 01/01/2017, units must be equipped with a leakage detection system
No Check 12 Months 6 Months 3 Months
No Check 24 Months 12 Months 6 Months
< 5 Tons
Charge <
3.5 kg
Charge <
2.8 kg
Charge <
2.4 kg
No requirement
5 ≤ Charge
< 50 Tons
3.5 ≤
Charge <
34.9 kg
2.8 ≤
Charge <
28.2 kg
2.4 ≤
Charge <
23.9 kg
50 ≤ Charge
< 500 Tons
34.9 ≤
Charge <
349.7 kg
28.2 ≤
Charge <
281.9 kg
23.9 ≤
Charge <
239.5 kg
Charge > 500 Tons(1)
Charge >
349.7 kg
Charge >
281.9 kg
Charge >
239.5 kg
Global Warming Potential (GWP): 2088 Periodic inspections for refrigerant leaks
may be required depending on European or local legislation. Please contact your local dealer for more information.
1. Any intervention on the refrigerant circuit of this product should be performed in accordance with the applicable legislation. In the EU, the regulation is called F-Gas, N°517/2014.
2. Ensure that the refrigerant is never released to the atmosphere during installation, maintenance or equipment disposal.
3. The deliberate gas release into the atmosphere is not allowed.
4. If a refrigerant leak is detected, ensure that it is stopped and repaired as quickly as possible.
5. Only a qualified and certified personnel can perform installation operations, maintenance, refrigerant circuit leak test as well as the equipment disposal and the refrigerant recovering.
8. A logbook must be established for equipments subject to periodic leak tests. It should contain the quantity and the type of fluid present within the installation (added and recovered), the quantity of recycled fluid, regenerated or destroyed, the date and output of the leak test, the designation of the operator and its belonging company, etc.
9. Contact your local dealer or installer if you have any questions.
Protection device checks:
If no national regulations exist, check the protection devices on site in accordance with standard ISO 5149: every five years
for external relief valves.
NOTE: The following statements are only indicated if a pressure switch is available on the unit.
The company or organisation that conducts a pressure switch test shall establish and implement a detailed procedure to fix:
- Safety measures
- Measuring equipment calibration
- Validating operation of protective devices
EREBA He
EN-10
1 - INTRODUCTION
- Test protocols
- Recommissioning of the equipment.
Consult Service for this type of test. The manufacturer mentions here only the principle of a test without removing the pressure switch:
- Verify and record the setpoints of pressure switches and relief devices (valves and possible rupture discs)
- Be ready to switch-off the main disconnect switch (on the unit or on the installation) of the power supply if the pressure switch does not trigger (avoid over-pressure)
- Connect a calibrated pressure gauge (with Schrader female port of ½ UNF)
Inspect the protection devices such as valves.
If the machine operates in a corrosive environment, inspect the protection devices more frequently.
Check regularly for leaks and repair immediately. Ensure regularly that the vibration levels remain acceptable and close to those at the initial unit start-up.
Before opening a refrigerant circuit, transfer the refrigerant to bottles
specically provided for this purpose
and consult the pressure gauges. Change the refrigerant after an
equipment failure, following a procedure such as the one described in NF E29-795 or carry out a refrigerant analysis in a specialist laboratory.
If the refrigerant circuit remains open after an intervention (such as a component replacement, etc.):
● Seal the openings if the duration is less than a day
● If more than 1 day, charge the
circuit with oxygen free nitrogen
(inertia principle).
The objective is to prevent penetration of atmospheric humidity and the resulting corrosion.
1.2.4 - Repair safety considerations
All installation parts must be maintained by the personnel in charge to avoid deterioration and injury. Faults and leaks must be repaired immediately. The authorized technician must have the responsibility to repair the fault immediately. After each unit repair check the operation of the protection devices and create a 100% parameter operation report.
Comply with the regulations and recommendations in unit and HVAC installation safety standards, such as: ISO
5149.
If the supply cord is damaged, it must be replaced by the manufacturer, its service
agent or similarly qualied persons in order
to avoid a hazard. RISK OF EXPLOSION
Never use air or a gas containing oxygen
during leak tests to purge lines or to pressurise a machine. Pressurised air
mixtures or gases containing oxygen can be the cause of an explosion. Oxygen reacts
violently with oil and grease. Only use dry nitrogen for leak tests, possibly
with an appropriate tracer gas. If the recommendations above are not
observed, this can have serious or even fatal consequences and damage the installation.
Never exceed the specied maximum
operating pressures. Verify the allowable
maximum high- and low-side test pressures
by checking the instructions in this manual and the pressures given on the unit name plate.
Do not unweld or amecut the refrigerant
lines or any refrigerant circuit component until all refrigerant (liquid and vapour) as well as the oil have been removed from the heat pump. Traces of vapour should be displaced with dry nitrogen. Refrigerant in contact with
an open ame can produce toxic gases.
The necessary protection equipment
must be available, and appropriate re extinguishers for the system and the
refrigerant type used must be within easy reach.
EN-11
EREBA He
1 - INTRODUCTION
Do not siphon refrigerant. Avoid spilling liquid refrigerant on skin
or splashing it into the eyes. Use safety goggles and safety gloves. Wash any spills from the skin with soap and water. If liquid refrigerant enters the eyes, immediately
and abundantly ush the eyes with water
and consult a doctor. The accidental releases of the refrigerant,
due to small leaks or signicant discharges following the rupture of a pipe or an unexpected
release from a relief valve, can cause frostbites
and burns to personnel exposed. Do not
ignore such injuries. Installers, owners and especially service technicians for these units must:
- Seek medical attention before
treating such injuries.
- Have access to a first-aid kit,
especially for treating eye injuries.
We recommend to apply standard ISO 5149.
Never apply an open ame or live steam to a
refrigerant circuit. Dangerous overpressure can result.
During refrigerant removal and storage operations follow applicable regulations. These regulations, permitting conditioning and recovery of halogenated hydrocarbons under optimum quality conditions for the products and optimum safety conditions for people, property and the environment are described in standard NF E29-795.
The units must never be modied to add
refrigerant and oil charging, removal and purging devices. All these devices are provided with the units.
Be sure pressure is at 0 kPa and that the unit has been shut-down and de-energised before removing components or opening a circuit.
Do not attempt to repair or recondition any safety devices when corrosion or build-up of foreign material (rust, dirt, scale, etc.) is found within the valve body or mechanism. If necessary, replace the device. Do not install safety valves in series or backwards.
No part of the unit must be used as a walkway, rack or support. Periodically check and repair or if necessary replace any component or piping that shows signs of damage.
Do not step on refrigerant lines. The lines can break under the weight and release refrigerant, causing personal injury.
Do not climb on a machine. Use a platform, or staging to work at higher levels.
Use mechanical lifting equipment (crane, hoist, winch, etc.) to lift or move heavy components. For lighter components, use lifting equipment when there is a risk of slipping or losing your balance.
Refer to the certied dimensional drawings
for the units. It is dangerous and illegal to re-use
disposable (non-returnable) cylinders or
attempt to rell them. When cylinders are
empty, evacuate the remaining gas pressure, and move them to a designated place for recovery. Do not incinerate.
Do not attempt to remove refrigerant circuit
components or ttings, while the machine
is under pressure or while it is running.
EREBA He
EN-12
1 - INTRODUCTION
Use only original replacement parts for any repair or component replacement. Consult the list of replacement parts that corresponds
to the specication of the original
equipment. Do not drain water circuits containing
industrial brines, without informing the technical service department at the installation site or a competent
body rst.
Close the entering and leaving water shut-off valves and purge the unit hydraulic circuit, before working on the components installed on the
circuit (screen lter, pump, water ow switch, etc.).
Periodically inspect all valves,
ttings and pipes of the refrigerant
and hydraulic circuits to ensure that they do not show any corrosion or any signs of leaks.
It is recommended to wear ear defenders, when working near the unit and the unit is in operation.
Always ensure you are using the correct refrigerant type before recharging the unit.
Charging any refrigerant other than the original charge type (R-410A) will impair machine operation and can even lead to a destruction of the compressors. The compressors operate with R-410A and are charged with asyntheticpolyol-ester oil.
Before any intervention on the refrigerant circuit, the complete refrigerant charge must be recovered.
1.3 - Preliminary checks
Check equipment received:
● Inspect the unit for damage or missing parts. If damage is detected, or if shipment is incomplete, immediately file a claim with the shipping company.
● Confirm that the unit received is the one ordered. Compare the name plate data with the order.
● The name plate is attached to the unit in two locations:
- on the outside on one of the unit sides
- on the inside.
● The unit name plate must include the following information:
- Model number - size
- CE marking
- Serial number
- Year of manufacture, pressure and leaktightness test date
- Fluid being transported
- Refrigerant used
- Refrigerant charge per circuit
- PS: Min./max. allowable pressure (high and low pressure side)
- TS: Min./max. allowable temperature (high and low pressure side)
- Unit leak test pressure
- Voltage, frequency, number of phases
- Maximum power input
- Unit net weight
● Confirm that all options ordered for on-site installation have been delivered, and are complete and undamaged.
The unit must be checked periodically, if necessary removing the insulation (thermal, acoustic), during its whole operating life to ensure that no shocks (handling accessories, tools, etc.) have damaged it. If necessary, the damaged parts must be repaired or replaced. See also chapter §5. Maintenance.
EN-13
EREBA He
1 - INTRODUCTION
1.4 - Dimensions and clearance for EREBA He units
1.4.1 - Dimensions and location of hydraulic connections
A
L
a
B
C
A
D
b
G
F
c
E
H
L
a
B
C
EREBA He A B C D E F G H L masse (kg)
5_1Ph 908 821 326 350 87 356 466 40 60 57
7_1Ph 908 821 326 350 87 356 466 40 60 69
11_1Ph 908 1363 326 350 169 645 744 43 73 115
15_1Ph 908 1363 326 350 169 645 744 43 73 115
11_3Ph 908 1363 326 350 169 645 744 43 73 121
15_3Ph 908 1363 326 350 169 645 744 43 73 121
NOTE : Dimensions are given in mm
b
G
D
c
F
E
H
EREBA He
EN-14
1 - INTRODUCTION
1.4.2 - Clearances to ensure the correct air flow
The picture presents the minimal distances of the wall to ensure the correct air flow on air
(1)
heat exchanger
.
200
500
150
150
003051
150
1000
1000
500
1000
150150
300300
300
200
1000
200
300
(1) Anticipate different maintenance actions before to place the unit (access of different parts / opening of panel/ part replacement…)
300
1000
300
000200510001
200
EN-15
EREBA He
1 - INTRODUCTION
1.5 - Physical data and electrical data of EREBA He units
1.5.1 - Physical data EREBA He
EREBA He 5 (1Ph) 7 (1Ph) 11 (1Ph) 15 (1Ph) 11 (3Ph) 15 (3Ph)
Sound levels
Standard unit
Sound power level
Sound pressure level at 10 m
Dimensions
Length mm 908 908 908 908 908 908
Width mm 350 350 350 350 350 350
Height mm 821 821 1363 1363 1363 1363
Operating Weight
Standard unit kg 57 69 107 115 121 121
Compressors Rotary compressor 1 1 1 1 1 1
Refrigerant R410A
(1)
Charge
Capacity control
Minimum capacity
Condenser Grooved copper tubes, aluminium ns
Fans Axial type
Quantity 1 1 2 2 2 2
Maximum total air flow l/s 800 800 1800 1800 1800 1800
Maximum rotational speed rpm 560 660 820 820 820 820
Evaporator Brazed plate heat exchanger
Water volume l 1,7 2,3 4,4 4,4 4,4 4,4
Hydraulic module Circulator, relief valve, paddle ow switch, expansion tank
Circulator Centrifugal pump (variable speed)
Expansion tank volume l 2 2 3 3 3 3
Max. water-side operating pressure with hydraulic module
Water connections
Inlet diameter (BSP GAS) inch 1 1 1 1 1 1
Outlet diameter (BSP GAS) inch 1 1 1 1 1 1
Chassis paint colour Colour code: RAL 7035 RAL 7035 RAL 7035 RAL 7035 RAL 7035 RAL 7035
(1) Values are guidelines only. Refer to the unit nameplate. (2) In dB ref=10
in accordance with ISO 9614-1 and certified by Eurovent.
(3) In dB ref 20 μPa, (A) weighting. Declared dualnumber noise emission values in accordance with ISO 4871 (with an associated uncertainty of +/-3dB(A)). For information,
calculated from the sound power level Lw(A). (4) Min. water-side operating pressure with variable speed hydraulic module is 40 kPa. (5) Cooling Eurovent condition
(2)
(3)
(1)
dB(A) 64 65 68 69 69 69
dB(A) 33 34 37 38 38 38
kg 1,1 1,6 2,8 2,8 3 3
(5)
(4)
-12
W, (A) weighting. Declared dualnumber noise emission values in accordance with ISO 4871 (with an associated uncertainty of +/-3dB(A)). Measured
% 23% 20% 20% 17% 20% 17%
kPa 300 300 300 300 300 300
1.5.2 - Electrical data EREBA He
EREBA He 5 (1Ph) 7 (1Ph) 11 (1Ph) 15 (1Ph) 11 (3Ph) 15 (3Ph)
Power circuit
Nominal power supply V-ph-Hz 230-1+N-50 230-1+N-50 230-1+N-50 230-1+N-50 400-3+N-50 400-3+N-50
Voltage range V 220-240 220-240 220-240 220-240 380-415 380-415
Control circuit supply 24V AC via internal transformer
Maximum unit power input (Un)
Cos Phi unit at maximum power
Maximum unit current drawn (Un-10%)
Maximum unit current drawn (Un)
Maximum Start-up current, standard unit
(1) Power input, compressors and fans, at the unit operating limits (saturated suction temperature 15 °C, saturated condensing temperature 68.3 °C) and nominal voltage
of 400 V (data given on the unit nameplate). (2) Maximum unit operating current at maximum unit power input and at 360 V. (3) Maximum unit operating current at maximum unit power input and at 400 V (values given on the unit nameplate). (4) Maximum instantaneous start-up current at operating limits (maximum operating current of the smallest compressor(s) + fan current + locked rotor current of the
largest compressor).
EREBA He
(1)
(1)
(2)
(3)
(4)
kW 1,80 3,38 4,73 5,18 10,32 10,32
0,98 0,98 0,98 0,98 0,98 0,98
A 8,9 16,7 23,3 25,6 16,8 16,8
A 8 15 21 23 15,2 15,2
A Not Applicable (less than the operating current)
EN-16
1 - INTRODUCTION
1.5.3 - Inside view
Electrical box 5 - 7 kW unit (1 Ph)
1
1
11 - 15 kW unit (1 Ph) 11 - 15 kW unit (3 Ph)
1
1
EN-17
EREBA He
1 - INTRODUCTION
1.6 - Accessories
Accessories Reference Description Advantages Utilisation
Hydraulic tubes 7187601
Rubber cushion 7447060
Floor heating thermal cut off 7274278 Floor heating protection Reduces risk of floor heating dammage EREBA He
Backup heater 5kW 7148641 Electrical backup system
Backup heater 9kW 7148642 Electrical backup system
Backup heater for 9 kW for buffer tank (100L & 200L)
Buffer tank 50L 7328746
Buffer tank 100L 7328744
Buffer tank 200L 7328747
Master / Slave sensor 7484985
Domestic hot water tank 300 L 7385910
Domestic hot water management sensor and 3 way valve
"Pool heating management sensor and 3 way valve"
Pool heating heat exchanger (ITEX POOL +)
Remote human interface Standard Remotely installed user interface
Additional outdoor ambient temperature sensor
Water filling kit 7013876 System enabling to fill the hydraulic circuit Hydraulic circuit easy filling EREBA He
DUO hydraulic module (for floor heating < 11kW)
7221389 Electrical backup system Easy and fast installation inside the buffer tank EREBA He
7411357
71111 22
7268480
7484983 Additional outdoor ambient temperature sensor Better reading of outdoor air temperature EREBA He
3911008
Tubes are used to decoupling hydraulic circuits and the units
Cushion installed under the unit to avoid vibration trasmission
Buffer tank available to resolve installions constraints
Buffer tank available to resolve installation constraints
Buffer tank available to resolve installation constraints
Unit equipped with supplementary water outlet temperature sensor kit to be field-installed allowing master/slave operation of two to four units connected in parallel
Tank designed to satisfy sanitary hot water productions
Sensor enabling to manage the water setpoint inside the tank used for domestic hot water production
Sensor enabling to manage the water setpoint used for pool heating
Essential parts to ensure good working of pool heating
This hydraulic module allows to manage two differents heat emitters (Ex: floor heating and radiators)
Reduces vibration transmission to hydraulic installation
Reduces vibration transmission EREBA He
Easy and fast installation, stepped power, hydraulic securities integrated (water relief valve, automatic purge)
Easy and fast installation, stepped power, hydraulic securities integrated (water relief valve, automatic purge)
Reduce unit cycling increasing reliability, play the roule of hydraulic separation to improve the control of water flow rate and water temperature in the system and finally, increase thermal inertia during defrost and options mode operation
Reduce unit cycling increasing reliability, play the roule of hydraulic separation to improve the control of water flow rate and water temperature in the system and increase thermal inertia during defrost and options mode operation
Reduce unit cycling increasing reliability, play the roule of hydraulic separation to improve the control of water flow rate and water temperature in the system and finally, increase thermal inertia during defrost and options mode operation
Optimised operation of chillers connected in parallel with operating time equalisation
Easy and fast installation, isolated tank to reduce heat loss
Useful for domestic hot water production EREBA He
Useful for pool heating production EREBA He
Titanium exchangers plates, removable, easy maintenance
Remote heat pump control with room temperature sensor used to offset the water control point. Possibility to configure the unit on field.
Easy and fast installation, independant control integrated
EREBA He
EREBA He
EREBA He
EREBA He
EREBA He
EREBA He
EREBA He
EREBA He
EREBA He
EREBA He
EREBA He
EREBA He
EN-18
2 - INSTALLATION OF UNIT
2.1 - General
To install an unit EREBA He the following steps are requested
1. Place the unit
2. Make hydraulic connections to filling the
system with water or brine fluid
3. Make electrical connections
4. Check for water leaks and the water flow
rate control
5. Finally, make commissioning of the unit
2.2 - Moving and placing the unit
2.2.1 - Moving
See §1.2.1 Installation safety considerations.

Figure 1: Transport configuration

2.2.2 - Placing the unit
In case of extra-high units the machine
environment must permit easy access for maintenance operations.
Always refer to § 1.4. Dimensions and
clearances to conrm that there is
adequate space for all connections and service operations. For the centre of gravity coordinates, the position of the unit mounting holes, and the weight distribution
points, refer to the certied dimensional
drawing supplied with the unit. Typical applications of these units do not
require earthquake resistance. Earthquake
resistance has not been veried.
Only use slings at the designated lifting points (refer to Figure 2 to
ofoad the unit).
Before siting the unit check that:

Figure 2: Offloading configuration

● the permitted loading at the site is adequate or that appropriate strengthening measures have been taken.
● if the unit has to operate as a heat pump in temperatures below 0°C it must be raised at least 300 mm from the ground. This is necessary to avoid ice build-up on the unit chassis and also to permit correct unit operation in locations where the snow level may reach this height.
● the unit is installed level on an even surface (maximum tolerance is 5 mm in both axes).
● there is adequate space above the unit for air flow and to ensure access to the components (see dimensional drawings).
● the number of support points is adequate and that they are in the right places.
● the location is not subject to flooding.
● for outdoor installations, where heavy snowfall is likely and long periods of sub-zero temperatures are normal, provision has to be made to prevent snow accumulating by raising the unit above the height of drifts normally experienced. Baffles may be necessary to deflect strong winds. They must not restrict air flow into the unit.
EN-19
EREBA He
2 - INSTALLATION OF UNIT
● OAT sensor, located on the coil, should not be exposed to the sun or other heat sources.
Before lifting the unit, check that
all casing panels are securely xed
in place. Lift and set down the unit with great care. Tilting and jarring can damage the unit and impair unit operation.
Never push or lever on any of the enclosure panels of the unit. Only the base of the unit frame is designed to withstand such stresses. If a unit includes a hydraulic module, the hydraulic module and pump piping must be installed in a way that does not submit it to any strain. The hydraulic module pipes must
be tted so that the pump does not
If EREBA He units are hoisted with rigging, it
support the weight of the pipes.
is advisable to protect coils against crushing while a unit is being moved. Use struts or a lifting beam to spread the slings above the unit. Do not tilt a unit more than 15°.
2.2.3 - Removing the unit panel
To access at the inside of the unit (refrigerant parts / electrical parts), the panel can be removed. This operation must be carried out by a qualified technician.

Figure 3 : How to remove front panel for 11 & 15 kW units

Figure 4 : How to remove front panel for 5 & 7 kW units

EREBA He
EN-20
2 - INSTALLATION OF UNIT

Figure 5 : Opening cable knockouts

2.2.4 - Checks before system start-up
Before the start-up of the refrigeration system, the complete installation, including the refrigeration system must be verified against the installation drawings, dimensional drawings, system piping and instrumentation diagrams, and wiring diagrams.
For these checks national regulations must be followed. If the national regulation does not specify any details, refer to standard ISO 5149 as follows:
External visual installation checks:
2.3 - Water connections
For size and position of the unit water inlet and outlet connections refer to the certified dimensional drawings supplied with the unit. The water pipes must not transmit any radial
● Ensure that the machine is charged with refrigerant. Verify on the unit nameplate
or axial force to the heat exchangers nor any vibration.
that the ‘fluid being transported’ is R-410A and is not nitrogen.
● Compare the complete installation with the refrigeration system and power circuit diag rams.
● Check that all components comply with the design specifications.
● Check that all protection documents and equipment provided by the manufacturer (dimensional drawings, P&ID, declarations etc.) to comply with
The water supply must be analysed and appropriate filtering, treatment, control devices, shut-off and bleed valves and circuits built in, to prevent corrosion (example: damage to the protection of the tube surface if the fluid is polluted), fouling and deterioration of the pump fittings.
Before any start-up verify that the heat exchange fluid is compatible with the materials and the water circuit coating.
the regulations are present.
● Verify that the environmental safety and protection and devices and arrangements provided by the manufacturer to comply with the regulations are in place.
● Verify that all documents for pressure
In case additives or other fluids than those recommended by the manufacturer are used, ensure that the fluids are not considered as a gas.
Recommendations on heat exchange uids:
containers, certificates, name plates, files, instruction manuals provided by the manufacturer to comply with the regulations are present.
● Verify the free passage of access and safety routes.
● Verify the instructions and directives to prevent the deliberate removal of refrigerant gases.
● Verify the installation of connections.
● Verify the supports and fixing elements (materials, routing and connection).
● Verify the quality of welds and other joints.
● Check the protection against mechanical damage.
● Check the protection against heat.
● Check the protection of moving parts.
● Verify the accessibility for maintenance or repair and to check the piping.
● Verify the status of the valves.
● Verify the quality of the thermal insulation and of the vapour barriers.
● No NH4+ ammonium ions in the water, they are very detrimental for copper. This is one of the most important factors for the operating life of copper piping. A content of several tenths of mg/l will badly corrode the copper over time.
EN-21
EREBA He
2 - INSTALLATION OF UNIT
● Cl- Chloride ions are detrimental for copper with a risk of perforations by corrosion by puncture. If possible keep below 10 mg/l.
2-
● SO
sulphate ions can cause perforating
4
corrosion, if their content is above 30 mg/l.
● No fluoride ions (<0.1 mg/l).
● No Fe2+ and Fe3+ ions with non negligible levels of dissolved oxygen must be present. Dissolved iron < 5 mg/l with dissolved oxygen < 5 mg/l.
● Dissolved silicon: silicon is an acid element of water and can also lead to corrosion risks. Content < 1mg/l.
● Water hardness: >0.5 mmol/l. Values between 1 and 2.5 mmol/l can be recommended. This will facilitate scale deposit that can limit corrosion of copper. Values that are too high can cause piping blockage over time. A total alkalimetric title (TAC) below 100 mg/l is desirable.
● Dissolved oxygen: Any sudden change in water oxygenation conditions must be avoided. It is as detrimental to deoxygenate the water by mixing it with inert gas as it is to over-oxygenate it by mixing it with pure oxygen. The disturbance of the oxygenation conditions encourages destabilisation of copper hydroxides and enlargement of particles.
● Electric conductivity: 0.001-0.06 S/m (10- 600 µS/cm).
● pH: Ideal case pH neutral at 20-25°C (7 < pH < 8).
Charging, adding or draining uid
from the water circuit must be done
by qualied personnel, using air
vents and materials suitable for the products. Water circuit charging
devices are eld-supplied.
The use of units in an open loop is forbidden.
2.3.1 - Operating precautions and recommendations
The water circuit should be designed to have the least number of elbows and horizontal pipe runs at different levels. Below the main points to be checked for the connection:
● Comply with the water inlet and outlet connections shown on the unit.
● Install manual or automatic air purge valves at all high points in the circuit.
● Use a pressure reducer to maintain pressure in the circuit(s) and install a relief valve as well as an expansion tank. Units with the hydraulic module include a relief valve and an expansion tank.
● Install drain connections at all low points to allow the whole circuit to be drained.
● Install stop valves, close to the entering and leaving water connections.
● Use flexible connections to reduce vibration transmission.
● Insulate all pipework, after testing for leaks, both to reduce thermal leaks and to prevent condensation.
● Use thermal tape to seal joints and to seam the insulation.
● If the external unit water pipes are in an area where the ambient temperature is likely to fall below 0°C, they must be protected against frost (frost protection solution or trace heating).
● The use of different metals on hydraulic piping could generate electrolytic pairs and consequently corrosion. Verify then, the need to install sacrificial anodes.
EREBA He
Charging and removing heat
exchange uids should be done with
devices that must be included on the water circuit by the installer. Never
use the unit heat exchangers to add heat exchange uid.
EN-22
2 - INSTALLATION OF UNIT
The plate heat exchanger can foul up quickly
at the initial unit start-up, as it complements
the lter function, and the unit operation will be impaired (reduced water ow rate due to
increased pressure drop). Units with hydraulic module are equipped
with a screen lter. Do not introduce any signicant static or
pressures). The products that may be added for thermal
insulation of the containers during the water piping connection procedure must be chemically neutral in relation to the materials and coatings to which they are applied. This is also the case for the products originally supplied by the manufacturer.
dynamic pressure into the heat exchange
circuit (with regard to the design operating
2.3.2 - General
For details on connection diameters, refer to §1.5.1 Physical data EREBA He.

Figure 6: Water connection on unit

Water inlet
Water outlet
Draining water pipe
EN-23
EREBA He
2 - INSTALLATION OF UNIT
3
2.3.3 - Minimum water loop volume
The minimum water loop volume, in litres, is given by the following formula:
Volume (l) = CAP (kW) x N
Where CAP is the nominal cooling capacity at nominal operating conditions.
Application N
Air conditioning 3,5
Heating or domestic hot water application 6
Industrial process cooling See note below
Note: For industrial process cooling applications, where high stability of water temperature levels must be achieved, the values above must be increased.We recommend consulting the factory for these particular applications.
This volume is required to obtain temperature stability and precision. To achieve this volume, it may be necessary to add a storage tank to the circuit. This tank should be equipped with baffles to allow mixing of the fluid (water or brine). Please refer to the examples below.
2.3.4 - Maximum water loop volume
Units with hydraulic module incorporate an expansion tank that limits the water loop volume. The table below gives the maximum loop volume for pure water or ethylene glycol with various concentrations.
If the total system volume is higher than the values given above, the installer must add another expansion tank, suitable for the additional volume.
Water maximum volume (L)
EREBA He
Static pressure (bar) 1,5 3
Fresh water 200 50
Ethylen glycol 10% 150 38
Ethylen glycol 20% 110 28
Ethylen glycol 30% 90 23
Ethylen glycol 40% 76 19
Bad Good
GoodBad
2.3.5 - Hydraulic circuit

Figure 7: Typical diagram of the hydraulic circuit with the hydraulic module

1
3
1
2
6
4
7
8
5
9
Legend:
1 Shut-off valves 2 Line filter for water 3 Pressure gauges 4 Filling valve 5 System drain valve 6 Air flushing valve 7 3-way valve 8 Sanitary water accumulation tank 9 Inside system
EREBA He
EN-24
The use of the hydraulic module on open loop is prohibited.
2 - INSTALLATION OF UNIT
Figure 8: Hydraulic module equipped with variable speed single pump low
available pressure with expansion tank
Hydraulic module
a
b
5 & 7 kW units
g
e
c
f
b
d
f
h
g
a
d
e
11 & 15 kW units
c
h
Legend:
a Automatic purge valve b Flow switch c Safety valve outlet d Leaving water temperature probe e Circulation pump f Plug to unblock the seizing pump g Expansion vessel h Entering water temperature probe
Minimum and maximum pressures necessary in the hydraulic circuit for correct operation of the units.
Hydraulic circuit
Variable speed hydraulic module 40 kPa (0.4 bar) 300 kPa(3 bar).
Minimum pressure at the suction of the pump to avoid the cavitation phenomena.
Maximum pressure at the suction of the pump
before the opening of the water relief valve
(1)
EN-25
EREBA He
2 - INSTALLATION OF UNIT
2.4 - Electrical connections
Please refer to the certified wiring drawings, supplied with the unit.
2.4.1 - Power supply
The power supply must conform to the specification on heat pump nameplate. The supply voltage must be within the range specified in the electrical data table. For connections refer to the wiring diagrams and the certified dimensional drawings.
After the unit has been commissioned, the power supply must only be disconnected for quick maintenance
operations (one day maximum). For
longer maintenance operations or when the unit is taken out of service and stored (e.g. during the winter or if the unit does not need to generate cooling) the power supply must be maintained to ensure supply to the electric heaters (compressor coil heater, unit frost protection).
Figure 9: Power connection with Main
Switch
3Ph 1Ph
2.4.2 - Recommended wire sections
Wire sizing is the responsibility of the installer, and depends on the characteristics and regulations applicable to each installation site. The following is only to be used as a guideline, and does not make Manufacturer in any way liable. After wire sizing has been completed, using the certified dimensional drawing, the installer must ensure easy connection and define any modifications necessary on site.
The connections provided as standard for the field-supplied power entry cables are designed for the number and type of wires, listed in the table below.
The calculations of favourable and unfavourable cases are performed by using the maximum current possible of each unit fitted with a hydraulic kit (see the tables of electrical data for the unit and the hydraulic module).
The calculation is based on PVC or XLPE insulated cables with copper core. A maximum ambient temperature of 46°C has been taken into consideration. The given wire length limits the voltage drop to < 5% (length L in metres - see table below).
5-7 1Ph+N
L N
11-15 1Ph+N
L
L N
11-15 3Ph+N
L1 L2 L3
N
IMPORTANT: Before connection of the main power cables (L1 - L2 - L3 - N - PE or L1 - N - PE) on the terminal block, it is imperative to check the correct order of the 3 phases before proceeding to the connection and the good connection of the neutral wire (if the neutral
N
conductor is not connected correctly, the unit can be damaged permanently).
EREBA He
EN-26
2 - INSTALLATION OF UNIT
Table 1: Minimum and maximum wire section (per phase) for connection to
EREBA He units
Max.
connectable
EREBA He Section Section
(per phase)
5 (1Ph) 3G4² 3G2,5² 100 H07RNF 3G2,5² 80 H07RNF
7 (1Ph) 3G4² 3G2,5² 100 H07RNF 3G2,5² 80 H07RNF
11 (1Ph) 3G4² 3G4² 100 H07RNF 3G4² 80 H07RNF
15 (1Ph) 3G4² 3G4² 100 H07RNF 3G4² 80 H07RNF
11 (3Ph) 5G4² 5G2,5² 100 H07RNF 5G2,5² 80 H07RNF
15 (3Ph) 5G4² 5G2,5² 100 H07RNF 5G2,5² 80 H07RNF
Accessory Remote WUI
Notes:
(1) Connection capacities actually available for each machine, defined according to the connection terminal size, the control box access opening size and the available
space inside the control box. (2) Selection simultation result considering the hypothesis indicated. (3) If the maximum calculated section is for an XLPE cable type, this means that a selection based on a PVC cable type can exceed the connection capacity actually
available. Special attention must be given to the selection.
Use cables H07RN-F 4x0.75 mm² up to 50m to connect the user interface WUI (not supplied with accessory)
CAUTION: Use the grey ferrite which is supplied in accessory to clamp around the WUI cable. Please clamp it directly after the customer's terminal block
section
mm²
(1)
- Suspended aerial lines (standardised routing No. 17)
- XLPE insulated cable
(per phase)
Calculation favourable case: Calculation unfavourable case:
- Conductors in conduits or multi-conductor cables in closed conduit (standardised routing No. 41)
- PVC insulated cable, if possible
mm²
Max. length for
(2)
voltage drop <5%
Cable type Section
m -
mm²
(per phase)
Max. length for
(2)
voltage drop <5%
m -
Cable type
(3)
Power cable entry
The power cables must be entered through the cable gland from the rear of the unit.
Use a black ferrite which is supplied in accessory to clamp around the supply cable. Please clamp it directly after the customer’s terminal block.
Please clamp the second one close to the cable gland.
The power cable should not be in contact with hot parts of the system.
Electrical data and operating conditions notes:
• EREBA He units have a single power connection point located immediately upstream of the field power connections.
• The control box includes the following standard features:
- Variable frequency drive for compressor, fans and pump (option)
- The control devices.
• Field connections:
All connections to the system and the electrical installations must be in full accordance with all applicable local codes.
• The ERE BA He units are designed and built in compliance with EN 60335-1 and 2
NOTES:
• The operating environment for the EREBA He units is specified below:
1. Physical environment
EN 60364:
- outdoor installation: protection level IP44
- operating temperature range: -20°C to +46°C
- storage temperature range: -20°C to +48°C
- altitude: ≤ 2000 m (see note for table 1.5.4 - Electrical data, hydraulic module)
- presence of hard solids, class AE3 (no significant dust present)
- presence of corrosive and polluting substances, class AF1 (negligible)
(2)
. The classification of environment is specified in standard
(2)
(1)
.
2.4.3 - Recommended customer electrical protection
Electrical protection is the responsibility of the installer, and depends on the characteristics and regulations applicable to each installation site. The following is only to be used as a guideline, and does not make manufacturer in any way liable.
5
EREBA He
Circuit breaker:
Type C C C C C C
Current A 10 16 25 25 16 16
Fuses:
Type gG gG gG gG gG gG
Current A 16 20 32 32 20 20
2. Power supply frequency variation: ± 2 %.
3. The neutral (N) conductor must be always connected to the unit
4. Overcurrent protection of the power supply conductors is not provided with the unit.
5. The units are designed for simplified connection on TT networks (IEC 60364).
Caution: If particular aspects of an actual installation do not conform to the conditions described above, or if there are other conditions which should be considered, always contact your local representative.
(1) The absence of main power disconnect switch is an exception that must be
taken into account at field installation level.
(2) The required protection level for this class is IP43BW (according to reference
document IEC 60529). All EREBA He units fulfil this protection condition:
- Closed electrical box is IP44
- When accessing to interface, the level is IPxxB
(1Ph)
7
(1Ph)
11
(1Ph)
15
(1Ph)
11
(3Ph)
15
(3Ph)
EN-27
EREBA He
2 - INSTALLATION OF UNIT
2.5 - Water flow rate control
2.5.1 - Water leakage
Check that the water-side connections are clean and show no sign of leakage.
2.5.2 - Minimum water flow rate
If the installation flow rate is below the minimum flow rate, there is a risk of excessive fouling.
2.5.3 - Maximum water flow rate
This is limited by the permitted water heat exchanger pressure drop.
2.5.4 - Water heat exchanger flow rate
Data applicable for:
- Fresh water 20°C
- In case of use of the glycol, the maximum water flow is reduced.
EREBA He units
Minimum water
flow rate
m3/h
5 (1Ph) 0,18 0,9 4,3
7 (1Ph) 0,42 1,2 4,3
11 (1Ph) 0,6 1,9 7,0
15 (1Ph) 0,6 2,6 7,0
11 (3Ph) 0,6 1,9 7,0
15 (3Ph) 0,6 2,6 7,0
(1) Eurovent heating conditions
Nominal water
flow rate
m3/h
Maximum water
(1)
flow rate
m3/h
2.5.5 - Nominal system water flow control
The water circulation pumps of the EREBA He units have been sized to allow the hydraulic modules to cover all possible configurations based on the specific installation conditions, i.e. for various temperature differences between the entering and the leaving water
(∆T) at full load, which can vary between 3
and 10 K.
This required difference between the entering and leaving water temperature determines the nominal system flow rate. Use this specification for the unit selection to find the system operating conditions.
In particular, collect the data to be used for the control of the system flow rate:
● Units with variable speed pump-control on adjustable constant speed: nominal flow rate,
● Units with variable speed pump - control on temperature difference: heat
exchanger ΔT (variable flow).
If the information is not available at the system start-up, contact the technical service department responsible for the installation to get it. These characteristics can be obtained from the technical literature using the unit
performance tables for a ∆T of 5 K at the
water heat exchanger.
EREBA He
EN-28
2 - INSTALLATION OF UNIT
Table 2: Steps to clean, purge, and define a flow rate for hydraulic circuit
Cleaning procedure
Purge procedure
Water flow control procedure
1 Open the manual control valve fully. No manual control valve required with Variable Speed Hydraulic module
2 Set the system pump
Read the BPHE pressure drop...
3
… by taking the difference of the readings of the pressure gauge connected to the unit inlet and outlet.
4 Let the pump run for two consecutive hours to flush the hydraulic circuit of the system (presence of solid contaminants).
5 Take another reading.
6 Compare this value to the initial value.
7 If the pressure drop…
… has decreased, this indicates that the screen filter must be removed and cleaned, as the hydraulic circuit contains solid particles.
In this case stop the pump
8
section of the unit.
9 Repeat, if necessary, to ensure that the filter is not contaminated.
1 After filling with water, wait about 24h before activating the purge procedure.
Activate the purge mode
2
switch value
3 The air purge is field-supplied.
If the purge is automatic, air will vent from circuit automatically.
If the purge is manual, open the valve to vent air from the circuit
When the circuit is cleaned and purged, activate the pump in quick test mode
1
pressures at the pressure gauges (entering water pressure - leaving water pressure), …
Compare this value to the graph of available external static pressure using the appropriate speed
3
curve (Graphic 1).
4 If the flow rate corresponding is higher, decrease pump speed
5 Proceed by successively adjusting the pump speed until the expected water flow rate is achieved.
(2)
With Variable Speed Hydraulic module
Adjustable constant speed
(1)
.
(1)
and close the shut-off valves at the water inlet and outlet and remove the screen filter after emptying the hydraulic
(1)
.
: water pump is requested to run continuously at maximum speed to purge the hydraulic circuit regardless the flow
(1)
, and vice versa.
(1)
, and read the
With Variable Speed Hydraulic
No need to adjust the flow rate because of
ΔT control.
But it is necessary to adjust the Minimum pump speed [P567]to ensure closure of flow switch
(1)
.
module ΔT
(1) For configuration details, refer to table 3. (2) CAUTION: In purge mode, the value of the flow switch is ignored, so check that there is water in the circuit, to avoid damage to the pump.
Table 3:
Actions in WUI parameter menu or Service tools to activate the cleaning
purge and control of flow rate for hydraulic circuit
Steps Table Par. Designation Description Range Default Ex. Unit
321 Quick Test enable Access to Quick test mode 0 to 1 0 1 -
331 Water Pump Speed Activate the pump 0 to 100 0 100 %
Wait around 2h that the hydraulic circuit is cleaned
331 Water Pump Speed Stop the pump 0 to 100 0 0 %
321 Quick Test enable Exit the Quick test mode 0 to 1 0 0 -
8 = Purge (water pump is constantly
REQ
44 System Mode Request
44 System Mode Request
running to purge the hydraulic circuit) 0 to 6 and 9 = not used for this
configuration
Wait that the circuit purges
To exit purge mode, change the value of [P044] with the wanted mode (0 or 1 or 2 or 4)
0 to 9 - 8 -
0 to 9 - 0 / 1 /2 /4 -
Cleaning procedure
Purge procedure
QCK_ TEST
MOD_
EN-29
EREBA He
Loading...
+ 67 hidden pages