NA 15.15 B EN - 2
1 - INTRODUCTION
The standard CONDENCIAT CL2 are outdoor air cooled condensing units equipped with :
- Low-noise scroll compressor.
- Air cooled condenser
- Axial flow fan or fans with speed regulation.
All units are factory checked and tested ; they are supplied with a full R 410A refrigerant charge.
2 - INCOMING GOODS
Check the unit and the conformity of the delivery on arrival.
If the unit has been damaged or if the delivery is incomplete, express all necessary reservations on the delivery note.
IMPORTANT: You must confirm these reservations to the shipping company by registered letter within three days following
delivery.
3 - IDENTIFICATION OF THE EQUIPMENT
A manufacturer’s data plate is fitted on each unit, with an identification number.
The number must be mentioned in all correspondence.
4 - GUARANTEE
The guarantee covers a period of 12 months after commissioning, if this occurs within the 3 months following the invoicing date.
In all other cases, it covers a period of 15 months after invoicing date.
NB : For further details, refer to the document concerning the CIAT guarantee.
5 - SAFETY RECOMMENDATIONS
To avoid all risks of accidents at the time of installation, starting-up and adjustment operations, it is essential to take into
consideration the specific aspects of the equipment such as:
- Refrigerant circuit under pressure
- Presence of refrigerant
- Presence of electrical voltage
- Location
- Temperatures up to 150°C
Only experienced, qualified persons can work on this type of equipment. It is essential to comply with the recommendations and
instructions mentioned in the maintenance manuals, on labels or specific instructions.
All standards and regulations in force must be complied with at all times.
IMPORTANT: before carrying out any work on the unit, make sure that it has been disconnected from power supply.
6 - UNIT LOCATION
Before handling, installing and connecting the unit, the installer must check the following points:
- These units must be installed in the open air, close to the building, on a flat roof or in a garden. They are designed to operate
in the rain, but can also be installed under a four-side open shelter.
- The surface of the ground or the structure must be strong enough to bear the weight of the unit.
- Place the unit above the average snow depth for the region where the unit is being installed.
- The unit must be set perfectly level.
- The unit must be fully accessible to enable servicing and maintenance work to be carried out easily.
Noise level: our units have been designed to operate at low noise levels. Nonetheless, it is necessary to make sure, at the
installation design stage, that the outside environment is suitable for radiated noise and that the type of building is suitable for
airborne and solid-borne noise (vibrations).
Have a study carried out by an acoustician if necessary.
7 - WEIGHT AND HANDING
Once the location has been selected for the unit, install the equipment. Take the weight and the overall measurements of the unit
into account (see the technical characteristics table and the «Dimensions» paragraph).
.
Attention: lift the unit carefully and keep it upright at all times.
8 - OPERATING LIMITS
The CL2 has to operate within the limits below :
Minimum Maximum
Outdoor temperature -15°C +45°C
Evaporating temperature -20°C +12.5°C