ChargePoint CT4000 Family, CT4000 SERIES Installation Manual

Installation
Guide
ChargePoint, Inc. 1692 Dell Ave. Campbell, CA 95008-6901 USA US toll free: +1-877-370-3802 www.chargepoint.com
Document P/N: 75-001084-01 Rev. 3
SAVE THESE IMPORTANT SAFETY INSTRUCTIONS
This manual contains important instructions that must be followed during installation of a ChargePoint® Networked Charging Station.
Grounding instructions
The ChargePoint® Charging Station must be connected to a grounded, metal, permanent wiring system; or an equipment-grounding conductor is to be run with circuit conductors and connected to the equipment grounding terminal or lead on the Electric Vehicle Supply Equipment (EVSE). Connections to the EVSE shall comply with all applicable codes and ordinances.
FCC Compliance Statement
This equipment has been tested and found to comply with the limits for a Class A digital device pursuant to Part 15 of the FCC Rules. These limits are designed to provide reasonable protection against harmful interference when the equipment is operated in a commercial environment. This equipment generates, uses, and can radiate radio frequency energy and, if not installed and used in accordance with the manufacturer’s instruction manual, may cause harmful interference with radio communications. Operation of this equipment in a residential area is likely to cause harmful interference, in which case, you will be required to correct the interference at your own expense.
Important: Changes or modifi cations to this product not authorized by ChargePoint, Inc., could affect the EMC compliance and revoke your authority to operate this product.
Exposure to Radio Frequency Energy: The radiated power output of the 802.11 b/g/n radio and cellular modem (optional) in this device is below the FCC radio frequency exposure limits for uncontrolled equipment. This device should be operated with a minimum distance of at least 20 cm between the 802.11 b/g/n and cellular antennas and a person’s body and must not be co-located or operated with any other antenna or transmitter by the manufacturer, subject to the conditions of the FCC Grant.
Industry Canada
This device complies with Industry Canada license-exempt RSS standard(s). Operation is subject to the following two conditions: (1) this device may not cause interference, and (2) this device must accept any interference, including interference that may cause undesired operation of the device.
Le présent appareil est conforme aux CNR d’Industrie Canada applicables aux appareils radio exempts de licence. L’exploitation est autorisée aux deux conditions suivantes : (1) l’appareil ne doit pas produire de brouillage, et (2) l’utilisateur de l’appareil doit accepter tout brouillage radioélectrique subi, même si le brouillage est susceptible d’en compromettre le fonctionnement.
FCC/IC Compliance Labels
Go to http://www.chargepoint.com/labels/.
Safety and compliance
This document provides instructions to install the ChargePoint® Charging Station and should not be used for any other product. Before installing the ChargePoint® Charging Station, you should review this manual carefully and consult with a licensed contractor, licensed electrician and trained installation expert to ensure compliance with local building practices, climate conditions, safety standards, and all applicable codes and ordinances.
The ChargePoint® Charging Station should be installed only by a licensed contractor and a licensed electrician and in accordance with all local and national codes and standards. The ChargePoint® Charging Station should be inspected by a qualifi ed installer prior to the initial use. Under no circumstances will compliance with the information in this manual relieve the user of his/her responsibility to comply with all applicable codes or safety standards. This document describes the most commonly-used installation and mounting scenarios. If situations arise in which it is not possible to perform an installation following the procedures provided in this document, contact ChargePoint, Inc. ChargePoint, Inc. is not responsible for any damages that may occur resulting from custom installations that are not described in this document.
No accuracy guarantee
Reasonable effort was made to ensure that the specifi cations and other information in this manual are accurate and complete at the time of its publication. However, the specifi cations and other information in this manual are subject to change at any time without prior notice.
Warranty information and disclaimer
Your use of, or modifi cation to, the ChargePoint® Charging Station in a manner in which the ChargePoint® Charging Station is not intended to be used or modifi ed will void the limited warranty. Other than any such limited warranty, the ChargePoint products are provided “AS IS,” and ChargePoint, Inc. and its distributors expressly disclaim all implied warranties, including any warranty of design, merchantability, fi tness for a particular purposes and non-infringement, to the maximum extent permitted by law.
Limitation of liability
IN NO EVENT SHALL CHARGEPOINT, INC. OR ITS AUTHORIZED DISTRIBUTORS BE LIABLE FOR ANY INDIRECT, INCIDENTAL, SPECIAL, PUNITIVE, OR CONSEQUENTIAL DAMAGES, INCLUDING WITHOUT LIMITATION, LOST PROFITS, LOST DATA, LOSS OF USE, COST OF COVER, OR LOSS OR DAMAGE TO THE CHARGEPOINT® CHARGING STATION, ARISING OUT OF OR RELATING TO THE USE OR INABILITY TO USE THIS MANUAL, EVEN IF CHARGEPOINT, INC. OR ITS AUTHORIZED DISTRIBUTORS HAVE BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES.
Copyright and trademarks
©2013 ChargePoint, Inc. All rights reserved. This material is protected by the copyright laws of the United States and other countries. It may not be modifi ed, reproduced or distributed without the prior, express written consent of ChargePoint, Inc. CHARGEPOINT is a U.S. and European Union registered trademark and service mark of ChargePoint, Inc. and can not be used without the prior written consent of ChargePoint. All other products or services mentioned are the trademarks, service marks, registered trademarks or registered service marks of their respective holders. ChargePoint, Inc. has several patents fi led.
i
Contents
1 Introduction
Summary of Shipping Boxes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-1
Installation Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-2
Before Installing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-2
Specifi cations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
Dual Circuit Wiring Diagram . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4
Shared Power Wiring Diagram . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5
Grounding Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-6
2 Installing a Bollard Mount
Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1
Overview of Steps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1
Step 1: Check Boxes for Correct Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-2
Step 2: Prepare Pole/Base Plate for Mounting . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-3
Step 3: Mount Pole/Base Plate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2-4
Step 4: Install Main Body . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-5
Step 5: Prepare Retractor for Mounting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-6
Step 6: Install Retractor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-7
Step 7: Connect Wiring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-8
Step 8: Check Voltages . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-9
3 Installing a Wall Mount
Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1
Overview of Steps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1
Step 1: Check Boxes for Correct Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-2
Step 2: Drill Holes in Wall . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-3
Step 3: Mount Rear Brackets to Wall . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-4
Step 4: Prepare Retractor for Mounting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-5
Step 5: Mount Retractor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-6
Step 6: Install Conduit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-7
Step 7: Install Main Mody . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-8
Step 8: Connect Wiring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-9
Step 9: Check Voltages . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-10
ii
4 Installing the Head and Top Cap
Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1
Overview of Steps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1
Step 1: Check Boxes for Correct Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-2
Step 2: Prepare Head Assembly for Mounting . . . . . . . . . . . . . . . . . . . . . . . . . . .4-4
Step 3: Slide Head Assembly Into Body . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-6
Step 4: Connect Head Assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-7
Step 5: Verify the Station Operates Correctly . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-8
Step 6: Install Cable Clamps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-10
Step 7: Secure Head Assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4-11
5 Preparing the Station for Activation on ChargePoint
Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1
Overview of Steps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1
Step 1: Pinpoint the Station . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-2
Step 2: Document the Radio Groups . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-5
Step 3: Complete the Post-Installation Checklist . . . . . . . . . . . . . . . . . . . . . . . . . 5-6
6 Troubleshooting
Check the Station’s Display . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1
Display Station Codes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1
Description of Station Codes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-2
Charging Cable Doesn’t Move Freely . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-5
Appendix A: Preparing the Installation Site for a Bollard Mount
Appendix B: Removing or Replacing the EV Charging Sign
Appendix C: CT4000 Power Sharing Instructions
Appendix D: Limited Product Warranty
1
1-1
Introduction
This document provides step-by-step instructions on how to install a CT4000 ChargePoint® Charging Station.
Summary of Shipping Boxes
Each CT4000 charging station ships in four boxes:
Assembly name... Label on box says.... High level overview of box contents...
For Installation Instructions, see...
Top Cap
IMPORTANT: Open
this box fi rst—it contains the printed Installation Guide
CT40XX-CAP*
Chapter 4
Body CT40X1-BD or CT40X3-BD
Includes a power sharing kit (CT4020-PSHARE) that allows both ports on a dual port station to share a single 40A circuit.
Bollard Mount (CT40X1-BD):
Wall Mount (CT40X3-BD):
Chapter 2 - Bollard Chapter 3 - Wall Mount
Cord Management Retractor CT4000-CMK Chapter 2 - Bollard
Chapter 3 - Wall mount
Head CT40X0-HD* or CT40X0-HD-GW*
For gateway stations the box also includes a Network Enablement Kit, CT4000-NEK1 (US) or CT4000-NEK2 (Canada)
Chapter 4
*The last two digits of the four-digit model number depends on the station’s features. The third digit (CT40X0) is “1” if the station has a single charging port, or ‘2” if the station has two charging ports. The last digit (CT401X) is either a 1 (bollard mount) or 3 (wall mount).
NOTE: A more detailed list of the contents in each shipping box is provided in the associated chapter with the step-by-step installation instructions.
1-2
ChargePoint® Charging Stations
Installation Sequence
Regardless of the specifi c type of CT4000 charging station you are installing, and the options included, the high level installation sequence is the same:
PREPARE THE INSTALL THE INSTALL THE HEAD PREPARE THE STATION INSTALLATION SITE MOUNTING OPTION AND TOP CAP FOR ACTIVATION
Before Installing
Ensure that the appropriate wiring, circuit protection, and metering is in place at the installation location by reviewing the specifi cations, wiring diagrams, and grounding requirements in the remainder of this chapter.
Ensure that adequate CDMA (Verizon) or GSM (AT&T, Rogers) cellular coverage is available at the installation location. To ensure adequate signal strength in underground garages or other enclosed parking structures, cellular repeaters may be required.
For bollard mount charging stations, prepare the installation site by following the instructions in Appendix A. The mounting template for the bollard is stapled into the center fold of this document and a PDF version is available at
www.chargepoint.com/support-installation-guides.php. Ensure the PDF version is accurate by printing it at 100% scale on
11” x 17” paper and then verifying at least one dimension.
Review the CT4000 Data Sheet (available at www.chargepoint.com/support-product-data-sheets.php).
Review the contents of this document to familiarize yourself with the contents of each shipping box and the required installation steps.
Ensure the wiring, circuit protection, and metering is in place. Read the remainder of Chapter 1. If installing a bollard mount, also read Appendix A.
Depending on the type of station, follow the steps in either: Chapter 2 - Bollard Chapter 3 - Wall mount
Follow the steps in Chapter 4
Follow the steps in Chapter 5
1 -3
Introduction
Specifi cations
Electrical Input
Single Port Dual Port
AC Power Input Rating - Standard 208/240VAC 60Hz single phase @ 32A 208/240VAC 60Hz single phase @ 32A x 2
AC Power Input Rating - Power Sharing n/a 208/240 VAC 60Hz single phase @ 32A
Input Power Connections - Standard One 40A branch circuit. Two independent 40A branch circuits.
Input Power Connections - Power Sharing n/a One 40A branch circuit
Required Service Panel Breaker - Standard 40A dual pole (non-GFCI type) 40A dual pole (non-GFCI type) x 2
Required Service Panel Breaker - Power Sharing n/a 40A dual pole (non-GFCI type)
Service Panel GFCI Do not provide external GFCI as it may confl ict with internal GFCI (CCID)
Wiring - Standard 3-wire (L1, L2, Earth) 5-wire (L1, L1, L2, L2, Earth)
Wiring - Power Sharing n/a 3-wire (L1, L2, Earth)
Standby Power 15W typical (standby), 20W maximum (operation)
Electrical Output
AC - Standard 7.2kW (240VAC @ 30A) 7.2kW (240VAC @ 30A) x 2
AC - Power Sharing n/a 7.2kW (240VAC @ 30A) x 1 OR
3.8kW (240VAC @ 16A) x 2
Functional Interfaces
Plug(s) Type SAE J1772™ SAE J1772™ x 2
Charging Cable Length 18’ (5.5 meters) 18’ (5.5 meters) x 2
Overhead Cable Management System Yes Yes
Card Reader ISO 15693, 14443, NFC
Locking Holster Yes Yes x 2
Safety and Connectivity Features
Ground Fault Detection 20mA CCID with auto retry
Open Safety Ground Detection Continuously monitors presence of safety (green wire) ground connection
Plug-Out Detection Power terminated per SAE J1772™ specifi cations
Power Measurement Accuracy +/- 2% from 2% to full scale (32A)
Power Report/Store Interval 15 minute, aligned to hour
Local Area Network 2.4 GHz Wi-Fi (802.11 b/g/n)
Wide Area Network 3G GSM, 3G CDMA
Safety and Operational Ratings
Enclosure Rating Type 3R per UL 50E
Safety Compliance UL listed for USA and cUL certifi ed for Canada; Complies with UL 2594, UL 2231-1,
UL 2231-2, and NEC Article 625
Surge Protection 6kV @ 3000A. In geographic areas subject to frequent thunder storms, supplemental
surge protection at the service panel is recommended.
EMC Compliance FCC Part 15 Class A
Operating Temperature -22°F to 122°F (-30°C to +50°C)
Operating Humidity up to 85% @ +50°C (122°F) non-condensing
Non-operating Humidity up to 95% @ +50°C (122°F) non-condensing
Terminal Block Temperature Rating 221°F (105°C)
Maximum Charging Stations per 802.11 Radio Group
10. Each station must be located within 150 feet “line of sight” of a gateway station.
ChargePoint, Inc. reserves the right to alter product offerings and specifi cations at any time without notice, and is not responsible for typographical or graphical errors that may appear in this document.
1-4
ChargePoint® Charging Stations
Dual Circuit Wiring Diagram
The following illustration describes the wiring for installing a CT4000 on a dual circuit. Wiring for a single circuit installation is described on the next page. Grounding requirements are described on page 1-6.
NOTE: Requires two dedicated circuits, each with its own two pole 40 A breaker.
1 -5
Introduction
Shared Power Wiring Diagram
The following illustration describes the wiring for installing a dual port CT4000 on a shared single circuit. For this installation, you will need the power sharing kit to allow both ports to share a two pole 40A circuit breaker. Wiring connections are provided in Appendix C. Grounding requirements are described on page 1-6.
Wiring for a dual circuit installation, see the previous page.
TERMINAL BLOCK WITH POWER SHARING JUMPERS INSTALLED
TERMINAL BLOCK WITH POWER SHARING JUMPERS INSTALLED
1-6
ChargePoint® Charging Stations
Grounding Requirements
The voltage of either line, relative to ground, must not fall below 80 volts or a Floating Line Connection error occurs (see page 6-3). Because the voltage of either line relative to ground must not be allowed to fl uctuate, use only center­grounded systems. Neutral is not used to power the station but must be properly connected to ground, at the panel or transformer, to provide the necessary voltage reference relative to ground.
Connect to these systems
In a wye system, connect the station to ANY two lines, as shown below.
In a delta system, connect the station to a center-tapped secondary only, where the center tap is bonded and the station is connected to L1 and L3. This allows voltages to remain constant regardless of other loads that may be using the lines.
Do not connect to these systems
Do not connect ChargePoint stations to the following types of power sources:
120/208 VAC 3 phase wye, ungrounded
120/240 VAC 3 phase delta, corner-grounded
Any system where the center point of the AC power source is not grounded
2
2-1
Installing a Bollard Mount
Before You Start
Before installing a bollard mount, prepare the installation site as described in Appendix A. After preparing the installation site, you need the following:
Ratchet and 3/8” socket
1/2” drive torque wrench and 15/16” 6-point deep socket (for 5/8-11 nut)
Crescent wrench
Bubble level
#2 Phillips screwdriver
Wire stripper
Multimeter
Overview of Steps
Installing the bollard mount involves a few simple steps, summarized below and detailed in the remainder of this chapter:
1. Check Boxes for Correct Contents (page 2-2)
2. Prepare Pole/Base Plate for Mounting (page 2-3)
3. Mount Pole/Base Plate (page 2-4)
4. Install Main Body (page 2-5)
5. Prepare Retractor for Mounting (page 2-6)
6. Install Retractor (page 2-7)
7. Connect Wiring (page 2-8)
8. Check Voltages (page 2-9)
When you have completed these steps, you will be ready to install the head and top assemblies as described in Chapter 4.
2-2
ChargePoint® Charging Stations
Step 1: Check Boxes for Correct Contents
The bollard mount ships in two boxes as described below.
Main Body
Main body, pre-assembled with mounting pole/base plate, rubber bumper, and brackets (1)
Adapter plastic cap (1)
¼”-20 x 1 ¼” screws (4)
Power sharing kit (use only if installing a dual-port station on a single 40A circuit) (1)
Cable Management Kit
Retractor assembly with pre-installed “EV CHARGING ONLY” sign (1)
Cable clamps (4)
Phillips screws (10*)
*Two extra screws are included.
Main Body
Cable Management Kit
2-3
Installing a Bollard Mount
Step 2: Prepare Pole/Base Plate for Mounting
Use a 3/8” socket wrench to loosen (but not remove)
the two screws holding the pole inside the bollard.
Remove the pole/base plate assembly from the main
body by pulling it out from the bottom.
Remove and discard the cardboard shipping spacer.
Loosen the 2 screws (don’t remove)
Rubber bumper
Pole
Base plate
2-4
ChargePoint® Charging Stations
Position a level at various locations, both horizontally and vertically, including over each bolt
Align the longer curved edge to where you want to position the front of the station
Adjust the lower nuts as necessary to ensure the pole/base plate is level
When level, tighten the upper nuts
Step 3: Mount Pole/Base Plate
Prepare the installation site as described in Appendix A, then mount the pole/base plate assembly as follows:
Pull wires through conduit.
Place the pole/base plate assembly over the conduit, ensuring the long curved edge of the base plate is located where you want the front of the charging station located.
Adjust the lower nuts as necessary to ensure the mounting pole is level.
When level, tighten the nuts on top of the base plate to at least 115-120 ft-lbs.
IMPORTANT: Ensure the pole/base plate is level by adjusting the nuts underneath the base plate. Verify accuracy after each adjustment by positioning the level at various locations on the pole, above each bolt.
2-5
Installing a Bollard Mount
Step 4: Install Main Body
To install the main body:
Align the notches on the rubber bumper with the front mounting nuts, then slide it all the way down the pole until it is fl ush with the base plate. This prevents any rocking motion between the main body and the base plate.
Slide the body over the mounting pole.
Re-tighten the screws you loosened in Step 2 to approximately 80 in-lbs using a 3/8” socket wrench.
IMPORTANT: Ensure the body is fi rmly aligned to the bottom surface and that no movement (rocking) can take place, even when signifi cant pressure is applied.
Position notches (2) at front
Re-tighten the 2 screws
2-6
ChargePoint® Charging Stations
Step 5: Prepare Retractor for Mounting
To prepare the retractor for mounting:
Position the retractor packaging so that the bottom of the retractor is near the base of the bollard.
IMPORTANT: Do not unwrap the cords.
Remove and discard the two shipping screws from the front face of the retractor.
NOTE: When you remove the shipping screws, the retractor’s counterweights are free to move in either direction. Therefore, do not tilt or carry the retractor
assembly with the top end lower than the bottom end.
Remove the foam packaging from the retractor.
OPTIONAL: If necessary, remove or replace the EV PARKING sign. See Appendix B.
Discard shipping screws
Top
Bottom
When handling, always keep the top end higher than the bottom end.
2-7
Installing a Bollard Mount
Step 6: Install Retractor
To install the retractor:
Insert the black cap into the space at the top of the
main body, between the main body and the retractor, as shown.
With a Phillips screwdriver and at least one of the
four ¼” - 20 x 1 ¼” screws in hand, position the retractor against the back of the main body. Place the slot at the bottom of the retractor over the knob at the bottom of the main body, as shown.
IMPORTANT: Hold the retractor in place until
you’ve secured it with at least one screw.
From inside the main body, insert the four ¼” - 20 x
1 ¼” screws through the main body and the retractor, and tighten to 60 in-lbs.
2-8
ChargePoint® Charging Stations
Step 7: Connect Wiring
IMPORTANT: To power a dual-port station using a single 40A circuit, use the Power Sharing Kit (CT4020-PSHARE) provided in the shipping box with the main body. Instead of following the instructions below, see Appendix C. You must also manually confi gure the station for power sharing, as described in Appendix C.
If you are not installing a power sharing kit, connect the wiring as follows:
Strip wires ½” (13 mm).
1/2” (13 mm)
Push the black tab on the terminal block to release the
terminal block cover, then slide the cover up until it locks into the raised position:
Lift the corresponding white lever on the terminal block,
insert the ground wire into the center connector, then push the lever down until it clicks into its fully closed position.
Lift the corresponding white levers, insert the 240 VAC L1
and L2 wires, then push the levers down until they click into their fully closed position.
WARNINGS:
Use copper conductors only.
Do NOT provide GFCI protection at panel. The CT4000
has built-in GFCI protection.
In areas with frequent thunder storms, add surge
protection at the service panel for all circuits.
Use new circuit breakers only. Used breakers can
damage equipment and introduce the potential for an electrical fi re.
Ensure all power and ground connections, especially
those at the breaker and buss bar, are clean and tight. Remove all oxide from all conductors and terminals before connecting wiring.
LEFT
L1
RIGHT
L1
GND
LEFT
L2
RIGHT
L2
For single port stations, use the connectors indicated for “RIGHT” side only.
For dual port stations:
2-9
Installing a Bollard Mount
Step 8: Check Voltages
Turn power ON.
Using a solenoid type voltage tester, check that the voltages at the charging station’s terminal block are as follows:
Measure Between Volts
L1 and L2 208/240
GND and L1 120
GND and L2 120
If the voltages are not as expected, ensure that the wiring has been properly connected as describing on the previous page. For detailed wiring diagrams and grounding requirements, see pages 1-4 to 1-6.
Before continuing, resolve any wiring issues and ensure that voltages are as expected.
Turn power OFF.
2-10
ChargePoint® Charging Stations
You have now fi nished installing the bollard mount and are ready to install the head assembly and top cap. See Chapter 4.
3
3-1
Installing a Wall Mount
Before You Start
You need the following:
Drill and Tap for appropriate wall attachment hardware
Attachment hardware, such as 3/8” (9.5 mm) x 3” (76 mm) lag bolts if mounting to a wood wall
Ratchet and 9/16” deep socket
#2 Phillips screwdriver
Tape measure
Bubble level
Marker
Wire stripper
Multimeter
Overview of Steps
Installing the wall mount involves a few simple steps, summarized below and detailed in the remainder of this chapter:
1. Check Boxes for Correct Contents (page 3-2)
2. Drill Holes in Wall (page 3-3)
3. Mount Rear Brackets to Wall (page 3-4)
4. Prepare Retractor for Mounting (page 3-5)
5. Mount Retractor (page 3-6)
6. Install Conduit (page 3-7)
7. Install Main Body (page 3-8)
8. Connect Wiring (page 3-9)
9. Check Voltages (page 3-10)
When you have completed these steps, you will be ready to install the head and top cap as described in Chapter 4.
3-2
ChargePoint® Charging Stations
Step 1: Check Boxes for Correct Contents
The wall mount ships in two boxes as described below.
Main Body and Mounting Kit
Main body, pre-assembled (1)
Mounting brackets with pre-installed screws and fl ange bolts (2 sets)
NOTE: The packing box for the brackets serves as a template for drilling mounting holes. Do not discard
packaging until you’ve completed Step 2.
Slot cover (2)*
Power sharing kit (use only if installing a dual-port station on a single 40A circuit) (1)
*One extra slot cover is included.
Cable Management Kit
Retractor assembly (1)
Cable clamps (4)
Phillips screws (10**)
**Two extra screws are included.
Main Body and Mounting Kit
Cable Management Kit
3-3
Installing a Wall Mount
Step 2: Drill Holes in Wall
The packing box for the brackets is used as a
template for drilling the wall holes. Tear the packing box along the perforation to allow it to lay fl at.
Place the template against the wall. As described on
the package insert, align the top where indicated, 49” above the fl oor or ground. Ensure that the template is level and the side of the packaging insert is plumb. Mark the four mounting holes.
Drill four holes in the wall at the marked locations.
NOTE:
If mounting to a hollow wall, bridge at least two
studs using a 1 5/8” channel strut. For wood studs, use 3/8” (9.5 mm) lag bolts that are long enough to penetrate at least 2 1/2” into the stud. Then mount the supplied brackets to the channel strut using 3/8­16 x 1” long bolts, 3/8 ID x 13/16” OD washers, and 3/8-16 channel strut nuts.
If mounting to a masonry wall, use 3/8” (9.5 mm)
expanding masonry fasteners.
If mounting to a wood wall, use 3/8” (9.5 mm) x 3”
(76 mm) lag bolts.
Loading...
+ 51 hidden pages