installation guideinstallation guide
10’
(2)
24”
(1)
48”
16”
(4)
6”
(3)
3”
Product Specications
Width 1.25 inch
Height 4.25 inch
Depth 1 inch
Weight .025 lbs
Max Spacing 48” on center
Recommended Load 36 lbs ~ 3 drywall layers
Max Safe Load 46 lbs ~ 4 drywall layers
Fail Load 300 lbs ~ 27 drywall layers
Green Glue Noiseproong Clip layout
(1) Clips are spaced no further than
48 inches apart horizontally
(2) Hat channel must not be spaced
more than 24 inches vertically
(3) Bottom clips must be less than 3
inches from the oor
(4) Top clips must be less than 6
inches from the ceiling
*Clips must be placed at the outermost
studs on every piece of hat channel
Layout pattern for Green Glue Noiseproong Clips
Step 1
Measure for placement of Green Glue Noiseproong Clips using layout guidelines listed above.
Mark locations and install clips using appropriate screws.
Recommended screws by stud type
Wood: Use #8 x 2-1/2”
coarse thread screws
Steel: Use #8, 10 or 12 x 1-5/8”
Type S self-tapping screws
Concrete: Use 3/16” dia x 2-1/4”
Tapcon or equal anchor Screw
Install ceiling drywall before walls to allow for a
Outermost clips must be spaced at every interval
re stop by butting ceiling drywall to studs
www.greengluecompany.com866.435.8893
installation guide
Step 2
Snap appropriate hat channel into clips
Recommended hat channel
Size: 25 gauge hemmed edges
Depth: 7/8”
Width Top: 1 ¼”
Width Bottom: 2 ½”
Most walls will require you to overlap hat channel, instructions for doing
so are as follows. Overlap 6 inches of hat channel between two clips.
Secure the hat channel with two 7/16” framing screws. 18 gauge tie-wire
can also be used.
Step 4
Be sure to use an acoustical sealant to ll gaps around electrical
boxes, windows, doors, and areas below or above sheets of
drywall. Green Glue Noiseproong Sealant is perfect for this
application as it allows exability while stopping sound from
transmitting through unsealed areas.
Step 3
Place shims on the oor to allow spacing between the
drywall and the ooring. This ensures decoupling from
the oor to make it impossible for vibrations to travel
from wall to oor and vice-verse.
Screw drywall in place through hat channel. Be sure
drywall is fully installed before removing shims from
underneath.
www.greengluecompany.com866.435.8893