Start up of the boiler
13.0. START UP OF THE BOILER
The start up has to be done by the person authorized on behalf of Centrometal d.o.o.
It is necessary the check if previous assemblage has been performed exactly according to
the requirements and description of this manual.
Additional following has to be check:
- the boiler and the central heating system have to be filled with water and air vented.
- the security elements are functioning and if they are correctly connected.
- the flue gas tube is well connected, insulated, and sealed.
- flue gas damper is properly set according to the chimney under pressure
- Are the cyclone and fan properly set to the boiler and the cyclone is well insulated.
- all objects, which eventually could have been left inside the boiler are removed (from the
combustion chamber, exhaust tubes, etc.). Some objects could have been put inside
during the assemblage for any reason and could negatively influence the functioning.
- the upper and lower door of the boiler and door of the primary air is well set (seal
properly).
- the primary air/cleaning door properly fits
- the air lid on the door for primary air can freely move – when boiler do not work must be
closed.
- the secondary air lid on the lower boiler door is closed
- the heating room has proper air circulation opening.
- the tube thermostat of the boiler's security pump is set to 65°C (the pump is functioning
from 0°C to 65°C)
- the tube thermostat of the heating circuit pump is set up to 75°C (the pump is functioning
above 75°C)
The start up procedure includes also:
- starting of at least one heating process during which the functioning of the lid in the flue
gas exhaust and the fan regulation thermostat has to be set, so that the temperature
inside the boiler during a normal firing process does not exceed 90°C and does not
decrease below 75°C.
- check the outlet water temperature during functioning, because this temperature should
not be under 60°C. If it happens the system should be accordingly set up.
- secondary air flow opening is set (can also be closed)
- training the person in charge of the boiler room, training protocol signed by the trained
person.