Carrier 16JA User Manual

Page 1
ti
Hermetic Absorption Liquid Chillers
Carrier
MACHINE OPERATION

MACHINE START-STOP SYSTEMS

General - The exact start-stop system for a given
machine is established by the customer. Systems can vary from one installation to another. These systems and procedures are meant for general guidelines only.
The three most common types of systems are given below. Review these systems and decide which applies to your machine. Then follow the start-stop procedure given.
NOTE: If machine has been shut down for more than 2 days, follow procedures under Start-Up
After Limited Shutdown or Start-Up After Extended Shutdown. In all cases below, when machine starts, the white run light will en
ergize. When the machine stops, the light will
go out after automatic dilution.
Automatic Start-Stop System - Starting and stop
ping with this system is accomplished by an automatic controller such as a thermostat or time clock, etc. Also, an AUTO-MANUAL switch is provided so the machine can be started by­pressing machine START button with switch in
MANUAL position. All auxiliary equipment is
tied in with the machine control circuit and will
start when the machine starts. If automatic time delay relays are provided, the machine will start
after a preselected time interval.
The operating engineer must make periodic checks to ensure that the machine with auxiliary equipment is operating satisfactorily.
PROCEDURES
1. Place AUTO-MANUAL switch in the AUTOpo-
sition for the machine to start or stop automat ically. The automatic controller determines when the machine starts or stops.
2. To start fully automatic machines after limited or extended shutdown place the AUTO-MANUAL
switch in MANUAL and press the START button. Then follow start-up procedures for limited or extended shutdown. Only after man ual start has been completed should the AUTO MANUAL switch be placed in AUTO.
NOTE: When the machine shuts down either automatically or manually, the refrigerant and solution pumps will continue to run until automatic dilution is completed.
Semiautomatic Start-Stop System - All auxiliary
equipment used with this system is tied directly to the control circuit. It is necessary for the operating engineer to press the START button to start the condensing water pump, chilled water pump, machine pumps, and cooling tower fan (if used).
PROCEDURES
1. Press STOP button to stop machine. START button to start machine.
NOTE: On shutdown the machine pumps will continue to run until automatic dilution
is completed.
Semiautomatic Start-Stop System with Manual
Auxiliaries - All auxiliaries must be started
manually.
PROCEDURES
1. Start chilled water pump.
2. Start condensing water pump.
3. Start cooling tower fan (if used). (This depends on outside temperature.)
4. Press START button to start machine.
5. To stop machine, press STOP button. Then stop the following: a. Cooling tower fan (if used). b. Condenser water pump. c. Chilled water pump.
NOTE: The refrigerant and solution pumps will continue to run until auto
matic dilution is completed.

MACHINE START-UP PROCEDURES

General - Procedures for start-up differ depend
ing on how long the machine has been shut down. There are two start-up procedures: Start-up after limited shutdown (3 days to 3 weeks), and
start-up after extended shutdown (over 3 weeks).

Start-Up After Limited Shutdown

PROCEDURES
1. Start the machine as outlined for your system under Machine Start-Stop Systems.
2. Check the leaving chilled water temperature. If temperature drops to design, then steps 3 and 4 are not necessary. If the temperature does not drop to design, noncondensables are probably present in the machine. Proceed with steps 3 and 4.
3. Determine the amount of noncondensables by taking an absorber loss reading (the temper ature difference between the refrigerant and solution vapor). To determine absorber loss, refer to Carrier Standard Service Techniques, publication SM-16. A machine with absorber
loss of less than 6 F can normally be started without the machine solution becoming solid ified. If absorber loss is greater than 6 F, auxiliary evacuation is recommended. A ma
chine fully evacuated will normally have an absorber loss of 2 F or less. Instructions for auxiliary evacuation are in Carrier Stand ard Service Techniques, publication SM-16.
Press
Carrier Corporation 1968 Printed in U.S.A.
1-68
16JA-1SO
Page 2
To prevent solidification while purging: a. Place reclaim switch to MANUAL.
b. Throttle back steam control valve.
(1) Electronic Control - Turn the control
point adjustor up approximately ten degrees (ten divisions).
(2) Pneumatic Control - Turn the chilled
water thermostat set point up ten degrees.
4. Evaluate machine tightness with a noncon densable accumulation rate check. Refer to Carrier Standard Service Techniques, publica tion SM-16.
Start-Up After Extended Shutdown - This pro
cedure is critical since accumulated noncon densables may allow the machine solution to solidify if the following precautions are not taken,
PROCEDURES
1. Start the machine as outlined for your system under Machine Start-Up Procedures. Make
sure steam valve is closed. If absorber solu tion level is high (above 9 in.) and refrigerant pump is noisy, open steam valve until absorber
level indicator shows approximately 9 in. of
solution, then close steam valve. Place refrig
erant pump switch in ON position.
2. Determine absorber loss by following proce dures outlined in Carrier Standard Service
Techniques, publication SM-16.
a. If absorber loss is less than 6 F, open
steam valve and allow machine to go into automatic operation.
b. If absorber loss is 6 F or greater, auxil
iary evacuation is required. Use instruc
tions for auxiliary evacuation provided in
Carrier Standard Service Techniques, pub lication SM-16.
3. Continue auxiliary evacuation until absorber loss is less than 6 F. Place machine in auto
matic operation.
4. After auxiliary evacuation, evaluate machine
tightness with a noncondensable accumulation
rate check.

WINTER CONDITIONS

General - At the end of each cooling season when
the machine is no longer required use one of the following winter shutdown procedures. The choice depends on whether the machine ambient tempera ture will be kept above or below freezing.

Shutdown Procedures

BELOW FREEZING
1. Stop machine and wait until automatic dilution completes and machine pumps stop.
2. Set dilution thermostat to its lowest possible setting.
3. Connect a hose between solution and refrig
erant pump service valves. Open both valves.
4. Switch refrigerant pump ON-OFF switch to OFF and solution pump switch to ON.
5. Press START button and allow solution pump to run for approximately 5 minutes.
NOTE: This procedure contaminates the refrigerant with lithium bromide solution lowering the refrigerant freezing point.
6. Press STOP button and reset dilution thermo
stat to 140 F (refer to Checking Dilution Ther
mostat under Maintenance).
7. Drain water from all chilled water, condensing,
steam and condensate circuits. Flush all cir
cuits with ethylene glycol.
ABOVE FREEZING
1. Press STOP button.
2. Allow machine to go thru automatic dilution.
When dilution has completed, machine may
be left in this condition until spring start-up.

Start-Up Procedures

BELOW FREEZING
1. Refill all water circuits that were drained at
shutdown.
2. Follow Start-Up After Extended Shutdown pro
cedures.
3. Reclaim lithium bromide from refrigerant
circuit. Follow Reclaim Solution procedures given under Maintenance.
4. Restart machine.
ABOVE FREEZING
1. If machine vacuum was broken for maintenance work, etc., follow auxiliary evacuation pro cedures outlined in Carrier Standard Service Techniques, publication SM-16. Then follow Start-Up After Extended Shutdown procedures.
2. If machine vacuum was not broken, follow Start-Up After Extended Shutdown procedures.

PURGE OPERATION

General - The 16JA purge unit automatically per
forms the following functions:
1. Removes noncondensables from the machine.
2. Accumulates these noncondensables in the purge storage chamber where they will not affect the machine performance.
3. Provides an indication of the degree of air
leakage into the machine.
The 16JA purge unit cannot be used as an auxil
iary evacuation device to evacuate the machine.
When the purge exhaust light (red) is energized
during machine operation, it indicates that the
purge must be manually exhausted. For instruc
tions refer to the instruction sticker located on the
separation chamber (Fig. 1) or use the following procedure.
Page 3
CONDENSER PURGE
SUCTION LINE
PURGE EXHAUST VALVE
INSTRUCTION STICKER PURGE
PURGE RETURN VALVE
TO GENERATOR OVERFLOW TUBE
SEPARATION
CHAMBER
STORAGE CHAMBER
SUPPLY LINE
service valve. With correct pump rotation, the gage will indicate a positive reading above at mospheric pressure. If the pump is solidified, the gage will indicate atmospheric pressure. If the casing is partially desolidified and the pump will not turn, the pressure gage will in dicate a deep vacuum. Continue to heat the casing until the pump is desolidified. Desolid ification of the heat exchanger will take place automatically once the pump starts functioning.
3. Refer to Troubleshooting Guide for possible causes of solidification and their correction.
SOLUTION PUMP-
Fig. 1 - Purge Exhaust System
Manual Exhaust Procedures
1. Close purge return valve.
2. Wait 10 minutes for storage chamber to pressurize.
3. Slowly open purge exhaust valve. If level in
container drops, shut valve and wait 2 minutes. Reopen valve. If bubbles appear, keep valve
open until bubbles stop and level in container
rises, then close valve.
4. Collect lithium bromide solution to recharge
into machine. Recharging procedures are given in Carrier Standard Service Techniques, pub lication SM-16.

SOLUTION DESOLIDIFICATION

General - Should solidification occur, it will occur
usually in the shell side ofthe heat exchanger, pre
venting the strong solution in the generator from returning to the absorber thru the strong solution line. However, the strong solution will be returned to the absorber thru the generator overflow tube (Fig. 6) thereby desolidifying automatically.
If during a shutdown period solidification has occurred to the extent that the solution pump will not rotate and the motor overloads trip put, de­solidify by using the following procedure.
PROCEDURE
1. Heat the pump casing and adjacent lines with
steam until the pump will rotate. Be careful
not to allow steam and condensate to enter the
pump motor and controls.
jpr«ic3iCitK»3S miSt he
fi a beaîiïig torch 1& used, cadesr
lîcf hhaajà heat he
iÈC35eciÎ3f to âîiy ifeïige <M№iectiOîias3â!e’S'«ry
2. Confirm pump rotation. Rotation of the her
metic pump cannot be viewed directly. Install a compound pressure gage on the solution pump
MAINTENANCE

INTRODUCTION

General - The following are routine steps nec
essary for normal preventive maintenance on 16JA Hermetic Absorption Liquid Chillers.
To ensure the continued satisfactory perform
ance of the machine, these schedules must be
closely adhered to.
We recommend the suggested steps be per
formed as often as indicated, and that an accurate
log be kept to aid in diagnosing any troubles.
Certain components and operations should be
checked on an individual basis as needed.

EACH MONTH

Reclaim Solution - During normal operation it is
possible that some lithium bromide might carry over into the refrigerant circuit.
To determine if contamination exists, remove a refrigerant sample from the machine using refrigerant and solution sampling procedures out lined in Carrier Standard Service Techniques, publication SM-16. Measure the specific gravity of the sample. If the value exceeds 1,02, the solu
tion must be reclaimed.
RECLAIM PROCEDURE FOR CONTINUOUS OP ERATION
1. Place reclaim valve switch in MANUAL posi tion. Wait for approximately 15 minutes. This causes refrigerant to flow into the solution circuit where the lithium bromide solution is reclaimed.
2, Place reclaim switch in AUTO position, de
energizing the refrigerant solenoid valve, thus stopping refrigerant flow.
RECLAIM PROCEDURE FOR FREQUENT SHUT DOWN - When the machine is shut down, the re claim valve will automatically reclaim the lithium bromide salt solution.
NOTE: If the reclaim solenoid valve does not
energize during the reclaim procedure (aud ible click, and typical rattling noise of refrig erant passing thru the valve) contact your
nearest Carrier representative for assistance.
Page 4
Check Machine Tightness - The most important
maintenance item on the absorption machine is maintaining vacuum tightness within acceptable
limits. Check machine tightness by determining the noncondensable accumulation rate. Use pro cedures given in Carrier Standard Service Tech niques, publication SM-16.
condenser water temperature. Turn down control point adjuster below design leaving chilled water temperature setting. Repeat steps 1 thru 4.
Continual removal of water indicates leakage in
one of the tube bundles. Leak test by using proce
dures outlined in Carrier Standard Service Tech
niques, publication SM-16.

EVERY 2 MONTHS

Check Dilution Thermostat - The dilution thermo
stat should be open when the strong solution drops to 140 F. If temperature cutout point is not 140 F, insert screwdriver in slot on face of thermostat (located on strong solution line) and turn adjust ment dial until cutout occurs at 140 F.
Check Low-Temperature Cutout - Remove low-
temperature cutout sensing element from sep
arable well in the evaporator shell. Place it in an ice bath. Low-temperature cutout should trip
at 5 F below design leaving chilled water tem perature or a minimum of 36 F. The actual cutout point is the dial setting less 3 F differential. When the control trips, the machine will shut down immediately without going thru a dilution cycle.
NOTE: The chilled water pump will continue to run if hooked up in the standard wiring arrangement.

EVERY 6 MONTHS

Check Evaporator Water Charge-Check the evap
orator water charge to determine if the reclaim valve has energized. If valve has energized then either tube leakage or excess refrigerant is
indicated.
Reclaim should start at full load (corresponds to approximately 62 percent lithium bromide in absorber for standard nominal conditions). Check as follows:
1. Operate machine at full load with design en tering condensing water and design leaving
chilled water.
2. Remove a sample of evaporator water from
refrigerant pump service valve and check the specific gravity. If specific gravity is below
1.02 proceed with step 3. If specific gravity
is above 1.02 reclaim solution (see instruc
tions for Reclaim Solution, page 3) until specific
gravity is below this point, then proceed with step 3.
3. Evaluate absorber loss. Should be 2 F or less. If more, purge air from machine.
4. Check reclaim line by feel. Listen for refrig erant flow (audible). If reclaim line is already
cold, with audible refrigerant flow, remove refrigerant until reclaim valve closes (audible
click) and refrigerant flow ceases.
If machine is operating under light load, it will
be necessary to concentrate the absorber weak
solution to 62 percent. To do this, raise entering
Check Capacity Control Valve - Check to see if
leaving chilled water is being maintained at design temperature. If not, adjust the electronic or pneumatic control.
TO ADJUST ELECTRONIC CONTROL
1. Move control point adjuster clockwise to in crease temperature, or counterclockwise to decrease temperature. If this fails to bring leaving chilled water within design temper ature, perform step 2.
2. Replace vacuum tubes in control motor. Make sure that new tubes are installed in correct plugs. If this fails to bring leaving chilled water within design temperature, proceed with step 3,
3. Clean relay contacts with stiff paper. If this fails to correct problem, contact Carrier
immediately.
TO ADJUST PNEUMATIC CONTROL
1. Reset control point setting to design.
2. If above fails to correct problem, contact
Carrier immediately.
Check Cooling Tower Bypass Control - If control
is not maintaining design entering condensing water temperature, recalibrate the control ther mostat. For information, contact the valve (or
control) manufacturer.

EVERY YEAR

Check for Absorber and Condenser Scale - Check
absorber and condenser tubes to see if cleaning
is required. Soft scale may be removed with tube
cleaning brushes. When hard scale has formed,
it may be necessary to chemically clean the tubes.
If a scale problem occurs, contact a water treat
ment representative. Annual tube cleaning may
not be required if adequate water treatment is
maintained.
Recharge Lithiunn Bromide - Recharge lithium
bromide when the purge exhaust bottle becomes
filled.
PROCEDURES
1. Open the exhaust valve and allow solution to be forced back into the purge,
2. Close the exhaust valve when the level nears the end of the tube. Do not allow air to be drawn into the tube.
Page 5

EVERY 2 YEARS

Replace Service Valve Diaphragms - Require
ment to replace valve diaphragms is determined by valve usage or number of machine operating hours. Less frequent usage of valves and lower number of machine operating hours results in longer life span for valve diaphragms. With min
imum usage the requirement to replace dia phragms might be 3 years. With maximum usage they will need to be replaced in approximately 2 years.
PROCEDURES
1. Remove all solution and refrigerant from the machine.
2. Break vacuum with nitrogen unless performed previously. Refer to Carrier Standard Service Techniques, publication SM-16,
3. Remove solution and refrigerant from machine unless performed previously.
NOTE: Store solution in clean containers for recharging.
4. Remove old valve diaphragms.
5. Install new valve diaphragms. Torque bolts to 3 ft lb.
6. Leak test all affected joints to make sure that all valves are leak tight.
7. Replace solution and refrigerant in machine.
NOTE: The same quantity of solution and refrigerant removed from the machine must be charged back into the machine.
3, Pull stator and adapter flange straight back
from pump casing. If paint has frozen flange to casing, gently pry between adapter flange and pump discharge pipe (item 4) until paint seal is broken.
4, Remove and discard gasket (item 5),
5. Remove impeller (item 6) by straightening locking tabs on impeller lock washer (item 7). Prevent impeller from rotating while removing locking bolt (item 8). Remove impeller key in
the shaft.
6. Remove bearing and wearing ring housing:
a. F-8 Frame Pumps (Fig. 2) - Unbolt cap
screws (item 9). Remove bearing and wear ing ring housing (item 10).
OAiliiWi Do. safe afc bearii® to
or 0300 XEOOr. AiSO oo ca. _ fel ucc lo Jos£i retaimfag clip iitom 18>
b. F-66 Frame Pumps (Fig. 3) - Remove stud
nuts (item 9). Use jacking screws to loosen bearing and wearing ring housing (item 10), Insert jacking screws in tapped holes pro vided in wearing ring housing.
7, Slide out rotor (item 11) carefully, so as not
to damage the stator can (item 12), rotor can (item 13), or motor end bearing (item 14).
8. Remove motor end bearing, retaining clip (item
15) and spring (item 16). Remove spring bear
ing plate (item 17) used on Frame F-8 only.
8. Re-evacuate the machine after service work is completed. See auxiliary evacuation pro cedures in Carrier Standard Service Tech niques, publication SM-16.

EVERY 5 YEARS

Inspect Hermetic Pumps - Pumps used on Carrier
Absorption Machines are hermetic and do not re quire seals. Pump motors are cooled by the fluid being pumped and are thermally protected with high-temperature cutouts (Klixons).
Inspect hermetic pumps and motors every
5 years or 20,000 hours, whichever comes first,
DISASSEMBLY PROCEDURES - Refer to Fig, 2
and Fig. 3.
1. Disconnect motor power leads at junction box on stator. Mark leads for ease in reassembly.
2, Remove bolts (item 1) holding motor adapter
flange (item 2) to pump casing (item 3),
NOTE: Use blocking to support weight of
motor stator when removing bolts.
INSPECTION PROCEDURES
1. Check for bearing wear by measuring depth from large end to start of cone (Fig. 4). If wear exceeds 3/16 in,, replace the bearing. Use standard parts lists for ordering new bearing.
Instructions for bearing replacement are fur
nished with new bearing.
2. Check recirculation passages (item 20). Clean
as required.
3. Check impeller stator can, rotor can and wearing rings for wear. Clean or replace if necessary.
NOTE: If wearing rings require replace
ment, break the old ring with a chisel. These rings were staked in place. Do not restake new wearing ring.
4. Check spring loaded bearings for free move ment within the bearing housing.
Page 6
note: item numbers are referenced in
DISASSEMBLY AND REASSEMBLY PROCEDURES.
Fig. 2 - F-8 Frame Pumps
NOTE: ITEM NUMBERS ARE REFERENCED IN
DISASSEMBLY AND REASSEMBLY
PROCEDURES
Fig. 3 - F-66 Frame Pumps
Page 7
J."
MAX
16
REASSEMBLY PROCEDURES
Refer to Fig. 2
and 3.
1. Clean all parts.
2. Replace wearing rings. Use hand pressure to position new rings.
3. Insert motor end spring and bearing plate (F-8 Frame Pump only).
4. Install retaining clip and spring in bear ing housing.
5. Insert motor end bearing into housing. Should be a free sliding fit without excessive ra
dial play.
6. Guide the rotor into position.
7. Install end bearing in bearing and wearing
ring housing: a. Frame F-8 Pumps - Be sure bearing re
tainer pin is in the retainer slot.
b. Frame F-66 Pumps - Be sure bearing re
tainer pin is in the bearing retainer hole.
8. Install bearing and wearing ring housing.
Tighten cap screws (Frame F-8 pumps), or
stud nuts (Frame F-66 pumps).
9. Install impeller with impeller key, lock
washer and locking bolt. Bend tabs of washers over flats of locking bolt heads.
10. Install new 1/32 in. thick EPR gasket by removing transfer tape from adhesive side of gasket and positioning gasket on adapter flange periphery.
11. Assemble motor stator housing and adapter flange assembly by sliding the housing and
adapter flange assembly into pump casing. Refer to step 2 of Disassembly Procedures as to blocking. Install and tighten bolts and washers. Remove blocking.
12. Connect power supply to stator junction box.

AS NEEDED

Adding Octyl Alcohol - Octyl alcohol is usually
required when the leaving chilled water tempera ture starts to rise above design providing the control set point has not been altered. Since a
rise in leaving chilled water temperature is also an indication of fouled condensing water tubes, use the following procedure to determine if alcohol is required.
PROCEDURE
1. Remove a sample of solution from solution pump service valve. If solution has no odor of alcohol (very pungent), then octyl alcohol
should be added.
2. Add alcohol using the procedure outlined in
Carrier Standard Service Techniques, pub lication SM-16.
3. If alcohol is not required, refer to Trouble
shooting Guide for symptoms of fouled tubes.
Log Sheets - We recommend that log sheets be
obtained from your Garrier representative and that readings be taken periodically. They are used to:
1. Familiarize operator with machine operation.
2. Be of assistance when planning maintenance.
3. Diagnose machine troubles.
Ordering Spare Parts - Order spare parts from
your nearest Carrier office. To speed up the process of filling part orders, the following in formation must accompany the order:
1. Delivery address.
2. Machine size.
3. Machine serial number.
4. Part name, part number and quantity required.
5. Orders for pump parts must show the motor
serial number found on the motor nameplate.

TROUBLESHOOTING

The remedies listed do not represent a series of corrective procedures. They are merely check points and possible individual remedies to machine problems. When the troubleshooting remedies fail to pinpoint a problem, contact your nearest
Carrier representative for assistance.
Page 8
TROUBLESHOOTING GUIDE
SYMPTOM OR DIFFICULTY
A. Lithium bromide
solidifies at start-up.
B. Lithium bromide
solidifies during operation.
POSSIBLE CAUSE
REMEDY
1. Condenser water too cold. 1. a. Reset cooling tower bypass valve to design conditions.
b. Check cooling tower fan con
trol setting.
2. Air in machine. 2. Purge the machine. Use Carrier Standard Service Techniques, publication SM-16.
3. Improper purging. 3. a. Check to see that all valves
are in correct position.
b. Check machine leak rate with
purge.
1. Condensing water too cold. 1. a. Reset cooling tower bypass valve to design conditions.
b. Check cooling tower fan con
trol setting.
2. Steam pressure above design. 2. Reset to design conditions.
3. Vapor condensate temperature
3. Reduce condensing water flow. too low. (Temperature should never be below 114 F at full load.)
4. Machine requires octyl alcohol. 4. Add octyl alcohol. Use Carrier Standard Service Techniques, publication SM-16.
5. Improper purging.
5. See Remedy in A-3 above.
6. Air leakage. 6. Leak test machine.
C. Low capacity
1. Air in machine. 1. Find and repair leak. Purge the machine.
2. Condenser tubes dirty. Noted by continually rising vapor con densate temperature (above 114 F) at full load.
2. Clean the tubes and take cor rective action in water treat ment methods. Use the Carrier Standard Service Techniques, publication SM-16.
3. Improper purging. 3. See Remedy in A-3.
4. Machine needs octyl alcohol.
4. Add octyl alcohol. Refer to Carrier Standard Service Tech niques, publication SM-16.
5. Improper setting of capacity control valve.
5. Reset capacity control valve to design temperature by turning
control point adjuster down.
6. Insufficient condensing water flow, or temperature too high.
6, a. Reset cooling tower bypass
valve to design temperature,
b. Check operation of tower fan.
c. Check the condenser water
strainer.
7. Solution temperature generator below design at full load. Note correct temperature at full load.
7. a. Raise steam press, to design. b. Unplug the steam strainer
or trap.
Page 9
TROUBLESHOOTING GUIDE (CONT)
SYMPTOM OR DIFFICULTY
D. Machine shuts down on
safety control.
E. Solidification during
shutdown.
POSSIBLE CAUSE
1. Motor overloads.
1. Reset all motor overloads and
REMEDY
check reason for failure.
2, Hermetic pump overload has
tripped.
2. a. If pump is out of liquid, add solution or water.
b. If pump is solidified, de-
solidify. (Refer to Solution Desolidification.)
3. Shutdown on low-temperature cutout.
3. a. Check low-temperature cut out setting.
b. Control point adjuster set
ting too low. Turn up chilled water controller to design.
c. Check condensing water tem
perature control.
1, Dilution cycle not long enough. 1. Check setting of dilution ther
mostat, Should be 140F. If still solidifies reset to lower cutout temperature.
2. Improper closing of capacity
2. Check valve closure, Desolidify,
control valve.
3. Machine is shut down, but con densing water pump is still
3. Manually shut down condensing water pump.
running.
F, Suspect air leakage. Leakage into vacuum side of
machine.
G. Loss of vacuum at
shutdown.
H, Failure to keep ma
chine purged.
Leakage into vacuum side of machine.
1, Leakage above the pumping rate
of purge.
2. Purge not performing properly.
Determine noncondensable ac cumulation rate. Refer to the Carrier Standard Service Tech niques, publication SM-16.
Leak test machine.
1. a. Perform leak rate check, b. Leak test machine.
2. a. Valves not opened properly. Check to see that all valves are in correct position,
b. Purge solidified. Desolidify. c. Lack of solution flow to purge
from solution pump. Con tact your Carrier repre
sentative.
Page 10
GENERAL INFORMATION

EQUILIBRIUM DIAGRAM

The Equilibrium Diagram (Fig. 5) is used to
determine solution concentration in your machine. It is important to maintain solution concentration within certain limits in order to maintain equilib
rium conditions.
Refer to the typical machine absorption cycle plotted on Fig. 5, Points 1 thru 7 represent a complete cycle. Specific point values are given
in Table 1. An explanation of each point and the lines drawn between is as follows:
Point 1 - The strong solution as it sprays out of
the absorber spray nozzle and starts to absorb refrigerant.
The following explains the equilibrium diagram
and how to determine solution concentration:
The curved line in the lower right-hand corner
is the crystallization line. This line indicates the point at which the solution will begin to change from a liquid to a solid. This sets the limits of the cycle. Crystallization of a solution is quite
different from the freezing of a single substance
such as water. When water is subjected to a
temperature even slightly below 32 F, all of it will eventually freeze. In contrast, when the
lithium bromide solution temperature is reduced
below the solidification point for that particular
concentration, only a portion of the salt will
crystallize or freeze. The remainder of the solu
tion will become more dilute or less concentrated
and will remain in a liquid state. Crossing of the
crystallization line does not necessarily result in
solidification provided the subcooling does not
progress too far. Solidification of solution will
not harm the absorption machine but it will
interrupt service. Satisfactory design requires that operation take place above the crystalliza tion line.
The scale on the left represents the straight horizontal lines and indicates the vapor pressure of the solution or evaporator water at equilib rium conditions.
On the right-hand side is the saturation temper ature scale for pure water corresponding to the vapor pressures on the left-hand scale. This
scale also represents the horizontal lines and is located on the right side to avoid confusion in reading the chart.
The scale at the bottom is for the vertical
lines. They represent solution concentration in
percent by weight. For example, a solution of
60% is 60% lithium bromide and 40% water by weight.
Point 2 - The weak solution as it leaves the ab
sorber and enters the heat exchanger. Line 1-2 represents absorption of the
refrigerant thereby diluting solution.
Point 3 - The weak solution after it has passed
thru the heat exchanger. Line 1-3 rep resents the amount of heat gained by the solution in the heat exchanger.
Point 4 - The weak solution entering the genera
tor and being heated. Line 3-4 repre
sents the amount of heat required to start the weak solution to boil.
Point 5 - Maximum solution concentration in the
generator after much of the refrigerant has boiled out. Line 4-5 represents the amount of heat required to boil off the
refrigerant.
Point 6 - The strong solution as it leaves the heat
exchanger on its way to spray nozzles.
Point 7 - The strong solution entering the spray
nozzles.
Table 1 - Cycle Data
POINT
1
SOLUTION
TEMP
(F) 115 0 25
2 3 4 5 6 7
101 165 192 3.20 59.5 115 215 134 0.45 64 0 119
VAPOR
PRESS. (in Hg)
0 25
1 65
3 20
0.30 63 0
PERCENT
LITHIUM
BROMIDE SOL
63.3 59 5 42 59 5
64 0 115
SATURATED
TEMP
(F)
42
95
55
45
The curved lines running from left to right
are solution temperature lines. These should not
be confused with the saturation temperatures.
The curved lines which extend upward from the bottom of the diagram are specific gravity lines. These are used to determine solution concentra tion. By measuring the specific gravity with a hydrometer and finding the temperature, the per
cent of concentration can be determined by plot
ting these two points on the diagram.
10
Page 11
“n
<p*
in
m
Si
E.
5"
c*
3
VAPOR PRESSURE IN INCHES OF MERCURY ABSOLUTE
® fv> cr w
ro ts> UJ OJ ^ Ol cn
o Ü» o o> o o o
Q
(Q
2
3
SATURATION TEMPERATURE (F)
Page 12

16JA ABSORPTION CYCLE

Figure 6 illustrates the basic absorption flow
diagram. The evaporator-absorber section oper ates at an absolute pressure of 0.25 in. Hg. As the cooling load passes thru the cooler, the re frigerant picks up heat and is vaporized (boiled) at 40 F because of the low absolute pressure. The
vaporized refrigerant migrates to the absorber
section due to the strong affinity for water of the
lithium bromide solution.
As more refrigerant is absorbed by the solution
the absorption rate decreases necessitating re
generation of the lithium bromide solution to a
more concentrated form to maintain machine ca pacity, To accomplish this, diluted solution in the absorber is pumped thru the tube side of a shell and tube heat exchanger where it picks up some heat from the hot strong solution returning from
the generator. On leaving the heat exchanger the now warmer weak solution enters the generator, is heated to boiling and the refrigerant is boiled out, becoming a strong solution again. This strong solution leaves the generator and passes thru the shell side of the heat exchanger losing some heat to the weak solution passing thru the tube side.
Usage of the heat exchanger reduces total heat
quantity required.
The strong solution returns to the absorber sprays and is then sprayed over the absorber tube bundle where absorption of refrigerant com mences again.
NOTE: Solution flow from generator to ab
sorber is the result of gravity and pressure difference and not by a pump.
Refrigerant boiled out of solution in the gen erator condenses on the condenser water coils and returns to the evaporator via the vapor condensate line. Refrigerant flows into the evaporator sump, where it is pumped to sprays over the evaporator coils and the cycle is repeated.
Capacity Control - A steam control valve is used
to control capacity. This valve operates by a con troller which senses the temperature of the leav ing chilled water. When the temperature is at or above the design point, the machine will beat full load. At this condition the steam control valve is wide open to reconcentrate the solution in the gen erator. As the chilled water temperature drops be low the design point, the steam will be throttled. At no load conditions the steam valve will be closed.
Manufacturer reserves the right to change any product specifications without notice
Tab 15 16JA-1SO New 1-68 Code MA Catalog No. 531-642
Loading...