Sensus Metering Systems
RM-1307
Model 043-B and 143-B Service Regulators
Installation and
Maintenance
Instructions
The Models 043-B and 143-B
are general purpose gas pressure regulators. They can be used for natural gas, air, CO2, propane, butane, nitrogen,
and other gases. They can be used for gas services to homes, commercial establishments and small industries,
for burners, unit heaters, boilers, and other equipment. All regulators include an internal relief valve.
THE GAS INDUSTRY
Installation and Start-Up
1. Remove the shipping plugs from both the regulator inlet and
outlet connections.
2. Make certain that the inside of the piping and the regulator
inlet and outlet connections are clean. The connections must
be free or dirt, dope and other debris.
3. Use pipe joint material only on the male threads of the pipe
being connected to the regulator. Do not use pipe joint
material on the female threads of the regulator.
4. Install the regulator in the piping. Make certain that the gas
flow through the regulator is in the direction as indicated by
the arrow on the regulator body.
The regulators may be installed in any position: right side up,
upside down, vertical piping, diagonal piping, etc., If required
the diaphragm case may be rotated 360°. The Model 043-B
can be rotated in 90° increments. The 143-B can be rotated
in any angle increment.
To rotate the 043-B diaphragm case, detach the diaphragm
case from the body by removing the two body-to-diaphragm
case screws. After repositioning the diaphragm case to the
desired position, reinstall the body-to-diaphragm case screws.
For the Model 143-B, the diaphragm case can be rotated on
the body without removing the body-to-diaphragm case
screws. Simply loosen the two body-to-diaphragm case
screws and retighten when the diaphragm case is in the
desired position. For both models, ensure that the body-todiaphragm screws are sufficiently tightened to reseal the
regulator. 35-50 ft-lbs. of torque is recommended.
The diaphragm case vent (11) should be positioned to
minimize the chances of moisture collecting on the vent side
of the diaphragm. The upper diaphragm case (4) may be
rotated to a downward position by removing the flange
screws (10).
The diaphragm case vent must be positioned to protect
against flooding, rain, ice formation, traffic, tampering, etc.
The vent must be protected against nest building animals,
bees, insects, etc. to prevent vent blockage and minimize the
chances for foreign material from collecting in the vent side of
the regulator diaphragm. If required, the upper diaphragm
case may be rotated by removing the upper-to-lower case
flange screws and rotating the upper diaphragm case to the
desired position. Reinstall the diaphragm flange screws and
tighten to hold the diaphragm case in position and reseal.
CAUTION:
Turn the gas on very slowly. If an outlet stop is used, it should be
opened first. Do not overload the diaphragm with a sudden surge
of inlet pressure. Monitor the outlet pressure during start-up to
prevent an outlet pressure overload.
5. Turn the gas on very slowly.
6. Make certain that there are no leaks and that all connections
are tight.
7. Adjust outlet pressure (set point) by removing cap (1) and
turning adjustment spring button (2). Turn clockwise to
increase and counter-clockwise to decrease outlet pressure.
Only adjust when gas is flowing through regulator. Be sure to
reinstall cap.
CAUTION:
It is the user's responsibility to assure that all regulator vents
and/or vent lines exhaust to a non-hazardous location away from
ANY POTENTIAL sources of ignition. Where vent lines are used,
it is the user's responsibility to assure that each regulator is
individually vented and that common vent lines ARE NOT used.
8. The vent connection is an escape path for the regulated gas.
Depending upon the type of gas, it could be flammable as with
natural gas and propane. Therefore, the vent connection needs
to be located and/or piped so that potential discharge occurs
in a safe area away from buildings, open flames, collection
areas, arcing devices, etc.
Regulators that are installed indoors or in a non-vented area
must be vented to the outside. Run vent piping from the
regulator vent connection to a non-hazardous location on the
outside away from any potential sources of ignition.
Since the Models 043-B and 143-B regulator are equipped
with internal relief valves (IRV), the vent piping must be vent
connection size or larger and its length be as short and direct
as possible to a safe area. This is to assure the venting of
the internal relief valve discharge to the atmosphere without
excessive pressure increase in the regulator and downstream
piping.
The outlet of the vent piping must allow for free and
unobstructed passage of air and gas and must be protected
against the potentials listed in instructions #4, #8 and #9.
Continued on back.
9. For outdoor installations, it is recommended that the regulator
be installed so that the regulator vent faces downward to avoid
the potential for water and other foreign matter entering the
regulator and interfering with the proper operation of the
regulator.
CAUTION:
Regulators are pressure control devices with numerous moving
parts subject to wear that is independent upon particular operating
conditions. To assure continuous satisfactory operation, a periodic
inspection schedule must be adhered with the frequency of
inspection determined by the severity of service and applicable
laws and regulations
Servicing
1. To access valve (7), orifice (6), or diaphragm assembly (8),
first remove spring compression by unscrewing the spring cap
(1) and spring adjustment ferrule (2). Remove spring (3) from
regulator.
2. For access to the valve (7) and orifice (6), remove body-to-
diaphragm case screws from body (5) with a 1/2" standard
socket (or standard screwdriver for the 043-B) and remove
diaphragm case assembly from body (5). For the 143-B,
the screws release a collar bracket, which attaches the
diaphragm case to the body.
3. To replace Buna-Nitrile valve pad (7), simply pull off of valve
stem (9) and replace with new pad.
4. To replace orifice (6), unscrew from body using a 7/8" hex
socket wrench. Apply sealant on threads of orifice when
installing replacement orifice. Re-screwing replacement orifice
must be installed at 50-60 ft-lbs. of torque.
5. To replace diaphragm assembly, remove flange screws (10)
and disassemble diaphragm assembly. Make certain all parts
are reassembled in their correct order and all threads and
joints are tightened evenly and firmly.
6. Before reassembling body to diaphragm case, make certain
that the 143-B gasket/043-B o-ring is in position.
Over Pressurization Protection
Protection must be provided for the downstream piping system
and the regulator's low pressure chambers to assure against
the potential for over pressurization due to a regulator malfunction
or a failure of the regulator to lock up. The allowable overpressurization is the lowest of the maximum pressures permitted
by federal codes, state codes, Sensus Bulletin RDS-1498,
or other applicable standards. The methods of providing overpressure protection could be a relief valve, a monitor regulator,
a shut-off valve device or similar device.
Buried Service
The Models 043-B and 143-B regulators are not recommended
for buried service.
Temperature Limits
The Models 043-B and 143-B regulators can be used for the
flowing temperature of -20° F to 150° F (-28.9° C to 65.5° C).
Maximum Emergency Pressures
The maximum pressure the regulator inlet may be subjected under
abnormal conditions without causing damage to the regulator is:
Maximum Inlet Pressure plus 50 psi.
The maximum pressure to which the regulators case may be
subjected under abnormal conditions without causing damage
to the internal parts of the regulator is: Set point plus 3 psi.
If the outlet pressure exceeds this pressure, the regulator must
be removed from service and carefully inspected. Damaged or
otherwise unsatisfactory parts must be replaced before returning
the regulator to service.
The maximum outlet pressure that can be safely contained in
the diaphragm case is 10 psi (safely contained means no leakage
as well as no bursting.)
805 Liberty Boulevard
DuBois, PA 15801
800-375-8875
Fax: (814) 375-8460
www.sensus.com
(open “North American Gas”)
© Sensus Metering Systems 2004 Made in USA
02-04-RV0-8M