Calorique LOADING DOCK User Manual

Installation Manual
Snow & Ice Melting
Loading Dock
Skid Plates
CCMM11002200
- 04-08-13
Junction Box
Before Installing
Installation must conform to all requirements of the National Electrical Code (NEC) 426.23(B) (Fixed Outdoor Electric Deicing and Snow-Melting Equipment) and any local codes or ordinances. In countries other than the USA, follow the dictates of the local electrical and building code.
The electrical source must conform to the heating units’ require­ments (voltage and circuit amperage capacity) and overcurrent protection device must incorporate a GFCI.
Connection of heating unit(s) should be performed by a licensed electrician.
Do not cut, bend or otherwise alter the CalorIQue Heated Skid Plate. Any alterations to the units may present a shock or fire hazard.
Suitable overcurrent protection shall be provided by means of circuit breaker or fuse. Overcurrent protection shall be of a type indicated as being acceptable for branch circuit protection.
WARNING: Ensure that adequate drainage is provided for water runoff.
Tools & Materials
CalorIQue Heated Skid Plate. See Free Estimate Worksheet (CM1012) for ordering details.
Typical heated skid plate. Your model may vary.
Standard Electrical Hand Tools.
Overcurrent Protection. User / installer supplied. The circuit
breaker used with this sistem must have an overcurrent rating of 30 amps and an integral GFCI rated for 30mA equipment protection.
Electrical Conduit. Rigid or flexible conduit meeting the requirements of N.E.C. 426.23(B) of local code (e.g. carflex).
Electrical Wire. Suitable wire for use within exterior conduit. Three conductors must be available. Conductors may range from #14-22 AWG, size based upon total ampacity connected.
Drill with Bits. Bit must be rated for drilling into the material onto which the skid plate(s) is being installed.
NOTE: If using an anchoring method other than the supplied expan­sion shields and stainless steel screws, follow the manufacturer’s instructions for best results. In all preparation and installation steps indicating use of the expansion shields and supplied 1/4” stainless steel screws, replace with the anchor manufacturer’s instructions.
Construction Adhesive. This adhesive must be water and heat resistant.
Non-Skid Surface
Silicone Sealant. Exterior grade silicone used to waterproof the junction box cover plate.
Control System. Supplied by CalorIQue, automatically turns the system on and off based on the temperature and presence of precipitation. UL Listed and CSA Certified.
Specification Sheet. Provides specifications for all skid plates included with the system.
Product Labels. Provide information about the system that may be required during future remodeling or repairs.
Warrantee Card. This card must be filled out and returned to CalorIQue to ensure proper registration of the warrantee.
Typical system wiring layout.
Preparation
If necessary, level worn or damaged loading docks with quick setting leveling compound.
Install and supply power to a junction box located conveniently for connection to the CalorIQue Heated Skid Plate(s). Make sure that power is turned off at the distribution panel before installing this system.
Install control system according to the separate instructions.
Using an accurate ohm meter, test each skid plate to ensure
that it is within the limits shown on the specificatasdfasdfion sheet.
Installation
Drill Holes to Accept Expansion Shields Using the skid plate as a template, mark and drill holes for the expansion shields.
TIP:Since the exact hole locations may differ from plate to plate, label each dock area and plate and use the appropriate skid plate to mark the hole locations.
Place skid plate(s) based on their junction box type, and the type of
railing or edge work.
Insert the Expansion Shields into the Holes.
Mount the Skid Plate(s). Repeat the following for each plate:
• Apply construction adhesive to the loading dock.
Junction Box Style B
Junction Box Style A
Wall or Railing
Junction Box Style A
Railing
Skid Plate(s)
Power Distribution Panel
Control Box
Sensors
• Replace the skid plate and secure in place using the supplied stainless steel screws.
Wire Skid Plates Together. (If more than one plate is used.)
Using the supplied tap connectors, wire the skid plates together. Using the following figure as a guide, route conduit into the junction box on each plate and splice the three legs of electrical power together using the supplied waterproof connectors.
Tap wires between each plate using the connectors within the attached junction box.
Secure Conduit in Place.
Use a recognized method for securing the conduit.
Attach Cover Plate.
Apply a continous bead of exterior grade silicone sealant along the inside edge of the cover plate, then screw the plate to the junction box using the included screws.
Check Resistance. Using an accurate ohm meter, test each skid plate to ensure that it is within the limits shown on the specification sheet. This test confirms that the plates were not damaged during installation.
Complete Electrical Connections.
• Connect Skid Plates to the Control System.
Following the manufacturer’s instructions for the control, con­nect the skid plates to the control.
• Supply Power to the Control.
• Test the System Operation.
Turn on the system and ensure that it is drawing the correct amount of current. The current draw for your system is listed on the order sheet that comes with the system.
Operation
NOTE: Do not operate the system when the air temperature is above
50°F (10°C). Operation above this temperature may overheat the ele­ments and present a shock hazard.
When using the CalorIQue snow sensor, the skid plates will heat up automatically when needed. No user intervention should be required. See the control’s operations manual for additional information.
When using an on/off switch as the sole control, turn on the system when snow or icy conditions are expected.
Copyright © 2002-2004 CalorIQue, Ltd. All rights reserved.
Printed in USA
CalorIQue, Ltd.
2380 Cranberry Highway West Wareham, MA 02576 USA +1 508.291.4224 voice
+1 800.922.9276
+1 508.291.2299 fax www.calorique.com info@calorique.com
Line
Line
Ground
To Next Plate
To Element
(internal)
To Previous Plate or Junction Box