Thank you for purchasing a Calomax Quasar 2 boiler. All our products are designed to give years of simple, reliable operation. To ensure this, it is important that the installation and subsequent servicing is carried out by a suitably qualified engineer in accordance with these instructions.
INTRODUCTION 3
CHECK LIST 3
APPROVAL S 3
CONSTRUCTION 4
INSTALLATION 4 - 6
LOCATION 4
COLD WATER INLET 5
DIMENSIONS AND WEIGHTS 5
VENT / OVERFLOW 6
ELECTRICAL CONNECTIONS 6
USER INSTRUCTIONS 6 - 8
SCALE 7
GENERAL OPERATION 8
GENERAL NOTES 8
CLEANING 8
ACCESSORIES 9 - 10
SERVICE INSTRUCTIONS 11,14 &15
EXPLODED DIAGRAM 12 - 13
SPARE PARTS 16 - 17
WIRING DIAGRAM 18
TROUBLE SHOOTING 19
MAINTENANCE AND SERVICE HISTORY 20 - 22
WARRANTY 23
PRODUCT SPECIFICATION 24
CHECK LIST
Before commencing installation, check that the following parts have been supplied with the boiler:
1. WRAS approved flexible water inlet hose suitable for potable water.
2. BPDTK- plastic / stainless free-standing drip tray
This product conforms to the CE marking directive 93/68/
EEC through compliance with the following standards:
Electromagnetic Compatibility Directive Low Voltage Directive 73/23/EEC in accordance with:
BS EN 60335-2-63:1993
Compliance with these standards has been confirmed through testing by an independent NAMAS approved body
Calomax products have been tested and found to comply with the requirements of the Water Supply (Water Fittings) Regulations 1999 for England and Wales Water Bylaws 2000, Scotland and the Water Regulations Ireland.
APPROVALS
PAGE
Page 4
Page 5
LOCATION
To comply with recommendations from the health and safety executive it is important that due consideration be given to safe operation of the controls of the boiler. The boiler should therefore be mounted in such a manner that the operator can stand directly facing the machine with the controls at a recommended height from the floor of 1200mm +/- 100mm. Consideration should also be given to the servicing requirements of the machine. The maximum and minimum
COLD WATER INLET
ambient operating conditions are 35 °C and 5 °C respectively. The appliance is not suitable for installation where a water jet could be used. Install the boiler on a surface suitable for near boiling temperatures and the working weight of the boiler. Allow adequate clearance for ventiation and for the easy removal of the outer casing lid and rear panel. Calomax ltd recommend a minimum clearance of 50mm on all sides of the boiler . A suitably qualified engineer must install this unit. Plumbing and electrical installation work is involved.
To comply with the U.K. Water Supply Regulation a single check­valve must be fitted to the supply. BEFORE CONNECTING, THE SUPPLY PIPE MUST BE THOROUGHLY FLUSHED OUT TO ENSURE THAT FOREIGN MATTER DOES NOT BLOCK OR ENTER THE SOLENOID VALVE
The boiler must be connected to a potable water supply using the food grade hose provided, in a manner which complies with appropriate local water regulations. The hose should be connected to a ½” (15mm) drinking water supply via an appropriate isolating valve. The supply must provide a constant pressure of between 20 KPa and 1000 KPa (0.2 to 10 Bar). If the water supply contains excessive solids in suspension it is recommended that a fine mesh “in-line” water filter is fitted in the pipe work after the stop cock. Failures due to scale and sediment are not covered by the warranty.
INSTALLATION
All metallic components of the machine, in direct contact with drinking water are manufactured from high quality 304 grade stainless steel, or non-ferrous materials, providing maximum resistance to corrosion.
CONSTRUCTION
MODEL
A B C D E
DRY
WEIGHT
WORKING
WEIGHT
Quasar 2mm 546 240 410 201 65 12 KG 29 KG
DIMENSIONS AND WEIGHTS
The boiler must be installed in a location where access is restricted to operators that are suitably trained, or where untrained operators of the machine can be supervised by trained personnel.
1200 ±100
B
C
E
D
A
Page 6
Page 7
ELECTRICAL CONNECTIONS
The boiler is supplied with a fitted plug and lead and should be plugged into a 220 - 240v 13A electrical socket, capable of carrying a load of 3kW. The installation of a residual current device (RCD) having a rated residual operating current not exceeding 30 mA is advisable.
USER INSTRUCTIONS
During normal operation some external parts will become hot. Care must be taken to avoid a burn or scald injury.
Commissioning
1. Turn water supply on
2. Turn electrical supply on. Ensure that the On / Off switch (located at the rear) is in the On position
On initial switch-on only
After a few seconds delay for the electronics to charge up, the boiler will begin filling with water and the ‘Ready’ light and push button will flash to indicate ‘Wait’. At this point the push button is disabled. When water reaches the low level sensor (element covered) the element will be energised as well as the solenoid. When the normal operating level is reached the solenoid will turn off and the element will remain on until full operating temperature is reached.
The push button will stop flashing and show solid colour when the boiler is up to full temperature and the button will be enabled. At this point the
VENT & OVERFLOW
The vent / overflow pipe must be extended and laid with a
continuous
fall,
discharging to a safe and visible point. The pipe should not be directly connected to a closed waste, as taste problems may occur and should never be allowed to become blocked or restricted. One way this could be connected is via a tundish arrangement. 15mm copper or ‘Speedfit’ pipe should be used. If the machine is operated without the overfill pipe being extended as advised, any subsequent damage incurred will be the resposibility of the installer.
‘Ready’ light will stop flashing and show solid colour and the ‘Full’ light will also be illuminated.
On subsequent operation of the boiler
The boiler will fill and heat in cycles. It will allow only a limited amount of water to enter the unit at any one time and then switch off the solenoid and energise the element.
Subsequent Use
After the boiler has finished the commissioning cycle and water is drawn from the dispense valve, water will be replaced in short cycles (small amount of water and then heat). The solenoid and element will never be on at the same time unless the boiler is switched off and on again (re-setting commission mode). In normal use the boiler will always be at operating temperature indicated by the ‘Ready’ light and push button showing a solid (not flashing) colour. When the boiler is full and ready the ‘Full’ light will also be illuminated. Note: When the green service indicator light on the front of the boiler is showing solid colour, the machine has been starved of water for in excess of 20 minutes and the solenoid valve has been disabled to prevent damage to the solenoid coil through overheat. To re-energise the solenoid, the unit must be disconnected from the electrical supply and then switched back on, after first reinstating the water supply.
SCALE
The production of scale is a natural phenomenon and commonly occurs in hot water systems. The nature of the scale produced and its rate of formation varies from area to area. To ensure continuous, reliable operation, the boiler should be regularly de-scaled by a suitably qualified engineer. Suitable chemical de-scalants must only be used if the manufacturer’s recommendations are strictly adhered to. This is to prevent health and safety issues, taste problems and potential damage to the appliance. Misuse of such chemicals is not covered by the product warranty.
The Quasar boiler benefits from an integral scale inhibitor. This is not a
scale eliminator and its effects will differ according to the water quality in your area. To ensure trouble free operation, periodically check for scale inside the boiling chamber. The production of scale is a natural
Page 8
Page 9
CLEANING
Hold a cup below the dispense valve or place large vessels on the drip tray. Care must be taken to avoid injury through splashing or over-filling.
To begin filling, press the dispense button and water will flow from the outlet nozzle.
To stop filling, release the dispense button.
NEVER PASS YOUR HAND BENEATH THE NOZZLE.
Please retain these instructions for future reference
Ensure that a suitable drip tray (such as the one supplied) is
positioned below the dispense valve. This will help keep the surrounding work surfaces and floor free from drips or splashes. Various options are available and are outlined on the Accessories page of this booklet.
All de-scaling and servicing must be performed by a suitably qualified engineer.
GENERAL NOTES
GENERAL OPERATION
Avoid using any abrasive materials. Wiping the outer casing with a damp cloth should be sufficient. Some stainless steel cleaning products may not be suitable for plastic and must not come in contact with the plastic fascia. Always disconnect the electrical supply before cleaning.
NEVER USE A SPRAY JET OR ANY OTHER METHOD WHICH COULD CAUSE WATER TO ENTER THE ELECTRICAL CHAMBER.
phenomenon and some de-scaling may be required within the first 12 months. This is not covered under the product warranty as it is not a fault. If the water supply contains excessive solids in suspension it is recommended that a fine mesh ‘in-line’ water filter is fitted in the pipe work after the stop cock.
Accessories
Worktop-mounting Stainless Steel drip tray
Ref. HSSDTK
(freestanding)
Ingredient caddy
Ref. IC3 (3 bay)
-
as shown
Shelf unit
Ref. SHU
IC4 (4 bay)
HSSDTWDK
(with drain outlet)
Page 10
Page 11
When the green service indicator light on the front of the boiler is showing solid colour, the machine has been starved of water for in excess of 20 minutes and the solenoid valve has been disabled to prevent damage to the solenoid coil through overheat. To re-energise the solenoid, the unit must be disconnected from the electrical supply and then switched back on, after first reinstating the water supply.
If the unit requires servicing the service indicator will flash a sequence of light pulses . A 2x or 3x-light pulse generally indicates that the low or normal level probes require de-scaling. A 4x-light pulse means the water level has reached the high level sensor and the likelihood is that the normal level sensor requires de-scaling, or the machine has over-filled due to debris trapped in the solenoid valve. The debris can be removed by drawing plenty of water from the dispense valve, causing the solenoid valve to operate and flush out the obstruction. The machine will reset itself once the problem has cleared. If this does not rectify the problem, turn off the water supply and remove the flexible hose to check for debris in the valve’s filter. The unit can be used normally while the service indicator is flashing a 4x pulse. For further assistance, contact our service department on 0113 249 6681, e-mail service@calomax.co.uk or find a local service engineer at www.calomax.co.uk
Once the outer casing is removed, access to the Service Area has been gained. This access must be restricted to persons having knowledge and practical experience of the appliance, in particular as far as safety and hygiene are concerned.
De-scale
To gain access to internal components, the body lid must be removed. The lid incorporates a condenser mechanism which must be fitted the correct way round. The lid is labelled accordingly. To remove the lid,
break the lid gasket seal and pull the lid forward and up, to the front of the machine before lifting it clear of the body.
SERVICE INSTRUCTIONS
CONTINUED ON PAGE 14
Plug-in time switch
Ref. 7DPIT
Max 3kW
Water filter kit
(To reduce taste & odour problems)
Ref. 10TOSCK
Ref. 10TOSC
(Filter & timestrip replacement for kit shown above)
For more information visit our website at www.calomax.co.uk or call 0113 249 6681
Fused spur time switch
Ref. 7DFST
Max 3kW
Page 12
Page 13
1
2
2
6
7
8
9
10
11
12
14
15
16
3
If parts required are not identified, please contact Calomax Limited
Includes nuts, washers, etc.
Exploded parts view for Quasar 2 boiler
(To be read in conjunction with the spare parts list)
*
*
*
(Body cut away to show internal components & Outer Casing removed for clarity)
13
4
5
17
Page 14
Page 15
The auxiliary PCB controls the dispense valve and push button functions.
Should an element fail and need to be replaced, it may be necessary to replace the lid gasket to ensure a reliable steam-tight seal. Note: the element has a permanent ‘Live’ feed, and the
‘Neutral’ is switched.
Printed Circuit Board replacement (PCB)
In the event of a PCB failing and a replacement being required, full instructions will be supplied. It is important to note however, that the Triac PCB must be securely mounted against the copper heat-sink to ensure reliable heat dissipation. Heat transfer compound is also supplied with all replacement circuit boards.
Adjusting the Water Temperature Set Point
The temperature potentiometer (Pot) is pre-set at Calomax and will only require adjustment in exceptional circumstances. Contact Calomax for advice.
Water boils at different temperatures depending on barometric pressure. The temperature should not be tuned higher than 98
°C, or over boiling may occur during low barometric pressure
conditions, causing the unit to trip the overheat cut-out device.
On / Off Switch
The On / Off switch is positioned at the rear of the machine. When in the off position the unit will cease to function & the light on the fascia will go out. NOTE: This switch must not be used to isolate the electrical supply for servicing / maintenance. When maintaining / servicing the unit the power cord must be removed from the mains supply.
Note: Whenever the body lid has been removed from the boiler a new lid gasket may be required to ensure a steam-tight joint. Damage to the unit caused by a poor lid seal is not covered by warranty.
Scale deposits should be removed from all internal surfaces, particularly the heating element, thermistor and level sensors by gently tapping or scraping. If the deposits are soft, use a nylon pad and flush out. Abrasive cleaning materials containing scouring powders and detergents must not be used, such materials can cause taste problems.
Suitable chemical de-scalants must only be used in accordance with the manufacturer’s recommendations. This will prevent health and safety issues, taste problems and potential damage to the appliance. All trace of these chemicals must be removed from the appliance before re-commissioning the unit . Misuse of such chemicals is not covered by the product warranty.
IMPORTANT Before re-commissioning the boiler it is important that all scale and moisture is removed from the level sensor insulating gaskets, to avoid a false signal being transmitted through the scale to the boiler body. Failure to remove this scale and/or moisture could cause the sensor to indicate to the PCB that water is covering the element, whether or not water is present. In this situation the PCB could energise the element causing failure. If in doubt, protect the element by hand filling with water to the level of the draw-off tap before switching on the electrical supply to the boiler.
General function
The printed circuit board (PCB) controls the heating and filling functions of the boiler by monitoring the thermistor and level sensors. The PCB also controls the external light unit to indicate the current state of the boiler. Red and yellow LED’S on the circuit board indicate whether the PCB has energised the element or solenoid respectively.
Page 16
Page 17
Spare parts are usually available ex-stock. Please quote Model & Serial Number.
SPARE PARTS (Refer to centre pages for location).
NB: Not to scale.
SPARE PARTS (Refer to centre pages for location).
SINGLE POLE ON/OFF SWITCH ( INC. COVERS)
SPRSK
17
QDVMMK
QRAPCBTQPCBTDPBK
NB15BLGCASSVCAP330NBE3HK
FIH CASMRCASLPK NBPRG
MULLER DISPENSE
VALVE & GROMMET
DISPENSE VALVE
SERVICE KIT
MAIN PRINTED CIRCUIT
BOARD Inc. TRIAC
WATER DISPENSE PUSH
BUTTON Inc. FITTING TOOL
AUXILIARY PCB
ELEMENT 3kWTHERMISTOR
ASSEMBLY KIT
SOLENOID VALVEBODY LID GASKET
WATER INLET
HOSE
MANUAL RESET
THERMAL CUTOUT
LEVEL PROBES KIT BODY LID
GROMMET
1234
8765
91011 12
16151413
DVSK
QUFK
UPPER FASCIA KIT
LOWER FASCIA KIT
SERVICE VALVE KIT
QRLFK
SVK
X1
Page 18
Page 19
BASIC TROUBLE SHOOTING
Symptoms Possible Cause Remedy
No lights on
front of unit
On / Off switch in Off position
Thermal cut-out tripped
Switch to On position
Reset and check for faults
(i.e. scale on thermistor
No boiling water available
Normal level sensor holding a signal
Thermal cut-out tripped (no lights on fascia) On / Off switch in Off position
Element failed
De-scale
Reset and check for faults (i.e. scale on thermistor) Switch to On position
Replace element
Thermal cut-out trips regularly
Excessive internal scale. (See ‘De-Scale’ )
Faulty wiring to thermistors / faulty thermistors
Te mperature controller needs adjusting
Element failed to earth
Defective Main Printed Circuit Board & / or Triac PCB
De-scale the boiler (Particularly thermistor)
Repair / replace as required
Lower operating temperature
Replace element
Replace Circuit Board & Triac (sold as a matched pair)
Overflows
Dirt in solenoid valve.
Level sensors require de­scaling or replacing
Main Printed Circuit Board faulty
Clean solenoid filter / or replace solenoid, “work the boiler” ­see Service Instructions
De-scale / replace sensors
Replace Main Printed Circuit Board
Wiring Schematic for Calomax Quasar 2 Water Boiler
RED
YELLOW
BLACK
BLUE
PINK
BROWN
ORANGE
WHITE
+12Vdc (BROWN)
BLACK
RED
0.75mm YELLOW
0.75 WHITE OR 0. 5mm YELLOW BLACK
BLACK
RED
N
E
L
BLUE
BLUE
L
N
E
BLACK
YELLOW / GREEN
BLACK
BLACK
YELLOW / GREEN
RED
0Vdc (ORANGE)
RED
RED
ORANGE
YELLOW
RED
BLUE
CONNECTOR PLUG
COLD WATER INLET
SOLENOID VALVE
ELEMENT
TRIAC PCB
HIGH
NORMAL
LOW
LEVEL
SENSORS
HOT WATER OUTLET
DISPENSE VALVE
HEATER
LED
SOLENOID
LED
THERMISTOR
PUSH BUTTON
ON FRONT
PANEL
THERMAL
CUTOUT
EARTH
ON BODY
EARTH
ON BASE
ORANGE
BROWN
OPT1
U1
OP1
EARTH ON
CASING
SINGLE POLE
ISOLATING
SWITCH
Page 20
Page 21
MAINTENANCE AND SERVICE HISTORY MAINTENANCE AND SERVICE HISTORY
Page 22
Page 23
Calomax have manufactured water boilers in the UK for over 50 years. We are proud of our products and the back-up service we provide.
Properly maintained and serviced, a Calomax boiler should last many years and we have no hesitation in providing a full 12 months (mainland U.K.) parts and labour warranty for all models. Please complete and return the enclosed product registration form as soon as possible to activate this, or register online at : www.calomax.co.uk .
In addition, the Clipper, Kudos and Quantum models carry an additional 12 month back to base warranty.
Some factors are beyond our control and would invalidate the warranty offered. These include: Incorrect installation High / Low water pressure Incorrect voltage supply Accidental damage Limescale build-up
The last item can be a particular problem for water dispensing equipment in hard-water areas. All hot water equipment should be serviced and de-scaled by approved organisations on a regular basis to avoid a damaging build-up of limescale.
Although our boilers incorporate scale-inhibitor technology, we recommend that a taste, odour and scale filter should be fitted where appropriate.
Please visit our website www.calomax.co.uk for details of our Service Partner Network and the range of filters and accessories available.
WARRANTY GUARANTEE (UK Mainland customers only)MAINTENANCE AND SERVICE HISTORY
Page 24
Model QUASAR 2 Serial Number Draw off Capacity 9 Litres Heat-up Time
(first switch-on)
9 Litre capacity 45 Minutes Average flow rate from
dispense valve
2.8 Litres / Minute
Voltage 220 - 240 V ac 50-60 Hz Power rating 3kW (MAX)
PLEASE ENTER SERIAL NUMBER FOR FUTURE REFERENCE
Note: All measurements are approximate.
PLEASE CONTACT OUR SERVICE DEPARTMENT FOR ASSISTANCE
Calomax Limited, Lupton Avenue, Leeds LS9 7DD Tel: 0113 249 6681 Fax: 0113 235 0358 e-mail: service@calomax.co.uk
Loading...