FLOOR INFEED
LIQUID™ WORKSP ACE
Assembly Instructions
MODEL:
MSB-F2
MSP-F3
Use this instruction sheet in conjunction with the appropriate
instruction sheet from either the Substation or Support.
CAUTION:
T urn off all power prior to connecting or disconnecting
the liquid electrical components.
MUST BE INSTALLED BY A QUALIFIED ELECTRICIAN

Substation
Steps to connect Floor Infeed to Junction Box
Substation
parts removed
for clarity
Substation
skin open
position
Infeed
Floor
monument
Note 2. :
Infeed
Junction Box
open end
Fig. 1
Note 1. :
Substation Channel instruction sheet step 1 thru step 3 must be completed before
wiring can be done.
The open end of the Infeed is to be installed by a certified electrician.
Will require cover plate to have 1 1/8” knock out and an appleton 7289v
connector to complete connection.
STEP 1
Plug the other end of the Infeed into the Junction Box. Close the
Substation Skins.