Flush the water supply lines before beginning installation and after installation is complete. Test
the unit for leaks and adequate water flow. Main water supply to the eyewash should be “ON” at all
times. Provisions shall be made to prevent unauthorized shutoff.
CAUTION
Emergency equipment must be supplied with tepid water (60°F to 100°F/15.6°C to 37.8°C). Any
prolonged exposure to near freezing water affects the body's ability to maintain body temperature,
increasing the risk of hypothermia.
NOTICE
Before installing this product, ensure that there are adequate clearances around the product and
activation of the product does not interfere with other products or obstructions.
Avoid cleaners containing organic solvents, alcohols and hydrocarbons. Rinse with water after
cleaning.
IMPORTANT
The installation and location of all safety drench showers, eye and eye/face washes must comply
with the requirements of ANSI/ISEA Z358.1.
Read this installation manual completely to ensure proper installation, then file it with the owner or
maintenance department. Compliance and conformity to drain requirements and other local codes
and ordinances is the responsibility of the installer.
Separate parts from packaging and make sure all parts are accounted for before discarding any
packaging material. If any parts are missing, do not begin installation until you obtain the missing
parts.
The ANSI/ISEA Z358.1 standard requires an uninterrupted supply of flushing fluid. Bradley plumbed
emergency fixtures require a minimum of 30 PSI (0.21MPa) flowing pressure.
Self-closing spring-loaded valves are not UL classified to ANSI/ISEA Z358.1.
Weekly activation must be conducted on all plumbed emergency equipment to ensure a suitable
flushing fluid supply is present and any sediment build-up in the supply line is cleared. Emergency
equipment should be inspected monthly to address any maintenance issues ensuring the
equipment is in good operating condition and that there are no signs of wear.
Workers who may come in contact with potentially hazardous materials should be trained regarding
the placement and proper operation of emergency equipment per ANSI/ISEA Z358.1.
For questions regarding the operation or installation of this product, visit www.bradleycorp.com or
call 800-BRADLEY (272.3539).
Product warranties and parts information may also be found under ”Products” on our web site at
bradleycorp.com.
Supplies Required:
• Piping to ½" NPT water supply inlet on unit
• Bolts for cabinet mounting
• Pipe sealant
• Sign-mounting hardware
2
Local codes may require the installation of a backflow prevention valve
to complete proper installation. Compliance with local codes is the
responsibility of the installer. Valve must be tested annually to verify that
it is functioning properly. Backflow prevention valves are not included
with the fixture and may be supplied by the contractor or purchased from
Bradley Corporation.
TEST THIS UNIT EACH WEEK
DIESES GERÄT 1ST WÖCHENTLICH ZU PRÜFEN.
34
ESSAI HEBDOMADAIRE
Test-operate valve(s) each week and sign below.
Report any malfunctions immediately.
Ventil(e) wöchentlich im Testbetrieb prüfen, bestätigt
durch Unterschrift. Jegliche Störung sofort melden.
Test le fonctionnement des valves chaque semaine et
signe en bas. S'il y à quelque chose qui ne va pas fait
un rapport immédiatement.
Date
Signed
Datum
Unterschrift
Date
Signe
Date Signed
Date
Date
26
R
35
Signed
Signed
32
33
Prepack S65-339 includes items 26, 27, 28
Prepack S88-068 includes items 25, 26, 27, 28
28
27
Eye/Face Wash Cover
Prepack S45-2676 includes
items 22, 24a and 24b