LEGEND: Obtain Dimension from Bobrick Layout Sheet.
Fig. 1a: Floor-Anchored or Ceiling-Hung
Front-Entry Corner Layout.
Fig. 1b: Overhead-Braced
Alcove Closed Layout.
NOTE: The stiles are in-line with panel.
Fig. 1c: Floor-Anchored or Ceiling-Hung
Alcove Closed Layout. Inswing Door.
NOTE: The center stile is perpendicular to panel.
Fig. 1d: Floor-Anchored or Ceiling-Hung
Alcove Closed Layout. Outswing Door.
NOTE: The center stile is perpendicular to panel.
X Dim. = Stile Edge to Centerline of Mounting Hole. Y Dim. = Centerline-to-Centerline of Mounting Hole.
A. Refer to Bobrick layout sheets for component locations on your specific application.
B. From back wall, measure and mark the location of the stile centerline. Stile centerline = 1/2" (13mm) + panel length + gaps
specified on layout sheets.
C. From side wall and center of stile location, measure dimensions for floor or ceiling anchors according to layout sheet. Refer
to the drilling tables below for center-to-center distances between anchors. For exmaple: Overhead Braced stiles centerline
of floor anchor from edge of stile is 1" (25mm); dimension on 3" (8cm) stile is 1-1/2" (38mm).
Fig. 1e: Detail of Overhead
Fig. 1f: Detail of Floor Anchored or Ceiling Hung Stile
Braced Stile
Floor Anchored StileCeiling Hung or .63 Option Stile
NOTE: 16", 18", 20", 24" (41, 46, 51, 61cm) stiles have 2 leveling bars. Use the 2 outside
slots for the 2 anchors.
Drilling Table
Overhead-Braced Series — Standard & .64 OptionFloor-Anchored Series & Ceiling-Hung StilesCeiling-Hung Series & .63 Option
A. Based on stile size locate centerline of floor L-brackets
from Drilling Table. (See page 3).
B. Drill 5/16" (8mm) diameter hole to 1-3/4" (45mm)
minimum depth. Remove all loose material from holes.
C. Install plastic anchors into holes.
D. Place one shoe retainer bracket at each hole location.
E. Place floor L-bracket on top of and inside each shoe
retainer.
F. Install #14 x 1-3/4" (M6.4 x 45mm) floor screws to retain
bottom floor L-brackets and shoe retainers. Do NOT
tighten screws. Screws should be loose enough to adjust
the floor L-brackets.
G Using the stile as a measurement tool, adjust the floor
L-brackets to fit inside the stile brackets. Mark locations.
H. Remove stile and tighten floor screws securely.
NOTE: Wood-floor anchors are available upon request. To
install drill 3/16" pilot hole in the floor and install using #14 x
1-3/4" (M6.3 x 45mm) screws.
FLOOR ANCHORS. Standard & All .63 Options.
A. Drill 3/8" (9.5mm) diameter hole to 2" (50mm) minimum
depth. Remove all loose material from holes.
B. Insert expansion shield (threaded side down) with
threaded rod into mounting hole. Extra flat washers are
supplied. Place as many flat washers as necessary onto
rod to ensure shoe retainer is placed above finished floor
surface. Install and tighten a hex nut above washer(s) and
shoe retainer, tightening and expanding anchor to secure
to floor. Make sure when tightening bolt that shoe retainer
is positioned properly to accept shoe (see Fig. 2b or 10b
for proper shoe retainer position).
C. Add a second hex nut, then a flat washer.
D. Set aside the third hex nut, flat washer, and the lock
washer. Install when stile is placed on anchor bolts.
E. Repeat process for each floor anchor.
NOTE: Wood-floor anchors are available upon request.
Fig. 2a: Detail of Overhead Braced
Floor Anchor.
Fig. 2b: Detail of Floor Anchor.
CEILING ANCHORS. Standard & All .64 Options.
NOTE: Ceiling anchors are to be installed before finished
ceiling is applied. All structural framing is to be furnished by
others. For Bobrick recommendations, refer to Bobrick Form
No. TB-32.
A. Drill 7/16" (11mm) diameter hole through structural
beam. Insert threaded rod through hole in beam. Rod
is furnished standard 6" (150mm) length. Longer rods
should be purchased locally if required.
B. Drop a bevel washer and lock washer over rod. Screw on
one hex nut.
C. Install second hex nut against bottom of beam and
tighten.
D. Install spacer, shoe retainer, flat washer, and a third
hex nut. Make sure shoe retainer is in proper position to
accept shoe (see Fig. 2c or 10b for proper shoe retainer
position).
E. Install remaining flat washers (2), lock washer (1), and
hex nuts (2), as shown in Fig. 2b.
F. Repeat process for each ceiling anchor.