Wall Charger 2 Installation Guide
7.4kW TETHERED SINGLE PHASE :
EVWC2T7G (7.4KW / WI-FI / LAN)
EVWC2T7GG (7.4KW / WI-FI / LAN / 4G)
Contents
click to navigate directly to the page
Introduction / Box contents
Safety information
Installation & testing
Troubleshooting
Domestic Commissioning
Stage 1 (Installer app)
Domestic Commissioning Stage 2 (User app setup)
Technical
syncev.co.uk
EVWC2T7G EVWC2T7GG V2 0823 GJW
Page 2
Introduction
This guide is intended for use by competent electrical installers to explain basic requirements and options to be considered when installing a BG SyncEV charger. The unit is designed for installations inside or outside, the advanced safety technology we have built into the unit ensures its safe usage. This guide provides information to assist when installing the EVWC2Sx chargers and should not be used
3
WARRANTY
with other EV chargers.
Box contents
• EV charger with 7.5m tethered cable and Type 2 charging gun
• Decorative fascia
• Installation template & quick start guide
• Accessories pack containing:
year
» Power connector » Cord grip and screws » M25 gland » 25mm blind grommet » Bonded sealing washers
» Assembly screws » Anti-tamper bit » x1 CT clamp
(EVA120CT1)
» x1 CT clamp connector
Tools required
Hex bit holder, PZ2 screwdriver, suitable drill bit and fixings
Return to Contents
Page 3
Safety information
Warning: The supplied BG SyncEV charger is manufactured to be safe without risk provide they are installed correctly, used, and maintained in accordance with the manufacturers recommendations and installed by a competent electrical installer in accordance with national and local regulations and legislation applicable at the time of installation, e.g. BS7671:2018 amendment 2.
The EV Charger is suitable for use with a single phase (for up-to 7.4kW charging) 220-240V Nominal AC supply. The supply should run from a dedicated 40A circuit breaker. We recommend the use of a Type B curve circuit breakers. The EV charger features an integral 30mA type-A RCD with 6mA DC leakage detection and therefore an external RCD is not usually required:
1. For cables without earthed metallic covering
installed in walls or partitions at a depth of less than 50mm and also within walls and partitions with metal parts, and not protected by steel conduit or similar then RCD protection is required.
2. If the cable is clipped directly to the surface
of a wall and does not pass through a wall or partition to the EV charger then a standard B type 40A MCB may be installed into the Consumer unit, however RCD protection may be required for other reasons such as if it forms part of a TT system and the earth
Return to Contents
Page 4
fault loop impedance values cannot be met. This will be in compliance with the current BS7671 Amendment 2 Wiring Regulations. To conform with BS 7671, on occasions a two pole MCB/RCD or other means of isolation may be required.
Important note: A DC Leakage fault in the vehicle may “blind” a type “AC” RCD and render it ineffective, never feed any EVSE From an upstream Type “AC” RCD.
Earthing requirements
The supplied EV charger features an on-board safety monitoring system to detect low or high voltage supplies and potential earth-neutral faults, this in accordance with regulation 722.411.4.1 (iv) of BS7671 2018. If such a condition is encountered the charge cycle is ended or prevented and the EV charger indicator flashes red and effectively becomes a double insulated (class II) device. The vehicle becomes isolated in accordance with Regulation 543.3.3.101(ii) from incoming supply and poses no risk to touch. This feature removes the requirement for an earth electrode where it may be ineffective or introduce further risk.
The EV charger may be connected directly to a TN-C-S (PME) earthing system without any special arrangements. It remains the responsibility of the installer to conduct a risk assessment of the immediate area to a range of 10 meters (equipotential zone) to ensure no other conductive metal fixings pose risks (mixture
Return to Contents
Page 5
of TT/TN-S and TN-C-S), this is important where cable length may enable charging inside or outside of a building/garage where the vehicle is within touch distance.
Where certain conditions dictate an earth electrode must be used it shall be independent from the distributors earth system with no direct interconnection (the incoming supply SWA protective earth should be isolated from the housing and/ or earth electrode). The electrical installer shall install a suitable electrode complete with termination housing and covers where appropriate, warning labels should be visible and close to the unconnected SWA protective earth, e.g. inside the charger.
The earth connection shall be made from the electrode to the charger via copper conductor earth wire of an appropriate CSA for the installation. The earth wire shall be installed in conduit where there is a risk of mechanical damage or UV exposure. Recommended Earth electrode impedance to be <100 ohms.
Return to Contents
Page 6
Surge protection
Guidance on requirements for surge protection devices given In BS7671: section 443.
The EV charger is protected against transient over voltages (+/-2kV Line-Earth and +/-1kV Line­Line as a requirement of EN 61000-6-1), a direct lightning strike carries a current of 30~ 200kA the EV charger’s internal protection would provide little or no protection in such an event, likewise nor would an SPD rated less than 30kA. If life support equipment or business operations could be affected by a lightning strike central SPD protection is advised if it does not already exist.
The guidance on risk calculation in section 443.5 of BS7671 in most cases is not possible due to unknown location of any SPD already fitted, length of cables to calculate LP etc, it is therefore recommended a common sense approach is used on choice of SPD (or if required).
Return to Contents
Page 7
Isolation and switching for safety and maintenance
To ensure the EV charger can be “turned off” to enhance security and enable maintenance activities, a two pole isolator (or DP RCD or RCBO) suitably rated must be installed within the customer’s property.
An isolator switch is a mandatory requirement for “new builds”, but optional for existing dwellings (at customer’s request), the switch should be mounted between 500mm and 1500mm above finished floor level to comply with regulations. The switch should be rated at 45 Amps.
All installations must comply to BS7671: 2018.
Return to Contents
Page 8
Installation requirements
The EV charger is suitable for installation inside and outside on a solid wall or structure. The installer should consult with the building owner to establish their preferred installation location. This should take into consideration the length of charging cable and risk of vehicle impact etc.
It is recommended the charger is installed at a height of 500mm-1500mm as per building regulations BS8300:2018.
If no suitable permanent structure is available, the EV charger can be mounted to a stand. We recommend of the BG SyncEV stand, EVASTAND12S (single) or EVASTAND12T (twin).
Ensure suitable fixings are used depending on the mounting surface. To avoid unnecessary dust inside the enclosure, it is recommended to use the included fixing hole template drill the surface, before fitting the enclosure.
Ensure installation wall has been checked for electric cabling or pipework with a suitable detector.
NOTE: if any groundworks are required e.g. cable trenching or earth electrode fitment, it is advisable to check if underground services could be present before commencement. Plans may be available at: www.linesearchbeforeudig.co.uk (free to domestic users).
Return to Contents
Page 9
The EV charger is suitable for bottom or rear cable entry, if using rear cable entry ensure the included 25mm rubber grommet is used to maintain the IP rating.
If using SWA cable the included 25mm compression gland is NOT suitable, an alternative gland will be required. When using SWA please supply the charger from the bottom left cable entry point. A maximum hole size of 32mm is acceptable at this location. Its advisable to earth the SWA armouring at the supply end of the cable.
Do not drill alternative cable entries into the charger housing, except marked cable entry location for rear or bottom entry.
We recommend using BG SyncEV Power & Data Combined cable on installs that require a CT clamp to use the chargers dynamic load management capabilities.
All of the cables that are to be connected in to the supply connector should have their insulation striped back 18-20mm. Connectors supplied are suitable for cables of 4-10mm².
Return to Contents
Page 10
Load balancing
If load balancing is required, a CT clamp should be used for correct balancing. One BG SyncEV CT clamps, EVA120CT1, is supplied in the box with this charger. This should be fitted around the incoming power to the main fuse and the correct max load (A) to be entered during setup and installation steps.
Locate the main incoming power cable
1
into the property. The CT Clamp needs to be fitted before any of the tails are split for correct measurement.
Open the CT Clamp and fit around the
2
incoming Live power cable, this is typically marked brown for most installations.
Ensure the Arrow is pointing into the property from the incoming fuse. K towards Source, L towards Load.
External Mid Metering - RS485
If using an external Mid Meter connected via a RS485 connection the Dip switches need to be set. Dip 2 Up/On is required for external Mid Meter use.
Return to Contents
Page 11
Final Electrical testing
To meet the BS7671:2018 (18th edition) requirements for testing of an electrical installation, the following tests and checks shall be performed by a competent electrical installer before during and after a BG SyncEV charger is installed:
• A visual inspection of the installation
including the existing electrical installation.
• Verification of the characteristics of the
electrical supply at the origin of the installation to confirm the supply is suitable for the additional load.
• A test to confirm the continuity of the circuit
protective conductors.
• A test to confirm the integrity of the circuit
insulation resistance.
• A test to confirm the polarity of the
installation is correct.
• Where applicable a test to confirm the earth
electrode resistance is within acceptable tolerances. (or)
• An earth loop impedance test.
Return to Contents
Page 12
• A test of the mechanical operation of
residual current devices (RCD’s).
• A test to confirm the operation of residual
current devices (RCD’s) is within stipulated time scales (at the rated current and at five times the rated current operating current).
• A test or calculated measurement of the
prospective fault current.
• A verification of the functional operation of
the EV charger.
• An electrical installation certificate must be
completed.
Ensure electrical testing is done before EV charger commissioning and network setup is performed.
For this testing, the Charger can be set to “Plug and Charge” Mode in the installation App.
Return to Contents
Page 13
Electrical Installation
Isolate the power
1
Use the included hole template to
2
drill fixing holes
110 mm
145 mm
Return to Contents
Page 14
Drill base for required cable entry.
3
Suitable for 16-32mm hole size. If using rear entry, ensure
included 25mm grommet is used
Left for
SWA cable
Ensure the supplied washers are
4
used to maintain IP rating
Right for rubber/ flex cable
Return to Contents
Page 15
Ensure correct polarity when
5
making incoming power connections
3 pin plug: N - Blue E - Yellow/Green L - Brown
Ensure supplied cord grip is fitted
6
on incoming power cable if using bottom cable entry location
Return to Contents
Page 16
Ensure Power connector is fully
7
inserted then slide clip to secure
For dynamic load
8
balancing, insert wires into the small connector
If using external 485 meter, then dip switch 2 needs to be changed to ‘On’
1 32
+
1 2 3
485A PV CT
+
485B PV CT
‒
‒
Return to Contents
Page 17
Plug connector into PCB, ensure
9
correct polarity
10
Fix charger to the base ensuring correct torque settings
T25S Security Torx
2.5 Nm
Return to Contents
Page 18
11
Snap front cover trim into place
12
Fit locking screw to secure cover
Return to Contents
Page 19
Troubleshooting
For further information, or to refer to our FAQs, please visit our website:
www.syncev.co.uk
The status of the EV charger can be identified by referencing the colour shown on the LED indicator:
• Solid Blue – Standby – Charger has power
and is connected to the network. Or, if in ‘plug and charge’ mode is not connected to the network, is ready to charge.
• Flashing BLUE – Charger is connected but
not charging, awaiting confirmation of charge in APP or scheduled start time
• Solid Dark Green – Charger is active and
Charging
• Solid Yellow – Charger is offline from
network, check local network is active and Wi-Fi is working on the 2.4Ghz band
• Flashing Red – Indicates the charger is in
fault mode and has stopped charging for users safety
Potential causes:
• Internal RCD has tripped
• Vehicle fault
• Under or over suitable charging voltage
Remove connection to the vehicle and reset power to the EV charger.
Return to Contents
Page 20
Commercial / Workplace / Fleet installation & commissioning
4 simple steps:
1
CONTACT
Email [email protected] with the
charge-point owner contact details
2
CONNECT
Install the charge-points
3
CONFIGURE
Set the configurations in the
BG SyncEV installer app and connect
all chargers to the internet
4
COMPLETE
Pass the charger details to the
charge-point owner
How it works:
To streamline the process, email us
before the first day of installation
with the following information:
Return to Contents
Page 21
• Model and charger ID
(for every charger in the installation)
• Contact details for the charge-point owner:
• Company name
• Name of charge-point manager
• Site address
• Telephone number for charge-point manager
• Email address for charge-point manager
Our Commercial Team will contact the charge-point owner to carry out the quick and simply Monta setup process.
By using this process we will have the back-office set up for installation day, ensuring all chargers are immediately ready for customer use once configured.
Return to Contents
Page 22
Domestic Commissioning Stage 1 of 2
INSTALLER APP - Download the ‘BG SyncEV
Installer’ app by clicking this link
Also available from the Installer Portal on the
syncev.co.uk website, or using
the QR code opposite.
Upon powering the charger, the status indicator light will show Yellow. This indicates that the charger is ready for network setup but is not yet connected to the internet.
For Wi-Fi connection we recommend that the router is set to only 2.4GHz band to reduce the risk of possible conflicts. Once setup the router can be restored to both 2.4GHz & 5GHz bands.
Return to Contents
Page 23
1
1. Ensure Bluetooth is active on your device. Open the BG EV Charging App and select the Charger ID Code as shown on the charger identification label.
2
2. Then enter the password shown on the identification label.
Return to Contents
Page 24
–
3 6
3. Select ‘Monta’ - this is the included app. ‘EV.Energy’ and ‘SyncEV’ are alternative options (additional costs may be incurred). ‘Manual’ can be used for other alternative back offices. If unsure, choose ‘Monta’.
4. Charge Mode: ‘APP’ for smart charging via the consumer App (see next page); ‘Plug and Charge’ for non-smart charging. Use ‘Plug and Charge’ if connection to server cannot be established and car charging is required.
5. Max Charger Current: Set to max current supported by installation if less than default 32A.
6. Indicator Brightness: Adjust from 1 to 100% to change the brightness of the status indicator.
Return to Contents
Page 25
–
7 8
7. Dynamic Load management: If dynamic load management is required then toggle right and select Clamp Configuration.
8. Home Max Current: For load balancing this should be the same or less than the main fuse rating. EV charger will reduce its charging rate to limit the total home load to be under the limit. If the available current is under the minimum of 6A the EV charger will pause the charging session.
Press Next to save these settings.
Return to Contents
Page 26
9
9. Check the shown electrical measurements match measured readings. This will allow checking the Load management CTs are fitted correct orientation. Press Next to continue
10
10. Choose between Wi-Fi, 4G and LAN.
• For Wi-Fi select the SSID network name
and enter password.
• For LAN ensure that “Manually set Static
IP Address” is set to OFF (unless advanced settings are required).
• For 4G the setting will have been
pre-configured.
Multiple options can be selected if required, this will allow a fall-back, e.g From Wi-Fi to 4G if fitted in case of
network loss.
Return to Contents
Page 27
11
11. On LAN the charger will default to DHCP. If static IP is required for the network connection, set the option “Manually Set Static IP Address” to OFF and a manual IP address can be entered.
12. Press next to start network connection, the charger will attempt a network connection, If successful will then reboot to complete an RCD and function check.
Return to Contents
Page 28
In less than 2 minutes, the indicator should turn from Yellow to Blue to confirm network connection.
If the charger continues to show yellow, power cycle (switch off/on at fuse board) and reconnect via the app to check the settings are correct.
If still unable to connect to the network but need to use the charger then change the Charge Mode to ‘Plug and Charge’ and press ‘SET’ again to re-update settings.
If unable to establish network connection call 01952 983 940 or email: [email protected]
Note: The network connection from the device to the Internet is fully encrypted and secure. Additionally, no user data is stored on the charger.
Return to Contents
Page 29
STEP 3
OPEN THE APP
Follow the links to open the app.
Android
STEP 4
CREATE YOUR ACCOUNT
Create your account using your phone number or social logins (Apple/Google/Microsoft).
Domestic Commissioning Stage 2 of 2
1. Download the Monta smart app:
Apple app store click here
Google play store click here
or search for ‘Monta EV charging’ on Apple app store or Google Play
2. Using your smart-phone scan the unique
sheet supplied with the EV Charger.
If you’re unable to use the QR, open a web browser on your smart-phone and manually
Monta QR Code on the ‘Quick Start Guide’
type the URL on the sticker
3. Open the Monta app
iOS
Android
Return to Contents
Page 30
4. Create an account using your customers
SUCCESSFUL CONNECTION
When you reach this step, your charge point is con- nected and you can use Monta to start charging.
phone number or social logins (Apple/ Google/Microsoft)
5. Connect the EV charger to Monta - name the charge-point and set the location
Return to Contents
Page 31
6. Successful connection - When you reach this step, your charge-point is connected and you can use Monta to start charging
Need help with the app?
Contact Monta customer support through the app or via the website Monta.com
Need help with the charge-point?
Contact BG SyncEV technical support at:
or via the website at www.syncev.co.uk
Return to Contents
Page 32
Technical information
Environmental Protection
This symbol is known as the “Crossed­out Wheelie Bin Symbol”. When this symbol is marked on a product or battery, it means that it should not be disposed of with your general household waste. Some chemicals contained within electrical/electronic products or batteries can be harmful to health and the environment. Only dispose of electrical/electronic/battery items in separate collection schemes, which cater for the recovery and recycling of materials contained within. Your co-operation is vital to ensure the success of these schemes and for the protection of the environment.
Guarantee
BG SyncEV products are guaranteed against faulty materials and workmanship for a period of 3 years from date of delivery: products will be repaired or (at BG SyncEV’s discretion) replacements will be supplied or (at BG SyncEV’s discretion) a credit note will be issued. This guarantee is subject to BG SyncEV’s conditions of sale and in particular to the following conditions being met:
Return to Contents
Page 33
1. Notification of any defect is given to BG SyncEV as soon as reasonably practicable after becoming apparent, and the products then returned to BG SyncEV.
2. The products have only been operated under normal operating conditions and have only been subject to normal use.
3. No work (other than normal and proper maintenance) has been carried out to the products without BG SyncEV’s prior written consent.
4. The products have been assembled, or incorporated into other goods, by a qualified and recognised electrician and only in accordance with any instructions issued by BG SyncEV.
5. The defect has not arisen from an item manufactured or supplied by a person other than BG SyncEV.
6. 3 year warranty as standard, optional product registration can be completed on the BG SyncEV website.
Follow this link to visit our Warranty web-page
Return to Contents
Page 34
Technical data
CODES : EVWC2T7G
TYPE : TETHERED
SOCKET / PLUG : TYPE 2 PLUG
KW : SINGLE PHASE : 7.4KW, 32A MODE 3
MIN CHARGE CURRENT :
ELECTRICAL INPUT : SINGLE PHASE : 220-240V, 50-60Hz
COLOUR : BASE & BODY RAL 9005 (BLACK)
CABLE MANAGEMENT :
PEN PROTECTION : YES, IN-BUILT EARTH DISCONNECTION
EARTH ROD : NOT REQUIRED
RCD PROTECTION : YES, 6mA DC, 30mA AC TYPE-A, IN-BUILT
(7.4KW / WI-FI / LAN) EVWC2T7GG
(7.4KW / WI-FI / LAN / 4G)
CONFIGURABLE, 6 - 32A
TRIM - RAL 7016 (ANTHRACITE GREY) OPTIONAL COLOURED TRIMS AVAILABLE AS ACCESSORIES
BUILT IN CABLE WRAP & HOLSTER
OVERLOAD AND FAULT PROTECTION :
ELECTRICAL CLASS : CLASS 1, HOUSING CLASS 2
CONSUMER UNIT REQUIREMENTS :
LOAD BALANCING : 1x EVA120CT1 LOAD MANAGEMENT KIT
METER ACCURACY : 2% CLASS C EQUIVALENT INTERNAL
TERMINALS : COMBI SCREW FIRST FIX PLUG
INDICATOR : RGB LED AND BUZZER
OVER CURRENT AND FAULT PROTECTION
40A MCB OR 30mA TYPE-A RCD
(DEPENDENT ON CABLE TYPE &/OR ROUTE)
INCLUDED
METER WITH OPTION FOR CONNECTION TO EXTERNAL RS485 MODBUS METER
CONNECTOR
Return to Contents
Page 35
INDICATOR MODES : BLUE - STANDBY, FLASHING BLUE -
PREPARING, GREEN - CHARGING, YELLOW - NO NETWORK, RED - ERROR
HOUSING : UV STABILISED POLYCARBONATE
WALL FIXING : 4 POINT WITH HORIZONTAL AND
VERTICAL ADJUSTMENT, SUPPLIED FIXING HOLE TEMPLATE. FIXING HOLE CENTRES : 110 HORIZONTAL, 145 VERTICAL (MM)
IP / IK RATING : IP55 / IK10
SOC MODULE : AI ESP32-S SOC
WI-FI & ETHERNET : 2.4Ghz 802.11 B/G/N & RJ45
WI-FI SECURITY : WPA/WPA2/WPA2-ENTERPRISE/WPS
BLUETOOTH : 4.2 BR/EDR and BLE
CONNECTION PROTOCOL :
OCPP 1.6J
4G DATA : MODEL SPECIFIC
3 YEARS INCLUDED, WHEN USED WITH MONTA (ON THE INCLUDED PACKAGE). TOP-UP ONLINE TO CONTINUE SERVICE AFTER 3 YEARS
APP : POWERED BY MONTA
OPERATING TEMP : -25 TO +40°C
†
SOFTWARE &
OVER-THE-AIR
FIRMWARE UPDATE :
WARRANTY : 3 YEARS
STANDARDS & APPROVALS :
IEC61851-1, IEC61439-7, IEC62955, IC 61851-21-2, BS EN62196, EN301 511, EN 301 908-1/2/13, EN 301 489-3, EN 300 330, EMC COMPLIANT, CE, UKCA, THE ELECTRIC VEHICLES (SMART CHARGE POINTS) REGULATIONS 2021 INCLUDING SCHEDULE 1
Return to Contents
Page 36
SUPPLIED ACCESSORIES :
1x EVA120CT1 LOAD MANAGEMENT KIT, 5x BASE FIXING WASHERS, 5x ASSEMBLY LID BOLTS, 1x BLANKING PLUG AND 1x 25MM COMPRESSION GLAND, USER-SIDE CONNECTOR, CORD GRIP AND 2x CORD GRIP ASSEMBLY SCREWS
DIMENSIONS (MM) : 305 (H) x 201 (W) x 115 (D)
ADDITIONAL : ANTI TAMPER DETECTION - 2 LAYER
PROTECTION, BLUETOOTH TO BLUETOOTH COMMISSIONING
ACCESSORIES : SINGLE CHARGER STAND
(EVASTAND12S) TWIN CHARGER STAND (EVASTAND12T) CHARGING CABLES COLOURED TRIMS
(VARIOUS OPTIONS, SEE SYNCEV.CO.UK)
115 mm
201 mm
305 mm
Return to Contents
Page 37
Technical support
Need help with the app?
Contact Monta customer support through the app or via the website Monta.com
Need help with the charge-point?
Contact BG SyncEV technical support at:
or via the website at www.syncev.co.uk
BG SyncEV is a trading name of Luceco PLC. Luceco PLC – Stafford Park 1, Telford, TF3 3BD, England
(EU) Luceco SE – C/ Bobinadora 1-5, 08302 Mataro, Spain
Return to Contents
Loading...