Benchmark places responsibilities on both manufacturers and installers. The
purpose is to ensure that customers are provided with the correct equipment for
their needs, that it is installed, commissioned and serviced in accordance with the
manufacturer’s instructions by competent persons and that it meets the
requirements of the appropriate Building Regulations. The Benchmark Checklist
can be used to demonstrate compliance with Building Regulations and should be
provided to the customer for future reference.
Installers are required to carry out installation, commissioning and servicing work
in accordance with the Benchmark Code of Practice which is available from the
Heating and Hotwater Industry Council who manage and promote the Scheme.
Visit www.centralheating.co.uk for more information.
Building Regulations and the Benchmark Commissioning
Checklist
Building Regulations (England & Wales) require notification of
the installation of a heating appliance to the relevant Local
Authority Building Control Department. From 1 April 2005 this
can be achieved via a Competent Persons Self Certification
Scheme as an option to notifying the Local Authority directly.
Similar arrangements will follow for Scotland and will apply in
Northern Ireland from 1 January 2006.
The Health & Safety Executive operates the ‘Gas Safe Register’,
a self-certification scheme for gas heating appliances.
These arrangements represent a change from the situation
whereby compliance with Building Regulations was accepted as
being demonstrated by completion of the Benchmark Logbook
(which was then left on site with the customer).
With the introduction of Self Certification Schemes, the
Benchmark Logbook is being withdrawn. However, a similar
document in the form of a commissioning checklist and service
interval record is incorporated at the back of these instructions.
This company is a member of the Benchmark initiative and fully
supports the aims of the programme. Its aim is to improve the
standards of installation and commissioning of central heating
systems in the UK and to encourage the regular servicing of all
central heating systems to ensure safety and efficiency.
Building Regulations require that installations should comply
with manufacturer's instructions. It is therefore important that
the commissioning checklist is completed by the installer. The
relevant section of Building Regulations only relates to
dwellings. Therefore the checklist only applies if the appliance is
being installed in a dwelling or some related structure.
Applications for the copyright owner’s permission to reproduce or make other
use of any part of this publication should be made, giving details of the proposed
use, to the following address:
The Company Secretary, Baxi Heating UK Limited,
Brooks House, Coventry Road, Warwick. CV34 4LL
Full acknowledgement of author and source must be given.
WARNING: Any person who does any unauthorised act in relation to a
copyright work may be liable to criminal prosecution and civil claims for damages.
0086
The flowchart opposite gives guidance for installers on the
process necessary to ensure compliance with Building
Regulations.
IMPORTANT - Installation, Commissioning, Service & Repair
This appliance must be installed in accordance with the manufacturer’s instructions and
the regulations in force. Read the instructions fully before installing or using the
appliance.
In GB, this must be carried out by a competent person as stated in the Gas Safety
(Installation & Use) Regulations.
Definition of competence: A person who works for a Gas Safe registered company
and holding current certificates in the relevant ACS modules, is deemed competent.
In IE, this must be carried out by a competent person as stated in I.S. 813 “Domestic
Gas Installations”.
The addition of anything that may interfere with the normal operation of the appliance
without express written permission from the manufacturer or his agent could invalidate
the appliance warranty. In GB this could also infringe the Gas Safety (Installation and
Use) Regulations.
Warning - Check the information on the data plate is compatible with local supply
conditions.
All Gas Safe registered engineers carry an ID card with their licence number and a
photograph. You can check your engineer is registered by telephoning
0800 408 5500 or online at www.gassaferegister.co.uk
This company declare that no substances harmful to
health are contained in the appliance or used during
appliance manufacture.
The appliance is suitable only for installation in GB and IE
and should be installed in accordance with the rules in
force, and only used in a suitably ventilated location.
In GB, the installation must be carried out by a Gas Safe
Registered Installer. It must be carried out in accordance
with the relevant requirements of the:
• Gas Safety (Installation & Use) Regulations.
• The appropriate Building Regulations either The Building
Regulations, The Building Regulations (Scotland), Building
Regulations (Northern Ireland).
• The Water Fittings Regulations or Water Byelaws in
Scotland.
• The Current I.E.E. Wiring Regulations.
Where no specific instructions are given, reference should
be made to the relevant British Standard Code of Practice.
In IE, the installation must be carried out by a competent
Person and installed in accordance with the current edition
of I.S. 813 ‘Domestic Gas Installations’, the current Building
Regulations and reference should be made to the current
ETCI rules for electrical installation.
All systems must be thoroughly flushed and treated
with inhibitor (see section 6.2).
The boiler meets the requirements of Statutory Instrument “ The Boiler (Efficiency)
o
Regulations 1993 N
3083” and is deemed to meet the requirements of Directive
92/42/EEC on the energy efficiency requirements for new hot water boilers fired with
liquid or gaseous fuels:-
Type test for purpose of Regulation 5 certified by:
Notified Body 0087.
Product/Production certified by:
Notified Body 0086.
For GB/IE only.
Codes of Practice, most recent version should be used
In GB the following Codes of Practice apply:
StandardScope
BS 6891Gas Installation.
BS 5482 Part 1Butane & Propane Gas Installation
BS 5546Installation of hot water supplies for domestic
BS EN 12828Heating systems in buildings.
BS EN 12831Heating systems in buildings - Calculation of load.
BS EN 14336Installation & commissioning of water based
BS 6798Installation of gas fired hot water boilers.
BS 5440 Part 1Flues.
BS 5440 Part 2Ventilation.
BS 7074Expansion vessels and ancillary equipment for
BS 7593Treatment of water in domestic hot water
In IE the following Codes of Practice apply:
StandardScope
I.S. 813Domestic Gas Installations.
The following standards give valuable additional information;
BS 5546Installation of hot water supplies for domestic
BS EN 12828Heating systems in buildings.
BS EN 12831Heating systems in buildings - Calculation of load.
BS EN 14336Installation & commissioning of water based
BS 7074Expansion vessels and ancillary equipment for
BS 7593Treatment of water in domestic hot water
purposes.
heating systems.
sealed water systems.
central heating systems.
purposes.
heating systems.
sealed water systems.
central heating systems.
1. The Potterton Gold FSB 30 HE is a gas fired room
sealed fan assisted condensing central heating boiler.
2. The maximum output of the boiler is 30.18 kW (Non Condensing) 32.61 kW (Condensing).
3. The boiler is designed for use on Natural Gas (G20)
only.
4. The boiler is suitable for fully pumped open vented and
sealed systems, providing heating and hot water.
5. A label giving details of the model, serial number and
Gas Council number is situated on the rear of the drop
down facia panel (Fig. 1).
6. The boiler data badge is positioned on the air box door
(Fig. 2).
7. The boiler is intended to be installed in residential /
commercial / light industrial E.M.C. environments on a
governed meter supply only.
Air Box Door
Case Securing Screws
8. The boiler must be installed with one of the purpose
designed flues such as the standard horizontal flue kit, part
no 236921.
1.2Important Information
Man-made mineral fibre
• Some component parts of this boiler (insulation pads,
gaskets and rope seals) are manufactured from man-made
mineral fibre.
• Prolonged or excessive exposure to this material may
result in some irritation to the eyes, skin or respiratory
tract.
• It is advisable to wear gloves when handling these items.
• Irritant dust will only be released from the items if they
are broken up or subjected to severe abrasion. In these
instances a suitable dust mask and goggles should be
worn.
• Always thoroughly wash hands after installation,
servicing or changing components.
• When disposing of any items manufactured from manmade mineral fibre care must be exercised.
• If any irritation of the eyes or severe irritation of the skin
is experienced seek medical attention.
Standard Flue Kit 850mm (inc. elbow)236921
Extended Flue Kit - 1.75M ( inc. elbow)5111457
Flue Plume Deflector Kit248167
Terminal Guard (suitable for use with above)248484
FLUE EXTENSION KITS (110/70)
Flue Extension 250mm241692
Flue Extension 500mm241694
Flue Extension 1000mm
Flue Bend x 2 - 45°
1. Switched Live On: When switched live is supplied to
the boiler and the flow temperature is less than the set
point the sequence below commences.
2. Flow Switch: After 10 seconds if the flow switch has
made then fan pre-purge occurs. After 10 seconds if
the flow switch has not made then anti-cycle occurs.
3. Fan Pre-Purge: The flow switch is made and the fan
is on while the spark generator and gas valve are off.
After 5 seconds ignition occurs.
4. Ignition: The flow switch is made, fan, spark
generator and gas valve are on. If a flame is detected
then burner on occurs. If a flame is not detected within
5 seconds and less than 5 ignition attempts have been
made then fan purge occurs. If a flame is not detected
within 5 seconds and 5 ignition attempts have been
made then ignition lockout occurs.
5. Burner On: The flow switch is made, fan and gas
valve are on while the spark generator is off. Flow
temperature is controlled by varying the fan speed (and
thereby the gas rate) to achieve optimum operation. If
the flow temperature is greater than the set point or
the TRVs all shut down then fan post purge occurs.
Flame Detected ?
shut or Flow temperature
greater than set point ?
Fan Post Purge.
YES
YES
Burner On.
All TRVs
YES
5 second
All TRVs
shut down ?
Ignition done and
5 attempts made ?
YES
Ignition
Lockout.
6. Fan Post Purge: The fan is on while the spark
generator and gas valve are off. After 5 seconds if the
TRVs are shut down then anti-cycle occurs.
7. Anti-cycle: The fan, spark generator and gas valve
are off.
8. Ignition Lockout: The fan, spark generator and gas
valve are off. The boiler can only be reset by manually
using the reset button.
9. Condensate Pump: Condensate accumulates in a
reservoir within the pump assembly. The pump may
run at any time, independent of boiler operation, to
discharge the condensate to drain.
Both Sides- 5mm
Above Casing- 15mm
Above Casing
Under fixed worktop (It is recommended that any
worktop is removable)- 25mm
Front (For Servicing)- 500mm
Front (In Operation)- 5mm
Electrical Supply230V~ 50Hz
The boiler must be connected to an earthed
supply. A permanent and switched live are
required. The boiler has a 4 wire connection.
Power Consumption 80W
External Fuse Rating 3A
Internal Fuse Rating (BS 4265)
Fuse3.15 AT (PCB)
Electrical Protection IPXX
Water Content
litres2.6
Static Head
max30 metres
min1 metre
Low Head 0.2m min
System Detail
Fully pumped open vented & sealed systems.
No bypass required.
Controls
boiler thermostat, safety thermostat,
flow switch, electronic flame sensing,
temperature protection thermostat &
condensate blockage and level sensors
This value is used in the UK Government’s Standard
Assessment Procedure (SAP) for energy rating of
dwellings. The test data from which it has been
calculated has been certified by 0087.
1. The boiler is suitable for use with open vent fully
pumped systems and sealed systems .
The following conditions should be observed on all
systems:
•The static head must not exceed 30m of water.
•The boiler must not be used with a direct cylinder.
•Drain cocks should be fitted to all system low points.
•All gas and water pipes and electrical wiring must be
installed in a way which would not restrict the servicing
of the boiler.
•Position isolating valves as close to circulating pump as
possible.
6.2Treatment of Water Circulating
Systems
1. All recirculatory water systems will be subject to
corrosion unless they are flushed and an appropriate
water treatment is applied. To prevent this, follow the
guidelines given in BS 7593 “Treatment of Water in
Domestic Hot Water Central Heating Systems” and the
treatment manufacturers instructions.
2. Treatment must involve the use of a proprietary
cleanser, such as Sentinel X300 or X400, or Fernox F3
and an inhibitor such as Sentinel X100 or Fernox MB-1.
3. Full instructions are supplied with the products, for
further information contact Sentinel (0800 389 4670) or
Fernox (0870 870 0362).
Failure to flush and add inhibitor to the system will
invalidate the appliance warranty.
4. It is important to check the inhibitor concentration after
installation, system modification and at every service in
accordance with the inhibitor manufacturer’s instructions.
(Test kits are available from inhibitor stockists.)
5. For information or advice regarding any of the above
contact Technical Enquiries 0844 871 1555.
1. The sizes of flow and return pipes from the boiler
should be determined by normal methods, according to
the requirements of the system.
2. The connection tails for the boiler are 28mm diameter.
The 28mm section of the tails can be cut back to 22mm if
required.
3. The flow & return tails are push - fit ‘O’ ring
and clip connections within the boiler case.
4. A 20 °C drop in temperature across the system is
recommended for condensing boilers. Existing radiators
may be oversized and so allow this, but where radiator
sizing is marginal it may be advisable to retain a system
temperature drop of 11°C.
5. In systems using non-metallic pipework it is necessary
to use copper pipe for the boiler Flow and Return. The
copper must extend at least 1 metre from the boiler and
include any branches (Fig. 9).
Boiler Air
Vent
Fig. 10
Fig. 11
Boiler
Typical Low Head Installation
45°
15mm
Cold
Feed
22mm
Open Vent
400mm
Min Head
150mm
Max
Return
500mm
1000mm
Min
If Conditions Require,
This System Possible
Pump
6. This boiler does not require a bypass.
6.4Low Head Installation
1. Using a close couple arrangement the minimum head is
as shown in the diagrams (Figs. 10 & 11) subject to the
following conditions:
a) The pump being adjusted to give a 20°C drop across
the boiler.
b) The pump must be fitted on the flow.
c) The pump must be fitted in accordance with the
pump manufacturer's instructions.
d) The open vent pipe must be taken up from a tee in a
horizontal section of the flow pipe.
Flow
2. For heads below 400mm then an alternative utilising a
combined vent and feed pipe may be connected (Fig. 12).
This must be a minimum of 22mm diameter. It is
recommended that an air separator is fitted when using a
combined feed and vent pipe.
This boiler requires a permanent live for
operation of the condensate pump and frost
protection.
b
w
Cylinder
Stat
1
C2
Y Plan
Diverter
Valve
gr
o
1. To comply with Part L1 of the Building Regulations the
heating system into which the boiler is installed should
include the following:
a) zone controls
b) timing controls
c) boiler control interlocks
System Control
S/LNE
P/L
Wiring Centre
Timer
L
N
CH on
HW on
HW off
LNE
Pump
Y Plan, Room Thermostat System, CH Interlocked By Room Thermostat,
DHW Interlocked By Cylinder Thermostat
At least the Radiator(s) near the Room Thermostat not TRV’d
Pump run from Switched Live
Boiler Connection
(4 Core Wire)
2. Such a system needs to be fully pumped and must
provide independent temperature and time control to
both the heating and hot water circuits and have a boiler
and system pump interlock.
3. The boiler should be controlled so that it operates on
demand only. Where it is proposed to effect control by
thermostatic radiator valves a room thermostat should
also be provided to switch off the boiler when there is
no demand for heating.
S Plan, Room Thermostat System, CH Interlocked By Room Thermostat,
DHW Interlocked By Cylinder Thermostat
At least the Radiator(s) near the Room Thermostat not TRV’d
Pump run from Switched Live
Vessel Charge Pressure = 1.0 bar
Initial System Pressure = 1.5 bar
Then :-
75 x 0.152 = 11.4 litres
Expansion Vessel Volume
NOTE
Where a vessel of the calculated size is not obtainable then
the next available larger size should be used.
3 Litre
Top Up Bottle
(if required)
Radiator
Circuit
Multiply Total
Water Content Of
System By (Litres)
0.067
0.112
0.207
0.441
0.087
0.152
0.330
0.125
0.265
6.0System Details
6.7Sealed Systems (Fig. 13)
1. SAFETY VALVE - A safety valve complying with the
requirements of BS 6750 Part 1 must be fitted close to
the boiler on the flow pipe by means of a horizontal or
vertically upward connection with no intervening valve
or restrictions and should be positioned to facilitate
testing. The valve should be pre-set and non-adjustable
to operate at a pressure of 3 bar (45 Ibf/in
arranged to discharge any water or steam through a pipe
to a safe outlet position.
2. PRESSURE GAUGE - A pressure gauge of minimum
range 0-4 bar (0-60 Ibf/in
2
) with a fill pressure indicator
must be fitted to the system, preferably at the same
point as the expansion vessel in an easily visible position.
3. EXPANSION VESSEL - An expansion vessel
complying with the requirements of BS 4814 must be
fitted to the system by means of a connection close to
the inlet side of the circulating pump in accordance with
the manufacturers instructions, the connecting pipe being
unrestricted and not less than 15mm (
The volume of the vessel should be suitable for the
system water content and the nitrogen or air charge
pressure should not be less than the system static head
(See Table. 1).
Further details of sealed system design can be obtained
from BS 5449 and the British Gas publication entitled
'Specifications for Domestic Wet Central Heating
Systems'.
4. FILLING POINT - A filling point connection on the
central heating return pipework must be provided to
facilitate initial filling and pressurising and also any
subsequent water loss replacement / refilling. The sealed
primary circuits may be filled or replenished by means of
a temporary connection between the primary circuit and
a supply pipe provided a ‘Listed’ double check valve or
some other no less effective backflow prevention device
is permanently connected at the inlet to the circuit and
the temporary connection is removed after use. The
filling method adopted must be in accordance with all
relevant water supply regulations and use approved
equipment.
Your attention is drawn to, for GB: Guidance G24.2 and
recommendation R24.2 of the Water Regulations Guide.
for IE: the current edition of I.S. 813 “Domestic Gas
Installations”.
5. MAKE UP SYSTEM - A method of replacing water
lost from the system should be provided either by
means of a make up vessel of not more than 3 litres (5
pints) capacity, mounted above the highest point of the
system, or by re-pressurisation of the system.
6. VENTING - A method of venting the system during
filling and commissioning must be provided by fitting
automatic air vents or by venting manually.
7. HOT WATER STORAGE - The hot water storage
vessel must be of the indirect coil type.
8. COMPONENTS - All components used in the system
must be suitable for operation at 110°C (230°F) and at
the pressure allowed by the safety valve.
CH
Return
Page 15
Zone 1
Zone 2
Window
Recess
Zone 2
7.0Site Requirements
7.1Location
NOTE: Due to the high efficiency of the boiler a
plume of water vapour will be discharged from the
flue. This should be taken into account when siting
the flue terminal.
1. The boiler must be fitted on a suitable flat and level
surface capable of supporting the weight. Any wall behind
the boiler must be at 90° to the floor to allow case top
cover to fit correctly.
2. The flue must pass through an outside wall or roof and
discharge to atmosphere in a position permitting
satisfactory removal of combustion products and
providing an adequate air supply.
Fig. A
Zone 1
Zone 0
Zone 0
Window
Recess
Zone 2
0.6 m
In GB Only
Window Recess
Zone 2
Zone 2
2.25 m
Ceiling
Outside Zones
3. The boiler should be fitted within the building unless
otherwise protected by a suitable enclosure i.e. garage or
outhouse.
4. The boiler incorporates a frost protection device. This
will only protect the boiler. To ensure protection of the
system pipework and components it is recommended to
incorporate an appropriate device within the system
controls.
5. If the boiler is fitted in a room containing a bath or
shower, it can only be fitted in Zone 3, (Figs. A & B
shows zone dimensions for a bathtub. For other
examples refer to the Current I.E.E. Wiring Regulations).
Reference must be made to the relevant requirements:In GB this is the current I.E.E. Wiring Regulations and
Building Regulations.
In IE reference should be made to the current edition of
I.S. 813 “Domestic Gas Installations” and the current
ETCI rules.
6. If the boiler is to be fitted into a building of timber
frame construction then reference must be made to the
current edition of Institute of Gas Engineers Publication
IGE/UP/7 (Gas Installations in Timber Framed Housing).
1. Where the boiler is installed in a cupboard or
compartment, no air vents are required for cooling
purposes providing that the minimum dimensions below
are maintained.
Width400mm
Height875mm
Depth525mm
2. Any compartment should be large enough to house
the boiler only.
15
Page 16
5mm Min
390mm
5mm Min
15mm Min
(25mm if under
non removable
worktop)
7.0Site Requirements
7.3Clearances (Figs. 15 &16)
1. These dimensions include the necessary clearances
around the boiler for case removal, spanner access and air
movement. Additional clearances may be required for the
passage of pipes around local obstructions such as joists
running parallel to the front face of the boiler. For side flue
installations also See Section 8.1, Figs. 20 & 21.
2. It is recommended that any worktop is removable for
servicing access.
Fig. 15
850mm
7.4Gas Supply
1. Check that the information concerning the state of
adjustment given on the data plate is compatible with local
supply conditions.
2. The gas installation should be in accordance with the
relevant standards. In GB this is BS 6891. In IE this is the
current edition of I.S. 813 “Domestic Gas Installations”.
3. The connection to the boiler is a 15mm tail on the gas
service cock. The tail protrudes through the boiler rear
panel and is protected by a transit bracket which may be
removed to aid connection.
4. Ensure that the pipework from the meter to the boiler
is of adequate size. (If the boiler is further than 3 metres
from the Gas Meter 22mm pipe should be used). Do not
use pipes of a smaller diameter than the boiler gas
connection.
7.5Electrical Supply
1. External wiring must be correctly earthed, polarised and
in accordance with relevant regulations/rules. In GB this is
the current I.E.E. Wiring Regulations. In IE reference
should be made to the current edition of ETCI rules.
NOTE: “The method of connection to the electricity
supply must facilitate complete electrical isolation of the
appliance and system”.
Connection may be via a fused double-pole isolator with a
contact separation of at least 3mm in all poles, which mustbe in an accessible position to the user and serve the
boiler and system controls only.
There is no method of isolating the boiler at the user
interface.
3. Four core cable is required to supply the boiler as a
permanent live is necessary for the operation of the
condensate pump and frost protection.
520mm
In Operation
Page 17
7.0Site Requirements
4
3
2
Head (metres)
1
0
1.5
Min. radius 100mm
Point ‘A’
Condensate Pump Flow Graph
2
2.5
Flow (l/min)
3.5
3
Gravity Drain min. fall 3°
7.6Condensate Drain - General
Failure to install the condensate discharge pipework
correctly will affect the reliable operation of the boiler.
1. Ensure the discharge of condensate complies with any
national or local regulations in force.
BS 6798 & Part H1 of the Building Regulations give further
guidance.
2. If any further drain pipe is required (additional to that supplied
with the boiler), it should be run in a proprietary material
e.g. PVC, PVC-U, ABS, PVC-C or PP.
4
3. Metal pipework is NOT suitable for use in condensate
discharge systems.
4. Any pipe fitted externally must be kept as short as possible to
minimise the potential of freezing and must be insulated using
waterproof material.
5. When discharging condensate into a soil stack or waste pipe
the effects of existing plumbing must be considered.
7.7Condensate Disposal
Fig. A
Boiler
Max. Head
3 metres
Note: The point of discharge from
the pumped length of condensate
pipe (point ‘A’) must not be below
the level of the pump, whether
discharging direct into a drain or
into an additional gravity drain.
Alternative Horizontal
Discharge
10mm PVC Pipe
(8.5mm I.D.)
Securing Clip
8.5mm Ø O.D.
1. This boiler incorporates an automatic pumped condensate
system. See the graph opposite for available pump flow rates.
2. 3.5 metres of flexible 10mm PVC pipe are supplied with the
boiler. 0.5 metres of this length remains coiled within the boiler
to allow removal of the pump assembly. This must not be
uncoiled to provide extra length.
3. A fitting and securing clip (Fig. B) to accept the 10mm PVC
pipe and connect to 21.5mm overflow pipe is also supplied.
4. The 10mm pipe can be routed to a maximum of 3 metres
vertically and then discharge via gravity or be routed horizontally
(Fig. A). A combination of vertical and horizontal runs is
permissible.
5. The pipe must be supported, either using suitably spaced clips
or run within larger diameter pipe. When using clips take care
not to deform the pipe.
6. When routing the pipe through a wall it must be suitably
sleeved. Also the pipe must not be exposed to sources of heat,
and should be protected in locations where it may be damaged.
7. The pipe should be routed so that any sharp bends, dips and
loops are avoided. A minimum radius of 100mm is
recommended for any bends. No slope is necessary and air
breaks are not required on the pumped part of the condensate
run.
8. If the boiler is fitted in an unheated location the entire length
of condensate pipe should be treated as external, and run within
insulated larger diameter pipe.
17
Page 18
7.0Site Requirement
10°
10°
Termination via internal discharge branch e.g
sink waste - downstream
Direct Connect Fitting
Sink
From Boiler
Fig. C
Pipe must terminate
above water level but
below surrounding surface
From Boiler
Branch of Tee to be
± 10° from vertical
Termination to an internal soil and vent pipe
Direct Connect Fitting
Min. 450mm
Fig. D
7.7Condensate Disposal (cont.)
9. Ensure that the condensate can discharge freely (without
blockage or restriction of the pipe) into the drain.
10. Examples are shown of condensate pipe methods of
termination:-
i) via an internal discharge branch
(e.g. sink waste) - Fig. C.
ii) to an internal or external soil and vent pipe -
Fig. D.
iii) to a drain or gully - Fig. E. Ensure that the
condensate can discharge freely (without
blockage or restriction of the pipe) into the
drain.
iv) to a soakaway - Fig. F.
Termination to a drain or gully
From Boiler
Fig. E
Pipe must terminate above
water level but below
surrounding surface
Termination to a purpose made
soak-away
From Boiler
Fig. F
500mm Min
Holes in the soak-away must
face away from the building
Terminal Position with Minimum Distance (Fig. 17)(mm)
AaDirectly below an opening, air brick, opening
windows, etc.300
BaAbove an opening, air brick, opening window etc.300
CaHorizontally to an opening, air brick, opening window etc.300
D Below gutters, soil pipes or drain pipes.25
E Below eaves.25
FBelow balconies or car port roof.25
G From a vertical drain pipe or soil pipe.25
H From an internal
(i)
or external
(ii)
corner.
(i)
(ii)
25
115
IAbove ground, roof or balcony level.300
JFrom a surface or boundary line facing a terminal.600
K From a terminal facing a terminal (Horizontal flue).1200
From a terminal facing a terminal (Vertical flue).600
LFrom an opening in carport (e.g. door, window)
into the dwelling. 1200
M Vertically from a terminal on the same wall.1500
N Horizontally from a terminal on the same wall.300
R From adjacent wall to flue (vertical only).300
SFrom an adjacent opening window (vertical only).1000
T Adjacent to windows or openings on pitched and flat roofs600
U Below windows or openings on pitched roofs2000
a
In addition, the terminal should be no nearer than 150 mm to an
opening in the building fabric formed for the purpose of accommodating
a built-in element such as a window frame. See BS 5440 Pt. 1.
7.0Site Requirements
7.8Flue
NOTE: Due to the high efficiency of the boiler a plume of
water vapour will be discharged from the flue. This should
be taken into account when siting the flue terminal.
1. The following guidelines indicate the general requirements
for siting balanced flue terminals.
For GB recommendations are given in BS 5440 Pt.1.
For IE recommendations are given in the current edition of I.S.
813 “Domestic Gas Installations”.
2. If the terminal discharges onto a pathway or passageway,
check that combustion products will not cause a nuisance and
that the terminal will not obstruct the passageway.
3. When siting the flue take into consideration the effect the
plume of water vapour may have on neighbours .
4. Adjacent surfaces close to the flue terminal may need
protection from the effects of condensation. Alternatively a flue
deflector kit (part no. 248167) is available.
5. For installation of the flue into an internal corner at the
25mm dimension the flue plume deflector kit (part no. 248167)
must be fitted.
NOTE: The distance from a fanned draught boiler terminal
installed parallel to a boundary may not be less than 300mm
in accordance with the diagram below, unless the flue deflector
kit is used (see 7.8.6 opposite)
*
Fig. 16a
IMPORTANT: If fitting a Plume
Displacement Flue Kit, the air inlet
must be a minimum of 150mm from
any opening windows or doors.
U
D
C
I
A
E
S
F
A
H
H
R
I
F
T
J,K
N
M
I
B
L
A
G
I
6. * Reduction to the boundary is possible down to 25mm but
*
the flue plume deflector kit (part no. 248167) must be fitted.
7. If a terminal is less than 2 metres above a balcony, above
ground or above a flat roof to which people have access, then
a suitable terminal guard must be provided.
8. If required a suitable terminal guard (part no. 248484) is
available from Potterton for use with the flue deflector. See
also Section 8.8.
9. For fitting under low soffits and eaves the Plume
Displacement Kit or Flue Deflector Kit is recommended.
IMPORTANT:
• Only ONE 25mm clearance is allowed per installation.
• Under car ports we recommend the use of the plume
displacement kit.
• The terminal position must ensure the safe and
nuisance - free dispersal of combustion products.
Concentric
The maximum equivalent lengths are 4m (vertical). Their
lengths exclude the standard elbow and terminal assembly
(vertical).
Twin Flue
The total maximum equivalent flue length is 150m.
NOTE: Each 1m of flue duct should be calculated as 2m.
Any additional “in line” bends in the flue system must be
taken into consideration. Their equivalent lengths are:
Concentric Pipes:135° bend0.5 m
93° bend1.0 m
Twin Flue Pipe:135° bend (air duct)1.3 m
135° bend (flue duct)2.6 m
90° bend (air duct)4.8 m
90° bend (flue duct)9.6 m
(i)
Vertical Flue
System Examples
Total Equivalent Length =
A+B+C+1x90°Bend
All vertical and angled runs must be included,
measured from the boiler adaptor (point X) to the
joint with the flue terminal (point Y). One 91.5°
bend or two 135° bends can be included without
reduction of the flue length.
If further elbows are required the flue length must
be reduced by the following amounts:-
1 metre for each 91.5° bend
(ii)
0.5 metre for each 135° bend
B
A
(i)
Roof
Terminal
C
This bend is equivalent to
1 metre
IMPORTANT: All flue systems must be securely
supported at least once every metre. Suitable pipe
supports are available as accessories.
1. In the case of a pitched roof 25 - 50 degrees, position
the lead tile to replace/flash over existing roof tiling. Make
an aperture in the roof suitable for the lower tube of the
roof terminal and ensure the integrity of the roof cover is
maintained. The adjustable plastic collar can either be
positioned on the lead tile or the lower tube of the roof
terminal prior to the final positioning of the vertical flue
through the tile. Check the collar is correctly located to suit
required roof pitch (either 25° to 38° or 37° to 50°). From
inside the roof adjust the flue to a vertical position and
secure to the roof structure with the clamp supplied.
2. For flat roof installations the aluminium flashing must be
incorporated into the roof covering and the appropriate
aperture made in the roof decking. The vertical flue is
lowered onto the flashing making sure the collar of the flue
locates securely with the flashing. (A mastic seal may be
necessary). From inside the roof, adjust the flue to a vertical
position and secure to the roof structure with the clamp
supplied.
IMPORTANT: If the boiler is not fitted immediately
after the flue system, temporary precautions must be
taken to prevent rain entry into the room of installation.
Any precautionary measures must be removed prior to
commissioning the boiler.
270mm800mm
Fig. 18
Flue Deflector
Fig. 18a
8.7Flue Dimensions
The standard horizontal flue kit allows for flue lengths
5
between 270mm (10
/8”) and 800mm (32”) from elbow to
terminal (Fig. 18).
The maximum permissible equivalent flue length is: 4
metres.
NOTE: Each additional 45° of flue bend will account
for an equivalent flue length of 0.5m.
eg. 45° = 0.5m, 90° = 2 x 45° = 1m etc.
8.8Terminal Guard (Fig. 19)
1. When codes of practice dictate the use of terminal
guards, they can be obtained from most Plumbers’ and
Builders’ Merchants.
2. When ordering a terminal guard, quote the appliance
model number.
3. The flue terminal guard should be positioned centrally
over the terminal and fixed as illustrated.
1. If required, push the flue deflector over the terminal end
and rotate to the optimum angle for deflecting plume.
Secure the deflector to the terminal with screws provided.
Fig. 19
Page 25
Plume Outlet (‘Peak’
MUST be Uppermost)
0.94 metre
9.0Plume Displacement
9.1Plume Displacement Kit (P.D.K.)
Kit No 5121371
Content of kit
1 70/110 Concentric Flue
1 1m 70 Dia Exhaust Flue Pipe
2 Support Brackets
1 93° Elbow/Plume Outlet Assembly
1 Flue Trim
2 “O” Rings
1 Elbow with Gasket
1. This kit is recommended for installations where the
condensate plume emitted from the flue may cause a nuisance
or affect the surroundings.
2. The terminal must be positioned outside the building with
the outlet connection upwards.
3. The 70Ø pipe connects to the outlet of the concentric
terminal assembly. The elbow/plume outlet must be fitted to
the end of the 70Ø pipe.
45°
45°
Outlet must be
at least 45° from
wall face
Fig. C
‘Peak’ MUST be
Uppermost
NOTE: The plume outlet must always be at least 45° to
the wall, with the ‘peak’ uppermost to prevent rain entry
(Figs. A & B), and be at least 2 metres above ground level.
It must be secured as shown in Fig. C.
The outlet must be positioned so that any condensate
plume is directed away from adjacent surfaces.
4. It is possible to reduce or increase (with the addition of
extensions) the length of either or both the 70/110 concentric
and 70Ø exhaust.
5. Standard concentric flue extension kits may be added
between the boiler elbow and the terminal assembly.
6. The minimum length of the concentric flue is 100mm when
measured from the edge of the boiler flue elbow. There is a
further 45mm engagement into the elbow.
IMPORTANT: The maximum equivalent length of
concentric flue is:- 4 metres
Additional elbows may be fitted in the concentric flue, but
the equivalent length must be reduced by 1 metre (93°
elbow) or 0.5 metres (45° elbow).
7. 70Ø 1 metre extensions (including support bracket), and
additional 93° & 45° elbows are available. Any additional 93°
& 45° elbows must be accounted for when calculating flue
lengths. 70Ø 93° elbows are equivalent to 3.5 metres of
straight length and 45° elbows to 1 metre.
NOTE: Permitted positions of the plume outlet relative to
doors, windows etc. are the same as for conventional
concentric flues as detailed in the main Installation &
Servicing Instructions and BS5440 Pt. 1. It is NOT
necessary to fit a terminal guard over the air inlet or the
plume outlet.
25
Page 26
30
28
26
24
22
20
18
16
14
12
10
70Ø Exhaust (metres)
8
6
4
2
0
0
Example 1
30
1
Concentric 70/110 Flue (metres)
Flue Lengths - Not Permissible
70Ø Exhaust
234
30
28
26
24
22
20
18
16
14
12
10
70Ø Exhaust (metres)
8
6
4
2
0
0
Example 3
Flue Lengths - OK
30
28
26
24
22
20
18
16
14
12
10
70Ø Exhaust (metres)
8
6
4
2
0
Example 2
Flue Lengths - OK
30
1
234
Concentric 70/110 Flue (metres)
0
1
30
234
Concentric 70/110 Flue (metres)
Support
Bracket
9.0Plume Displacement
9.2Determining Permissible Lengths - P.D.K.
In the graph the solid line diagonal represents the
relationship between the concentric flue assembly (and any
extensions) and the 70Ø exhaust (and any extensions or
additional bends).
Example 1 - Not Permissible
If, for instance, a concentric length of 3.25 metres was
required and the 70Ø exhaust needed to be 10 metres the
graph shows that this combination would NOT be
permissible as the intersection point would be above the
solid diagonal line.
Example 2 - Flue Lengths OK
Where both lengths have been determined they can be
applied to the graph to check that the installation is
permissible. For example, if it was known that 2 metres of
concentric flue and 4 metres of 70Ø exhaust were required,
the values could be applied to the graph as shown in
Example 2.. As the point of intersection of the dotted lines is
below the solid diagonal line, the combination of lengths is
shown to be acceptable.
Example 3 - Flue Lengths OK
In the example shown, assume that the concentric part of
the flue needs to be 2 metres long. Find the position of ‘2’ on
the horizontal axis of the graph and then project upwards to
the solid diagonal line. This is represented by the vertical
thick dotted line. Where this dotted line intersects with the
solid diagonal line on the graph, project across to the vertical
axis. As can be seen this corresponds with 14 metres.
Therefore, the total equivalent length of the 70Ø exhaust
can be up to 14 metres. Any elbow equivalencies must be
accounted for i.e. 93° elbows are equal to 1 metre, each 45°
elbow to 0.5 metres.
Y
Concentric 70/110 Flue
(MUST be installed
horizontally)
Additional Accessories
A - 93° Elbow5117381
B - 45° Elbow (Pair)5117382
C - 1 metre 60Ø Extension 5117380
In Fig. D opposite an additional 93° elbow and pair of 45°
elbows have been included in the 70Ø exhaust.
Also 3 straight extension pieces have been used.
To calculate total length:Length of 70Ø supplied in kit = 1 metre
3 x 1 metre Extensions =3 metres
1 x 93° Elbow =1 metre
2 x 45° Elbow =1 metre (0.5 metres each)
Total 70Ø =6 metres
After consulting the table in Example 3 it can be determined
that the concentric flue could be up to approximately 3.25
metres long.
Page 27
Min. 2 metres
Min. 0.3 metres
This section of the
flue MUST be
horizontal
9.0Plume Displacement
9.3General Fitting Notes - P.D.K.
1. Cut a hole in the external wall which the horizontal
concentric flue assembly will pass through.
2. When completed the terminal must be at least 2 metres
above ground level (Fig. E).
3. Measure and cut to size the concentric assembly and any
extensions that are being used.
4. Insert the concentric assembly through the hole from
outside the building and mark the position of the flue trim
securing holes.
5. Drill and plug the wall to accept the flue trim securing
screws, and re-insert the concentric assembly through the
wall.
6. Connect any extensions that are being used to the
concentric assembly. Engage the extension or concentric
assembly in the boiler flue elbow.
Fig. F
Fig. E
7. Fit the boiler flue elbow to the boiler top panel, ensuring
the gasket is in place (Fig. F).
Ensure that the concentric assembly is horizontal and that
the external air inlet is to the bottom. Any extensions
should fall back to the boiler.
8. Use suitable brackets to support the concentric assembly
and any extensions, and make good inside and outside.
Secure the flue trim to the wall.
9. The 70Ø exhaust can now be fitted to the spigot at the
terminal end.
10. If it is necessary to shorten the 70Ø exhaust or any of
the extensions, the excess material must be cut from the
plain end of the pipe.
11. Determine the position of the 70Ø exhaust and mark
on the wall a suitable position for the support bracket. Drill
and plug the wall. If extensions are being used, a support
bracket is supplied in each kit.
12. Engage the M6 threaded part of the mounting bolt in
the boss on the support bracket. Using the bracket for
leverage, screw the mounting bolt into the plugged hole
until the bracket is secure and level (Fig. G).
13. Slacken the two screws securing the retaining strap to
the bracket, and pivot the strap aside to allow fitting the
70Ø exhaust.
14. Complete the installation of the 70Ø exhaust, securing
in the brackets. Fit the 93° elbow and plume outlet. Ensure
the plume outlet is at least 45° to the wall and that the
‘peak’ is uppermost.
15. Continue with installation and commissioning of the
boiler.
27
Page 28
9.0Plume Displacement
Plume Outlet
Fig. H
200mm Min.
500mm Min.
Elbow
9.3General Fitting Notes - P.D.K. (cont.)
16. For aesthetic purposes it is permissible to route the
70Ø exhaust in an enclosed box, but the air inlet and
plume outlet MUST remain in free air.
17. It is also possible to separate the plume outlet from
the 93° elbow to allow the flue to be installed as shown
in Fig. H.
18. When the plume outlet is positioned under a balcony
or other projection (Figs. I & J) it must protrude at least
200mm (it is not necessary to extend it further than this).
EXAMPLE: If the boiler is 2 metres
away from corner of wall the flue
Example
V = 55mm
Horizontal
Side Flue
Centre Line
duct hole will be 55mm higher than
the horizontal side flue centre line.
This will maintain an approx. 1.5°
backfall to the boiler. It is especially
important to consider this when
fitting the boiler under a work top !
Wall Thickness
up to 227mm
up to 750mm
up to 1200mm
Template
Backfall to the boiler, ie. 2m flue offset (V) position 55mm
2. For the boiler to operate correctly it must be level
in both planes. Place the fixing template in the
proposed boiler position ensuring that it is level.
3. Mark the centre of the flue hole (rear exit).
For side exit: project the horizontal side flue centre
line into the corner of the room and along the wall to
where the flue hole will be drilled. (Fig. 20).
The diagram (Fig. 21) shows the dimensions required
to ensure any horizontal flue is installed with the
correct fall to the boiler. Mark the offset (V) dimension
and if required, mark the position of the gas, water and
condensate pipes. Remove the template.
4. Cut the hole for the flue (minimum diameter
125mm, see table (Fig. 20) for wall thicknesses and flue
hole diameters).
5. Complete any pipework and wiring that will be
inaccessible once the boiler is in position.
1.5°
6. Undo the securing screws and remove the facia,
front door panel and top panel (see Figs. 1 & 2 on
page 6). Remove the securing screw and disengage the
pipe access panel.
10.2Making the Water Connections
1. If desired the flow and return tails supplied with the
boiler can be fitted at this stage and secured with the
spring clips. The flow and return connections are
identified on the boiler rear panel. The flow pipe
incorporates a manual air vent.
2. Note that the seal is made by use of an ‘O’ ring,
therefore some pipe movement will be evident even
though a water tight seal has been achieved. Excessive
force could result in damage to the connection.
3. Make all soldered joints before connecting the tails
to the boiler to avoid damaging the ‘O’ rings.
4. Refit the pipe access panel.
10.3Making the Gas Connection
1. The connection to the boiler is a 15mm tail on the
gas service cock. The tail protrudes through the boiler
rear panel and is protected by a transit bracket which
may be removed to aid connection (see Fig. 22).
2. If solder joints are being used for the gas connection,
remove the gas tap from the valve as excessive heat
may damage the ‘O’ ring seal.
10.4Priming the Condensate Trap
1. Using a funnel and tube, carefully pour
approximately 1 cupful (250ml) of tap water into the
flue products exhaust at the terminal or flue elbow
sampling point to ensure a seal is made in the trap.
29
Page 30
At least
1.5°
Wall Thickness
10.0 Installation
10.5Fitting the Standard Flue
IMPORTANT: The flue should always be installed
with at least 1.5° fall from terminal to elbow, to
allow condensate to run back to the boiler.
1. The standard flue is suitable for lengths 270mm
minimum to 800mm maximum (measured from the
edge of the flue elbow outlet).
Rear Flue: maximum wall thickness - 575mm
Side Flue: maximum wall thickness - 535mm
2. For rear exit - measure the wall thickness
(Fig. 26) and to this dimension add 270mm. This
dimension to be known as (X).
i.e. (X) = wall thickness + 270
3. Take the flue and mark off (X) from the terminal end
as indicated in the diagram (Fig. 27).
4. For side exit - measure the distance from the edge
of the boiler case to the inner face of the wall (Fig. 26)
and to this dimension add the wall thickness + 280mm.
This dimension to be known as (Z).
Fig. 26
Fig. 27
Waste
(Z) = Side Exit
(X) = Rear Exit
Flue
Edge of Boiler Case to Wall
Wall Thickness
i.e. (Z) = case to wall + wall thickness + 280
5. Take the flue and mark off (Z) from the terminal end
as indicated (Fig. 27).
Before cutting check your dimensions !
6. The flue tubes are fixed together. Cut through both
tubes whilst resting the flue on the semi-circular packing
pieces. Deburr both tube ends.
NOTE: When cutting ensure the cut does not
interfere with the inner flue support bracket
(Fig. 27a).
7. Ensure the inner flue support bracket is positioned
in the flue (Fig. 28).
8. Engage the flue into the flue elbow using soap
solution to ease the engagement, ensuring the flue
terminal is positioned as shown (Fig. 29).
9. Place the gasket over the flue exit on the boiler.
10. Slide the flue assembly through the hole in the wall.
11. Engage the elbow on to the flue connection on top
of the boiler. Secure with the four screws supplied in
the kit.
12. Make good between the wall and air duct outside
the building ensuring the 3° drop between the terminal
and elbow.
13. The flue trim should be fitted once the installation
is complete and the flue secure (Fig. 30). Apply a
suitable mastic to the inside of the trim and press
against the wall finish, making sure the brickwork is
dust free and dry.
Gasket
14. If necessary fit a flue plume deflector kit and/or
terminal guard (see Sections 7.6 & 8.8).
Note: The point of discharge from
the pumped length of condensate
pipe (point ‘A’) must not be below
the level of the pump, whether
discharging direct into a drain or
into an additional gravity drain.
10mm PVC Pipe
(8.5mm I.D.)
Securing Clip
10.0 Installation
10.6Making the Condensate Drain
Connection
1. 3.5 metres of flexible 10mm PVC pipe are supplied
with the boiler, ready connected to the pump. 0.5
metres of this length remains coiled within the boiler
to allow removal of the pump assembly. This must not
be uncoiled to provide extra length.
2. A fitting and securing clip (Fig. B) to accept the
10mm PVC pipe and connect to 21.5mm overflow
pipe is also supplied. When using this fitting to connect
to a 21.5mm overflow tee piece the branch must be
vertical ± 10° (Fig. C).
3. Feed the pipe through the grommet in the rear
panel and connect to the drain system.
Fig. B
Termination via internal discharge branch e.g
sink waste - downstream
Direct Connect Fitting
Sink
From Boiler
Fig. C
Termination to a drain or gully
From Boiler
Fig. E
Pipe must terminate
above water level but
below surrounding surface
From Boiler
8.5mm Ø O.D.
21.5mm Ø O.D. to fit
Overflow Pipe
Termination to an internal soil and vent pipe
Direct Connect Fitting
Min. 450mm
Fig. D
Pipe must terminate above
water level but below
surrounding surface
Termination to a purpose made
soak-away
From Boiler
Branch of Tee to be
± 10° from vertical
500mm Min
Holes in the soakaway must face away
from the building
4. The 10mm pipe can be routed to a maximum of 3
metres vertically and then discharge via gravity or be
routed horizontally (Fig. A). A combination of vertical
and horizontal runs is permissible.
5. The pipe must be supported, either using suitably
spaced clips or run within larger diameter pipe. When
using clips take care not to deform the pipe.
6. When routing the pipe through a wall it must be
suitably sleeved. Also the pipe must not be exposed to
sources of heat, and should be protected in locations
where it may be damaged.
7. The pipe should be routed so that any sharp bends,
dips and loops are avoided. A minimum radius of
100mm is recommended for any bends. No slope is
necessary and air breaks are not required on the
pumped part of the condensate run.
8. If the boiler is fitted in an unheated location the
entire length of condensate pipe should be treated as
external, and run within insulated larger diameter pipe.
9. Ensure that the condensate can discharge freely
(without blockage or restriction of the pipe) into the
drain.
10. Examples are shown of condensate pipe methods
of termination:-
i) via an internal discharge branch
(e.g. sink waste) - Fig. B.
ii) to an internal or external soil and vent
pipe - Fig. C.
iii) to a drain or gully - Fig. D. Ensure that
the condensate can discharge freely
(without blockage or restriction of the
pipe) into the drain.
IMPORTANT: Four core cable is required to supply the
boiler as a permanent live is necessary for the operation
of the condensate pump and frost protection.
1. The electrical connections are on the right hand side of the
boiler. Depending upon the nature of the installation it may
be preferable to wire up to the boiler first before
manoeuvering into position.
2. Undo the two screws securing the cable clamp and place
to one side (Fig. 31).
3. Route the incoming electrical cable(s) from the system
control wiring centre through the grommet in rear of the
boiler and the grommet in the support bracket. This will
prevent damage to the cable(s).
4. Lay the cable through the cable clamp to gauge the length
of wire required when it is connected to the 4-way terminal
block.
Cable Clamp
4-way Terminal Block
S/LN
Fig. 31
P/L
5. Connect the (S/L), ( ), (N) and (P/L) wires to the
4-way terminal block (Fig. 33) and refit the cable clamp
(Fig. 31).
INTEGRAL PROGRAMMER
If the optional integral programmer is being fitted it can be
done at this stage. Consult the instructions supplied in the
programmer kit.
Check the electrical installation for;
earth continuity, short circuits, resistance to earth, correct
polarity and fuse rating.
bk - Black
br - Brown
r- Red
w- White
g/y - Green/Yellow
g- Green
gy - Grey
op - Opaque
y- Yellow
35
Page 36
INOUT
Flue Sampling Point
12.0Commissioning the Boiler
12.1Commissioning the Boiler
WARNING: The PCB Control and Fan Assembly
are 325 Vdc. Isolate at supply before access.
1. Reference should be made to BS:EN 12828 & 14336 when
commissioning the boiler.
DO NOT check gas pressure here
Inlet Gas Pressure Test Point
Low
High
Central Heating
Control Knob
(No OFF Position)
Manual Air Vent
Gas Service
Cock
Fig. 35
Open
Fig. 36
Turn the Central Heating Control Knob clockwise
to increase or anticlockwise to decrease the
boiler flow temperature.
Fig. 34
2. At the time of commissioning, complete all relevant sections
of the Benchmark Checklist at the rear of this publications.
3. Flush the whole system using a suitable flushing agent (see
Section 6.2) and vent the radiators. Check for water leaks.
4. Refill the system with inhibitor following the inhibitor
manufacturer’s instructions and BS 7593 Code of Practice for
Treatment of Water in Domestic Hot Water Central Heating
Systems (see Section 6.2).
5. Complete the label supplied with the inhibitor and attach to
the inside of the boiler case. Detail of system treatment should
be added for future reference.
6. Turn the gas supply on and purge according to in GB BS 6891
and in IE I.S. 813 “Domestic Gas Installations”.
7. Turn the gas service cock anticlockwise to the ON position
and check for gas tightness up to the gas valve (Fig. 34). Turn the
power to the boiler ON.
IMPORTANT: The combustion for this appliance has been
checked, adjusted and preset at the factory for operation on
the gas type specified on the appliance data plate. No
measurement of the combustion is necessary. Do not adjust
the air/gas ratio valve.
8. Having checked:
•That the boiler has been installed in accordance with
these instructions.
•The integrity of the flue system and the flue seals.
•The integrity of the boiler combustion circuit and the
relevant seals.
Proceed to put the boiler into operation as follows:
The Reset Button should extinguish the
Flame Failure Light and restore normal
operation.
This indicates that there is electricity to the Boiler.
This indicates that the Burner has fired up
and is heating your system.
If Flame Failure Light is ON. Press the Reset
Button. If Flame Failure occurs persistently
consult your Installer or Service Engineer.
This indicates that the Condensate Pump is running.
The pump ONLY runs when the condensate reservoir is full.
Fig. 36a
12.2Priming the Condensate Pump
1. Using a funnel and tube, carefully pour approximately 1litre of
tap water into the flue products exhaust at the terminal or flue
elbow sampling point to fill the trap and allow the condensate
pump reservoir to fill.
2. Continue filling with water until the condensate pump
operates.
3. Check that the condensate drain pipework is not leaking and
that it is discharging correctly to drain.
4. See Fig. 36a for operation of LEDs on boiler facia.
Page 37
INOUT
DO NOT check gas pressure here
12.0 Commissioning the Boiler
12.3Check the Operational (Working) Gas
Inlet Pressure
1. Ensure that all controls are calling for heat and
maximum load is applied to the system.
2. With the boiler operating in the maximum rate
condition check that the operational (working) gas
pressure at the inlet gas pressure test point is in
accordance with B.S. 6798 & B.S. 6891.
3. Ensure that this inlet pressure can be obtained with
all other gas appliances in the property working.
Measure the Gas Rate
4. With any other appliances & pilot lights turned OFF
the gas rate can be measured. It should be as shown in
Section 4.0 Technical Data.
5. Carefully read and complete all sections of the
Benchmark Commissioning Checklist at the rear of this
publication that are relevant to the boiler and
installation. These details will be required in the event of
any warranty work. The publication must be handed to
the user for safe keeping and each subsequent regular
service visit recorded.
Inlet Gas Pressure Test Point
Fig. 36b
6. For IE, it is necessary to complete a “Declaration of
Conformity” to indicate compliance with I.S. 813. An
example of this is given in I.S. 813 “Domestic Gas
Installations”. This is in addition to the Benchmark
Commissioning Checklist.
1. Refit the case top panel and front door, securing with
the screws previously removed (Fig.37).
2. Locate the facia panel and secure with the screws
previously removed (Fig. 38).
3. The “Important Ventilation Information” label can be
removed unless the boiler is installed in an unventilated
compartment.
13.2‘Benchmark’ Checklist
1. Carefully read and complete all sections of the
Benchmark Commissioning Checklist at the rear of this
publication that are relevant to the boiler and
installation. These details will be required in the eventof any warranty work. The publication must be handed
to the user for safe keeping and each subsequent
regular service visit recorded.
Facia Securing Screws
2. For IE, it is necessary to complete a “Declaration of
Conformity” to indicate compliance to I.S. 813. An
example of this is given in I.S. 813 “Domestic Gas
Installations”. This is in addition to the Benchmark
Commissioning Checklist.
Fig. 37
13.3Handover
1. Instruct the user in the operation of the boiler and
system controls. Hand over the User’s Operating,
Installation and Servicing Instructions, giving advice on
the necessity of regular servicing.
2. Demonstrate to the user the action required if a gas
leak occurs or is suspected. Show them how to turn off
the gas supply at the meter control, and advise them
not to operate electric light or power switches, and to
ventilate the property.
3. Show the user the location of the system control
isolation switch, and demonstrate its operation.
4. Advise the user that they may observe a plume of
vapour from the flue terminal, and that it is part of the
normal efficient operation of the boiler.
WARNING: The PCB Control and Fan
Assembly are 325 Vdc. Isolate system controls
before access.
IMPORTANT: When servicing ensure that both the gas and
electrical supplies, including Switched and Permanent Live to the
boiler are isolated before any work is started.
The four LEDs on the facia will all be OFF.
It is important to isolate the electrical supply at the system
isolation switch as it is not possible to do this on the boiler itself.
Hazardous materials are not used in the construction of this
product, however reasonable care during service is
recommended - see Section 1.2.
When replacing the combustion box door after servicing it is
essential that the retaining screws are tightened fully.
1. For reasons of safety and economy, it is recommended that
the boiler is serviced annually. Servicing must be performed by a
competent person in accordance with B.S. 7967-4.
2. After servicing, complete the relevant Service Interval Record
section of the Benchmark Commissioning Checklist at the rear of
this publication.
IMPORTANT:During routine servicing, and after any
maintenance or change of part of the combustion circuit, the
following must be checked:-
•The integrity of the complete flue system and the flue seals.
•The integrity of the boiler combustion circuit and relevant
seals as described in Section 14.2.
•The operational gas inlet pressure as described in Section
12.2.1 to 12.2.3 and the gas rate as described in 12.2.4.
•The combustion performance as described in ‘Check the
Combustion Performance’ (14.1.4 to 14.1.6 below).
3. Competence to carry out Checking Combustion
Performance
B.S. 6798 ‘Specification for Installation & Maintenance of Gas
Fired Boilers not exceeding 70kW’ advises that:-
• The person carrying out a combustion measurement should
have been assessed as competent in the use of a flue gas
analyser and the interpretation of the results.
• The flue gas analyser used should be one meeting the
requirements of BS7927 or BS-EN50379-3 and be calibrated
in accordance with the analyser manufacturers’ requirements.
• Competence can be demonstrated by satisfactory
completion of the CPA1 ACS assessment, which covers the
use of electronic portable combustion gas analysers in
accordance with BS 7967, Parts 1 to 4.
2
Check the Combustion Performance (CO/CO
ratio)
4. Set the boiler to operate at maximum rate as described in
Section 12.2.
5. Remove the cap from the flue sampling point, insert the
2
analyser probe and obtain the CO/CO
ratio. This must be
less than 0.004.
2
6. If the combustion reading (CO/CO
ratio) is greater than
this, and the integrity of the complete flue system and
combustion circuit seals has been verified, and the inlet gas
pressure and gas rate are satisfactory either:
•Perform the ‘Annual Servicing - Inspection’ (Section 14.2) &
7. To clean the heat exchanger and burner proceed as
follows:
a) Disconnect the electrical leads to the fan component
protection sensor (Fig. 42).
Injector Pipe
Injector Pipe Retaining
Screw
Protection
Sensor Leads
Fig. 42
Wing Nuts
Central Insulation Panel
Fig. 41a
Electrical Supply
Trap to Condensate
Pump Inlet Pipe
Fan
Sensor
Leads
Condensate
Lock Nut
Fig. 43
Securing Nut
Trap
Service Drain
Plug
b) Loosen the screw retaining the gas injector pipe at
the venturi (Fig. 42).
c) Undo the two wing nuts to disconnect the fan
(Fig. 42).
d) Remove the fan and disconnect the electrical supply
to it (Fig. 42).
e) Remove the gas injector pipe from the gas valve
(push-fit) (Fig. 42).
f) Remove the condensate trap drain plug and place a
vessel underneath to catch the condensate (care should
be taken as this could be hot). The condensate drain
pipe may be removed to increase access.
g) Undo the condensate trap securing nut, lock nut and
the condensate drain pipe. Remove the condensate trap
and disconnect the sensor leads (Fig. 43). Clean the trap
and refit the drain plug.
h) Remove the two screws securing the burner and
remove the burner. Visually inspect the internal burner
baffle for obstruction, check seal around baffle for
cracks/damage. Clean with a soft brush.
i) Loosen the two screws retaining the heat exchanger
support bracket and slide to the left to remove
(Fig. 44).
j) Remove the four screws securing the heat
exchanger/combustion box base and withdraw the
base.
k) Lower the central insulation panel and check
condition (Fig. 44). Replace the lower insulation pad if
necessary.
l) Ensure the heat exchanger fins are clear of any
obstruction.
m) Check condition of all seals. Important: Pay
particular attention to the condition of the
combustion box door seals.
n) Reassemble in reverse order and check for leaks.
8. Check the operation of the condensate pump and
drain pipework (see Section 10.1)
2
9. Check CO/CO
ratio at flue sampling point (Fig.41a).
See section 4.0.
10. Complete the relevant Service Interval Record
section of the Benchmark Commissioning Checklist at
the rear of this publication and then hand it back to the
user.
41
Page 42
15.0Changing Components
15.1Changing Components & Preparation
WARNING: The PCB Control and Fan
Assembly are 325 Vdc. Isolate system
controls before access.
IMPORTANT: Ensure that both the gas and electrical
supplies, including Switched and Permanent Live to the
boiler are isolated before any work is started.
The four facia LEDs will be all OFF.
It is important to isolate the electrical supply at the
system isolation switch as it is not possible to do this
on the boiler itself.
Hazardous materials are not used in the construction of
this product, however reasonable care is recommended
- see Section 1.2.
When replacing the combustion box door it is essential
that the retaining screws are tightened fully.
Remove the facia and front door panel.
Safety
Thermostat
(Black)
Fig. 45
Heat Exchanger
Manifold
Drain Point
Electrical Connections
Flow Temperature Thermistor (Red)
Tube
Pipe Access
Panel
For the replacement of some components it will be
necessary to drain the boiler. Proceed as follows:-
1. Isolate the water circuit and drain the system as
necessary. A drain point is located on the heat
exchanger manifold at the right hand side of the boiler
(Fig. 45) to enable the heat exchanger to be drained.
2. Place a tube on the drain point to drain water away
from the electrics. Turn anticlockwise to open (Fig. 45).
3. After changing a component recommission the boiler
where appropriate and check the inhibitor
concentration (see Section 6.2 and 10.1).
The thermistor, safety thermostat, interface PCB and
the flow switch can be accessed after removal of the
pipe access panel (Fig. 46).
15.2Flow Temperature Thermistor and
Safety Thermostat
(Fig. 46)
1. The procedure is the same for both the thermistor
and the safety thermostat.
2. Remove the pipe access panel and disconnect the
electrical connections from the sensor.
4. Fit the new thermistor or safety thermostat and
reassemble in reverse order.
Page 43
Support Bracket
Pipe Access
Panel
15.0Changing Components
15.3Flowswitch (Fig. 47)
1. Drain the boiler (see Section 13.1 paragraph 2 & 3).
2. Remove the pipe access panel and remove the securing
clip from the ‘O’ ring joint between the flow pipe and the
system. Undo screws on support bracket.
3. Remove the securing clip from the ‘O’ ring joint
between the flow pipe and the flowswitch.
4. Remove the two screws securing the flow switch to the
boiler.
5. Disconnect the inline electrical connection and remove
the flowswitch.
Flow Switch
Over Level Switch
Clip
Flow Pipe
Fig. 47
6. Fit the new flowswitch and reassemble in reverse order.
7. Recommission the boiler and check the inhibitor
concentration (see Section 6.2 and 10.1).
15.4Condensate Pump - Complete (Fig. 47a)
1. Remove the pipe from the trap to the pump inlet and
disconnect the electrical plug.
2. Lift the pump off the support studs and ease it
forwards. Release the snap fit clip and disconnect the
condensate outlet pipe.
3. Connect the condensate outlet pipe to the new pump
using the new clip provided.
4. With the new pump in place on the studs, refit the trap
discharge pipe, ensuring the ‘O’ ring is in place. Reconnect
the electrical plug.
5. Neatly coil the excess condensate outlet pipe adjacent
to the pump, ensuring that it is not kinked or restricted.
6. Check operation of the pump - See Section 10.2.
1. Remove the complete Condensate Pump as described
in Section 13.4, and remove the cover.
2. Disconnect the wires from the switch(es) and remove
the retaining screws. On the Level Switch remove the
circlip and washers connecting the plunger to the
actuating arm.
3. Fit the new switch(es). Align the actuating arm of the
Level Switch with the plunger, ensuring that there is a
washer at each side of the arm.
4. Reconnect the wires. On the Over Level Switch there
is no connection to the lower spade terminal.
5. Check operation of the pump - See Section 10.2.
43
Page 44
Control
Knob
Fig. 48
Plastic Button
Cover
PCB Housing Securing
Screw
15.0Changing Components
15.6PCB (Figs. 48 & 49)
WARNING: The PCB Control and Fan
Assembly are 325 Vdc. Isolate system
controls before access.
1. Pull the control knob off the spindle and remove the
plastic button cover. Refit them onto the new PCB
(Fig. 48).
2. Remove the top right hand securing screw and swing
out the PCB housing. Remove the PCB cover and
disconnect the electrical plugs noting their positions
3. Remove the screw securing the PCB to the housing.
The PCB can be removed from the housing.
4. Ensure that the two jumpers are fitted to the new
PCB as shown (Fig. 49).
5. Reconnect the plugs, fit the new PCB to the housing
and reassemble in reverse order.
The fan and venturi, gas valve, injector pipe,
condensate trap, fan protection sensor, spark and
sensing electrodes can be accessed and changed on
the removal of the airbox door panel.
1. Remove the airbox door panel by loosening the four
1
/4turn screws (Fig. 50).
15.7Spark and Sensing Electrodes
(Fig. 51)
1. Disconnect all three leads from tabs.
Spark-Opaque cable
Earth-Green/Yellow cable
Sensing-White cable
2. Remove the two screws securing each of the
electrodes to the combustion box door and remove the
electrodes.
3. Fit the new electrodes (and new gasket, as required)
and reassemble in reverse order.
Spark
Earth
Injector Pipe
Screw
Sensing
Fig. 51
Combustion
Box Door
Injector
Opening
Gasket
Fig. 50
15.8Fan (Fig. 52)
WARNING: The PCB Control and Fan
Assembly are 325 Vdc. Isolate system
controls before access.
1. Loosen the screw holding the injector pipe into the
venturi.
2. Remove the electrical connections to the fan and
protection sensor on the fan.
3. Remove the wing nuts securing the fan to the base of
the combustion box.
4. Lower the fan and remove.
5. If changing the fan, remove the screws securing the
venturi and fan protection sensor bracket, noting the
positions of the injector opening and sensor bracket, fix
them to the new fan.
6. Fit the new fan and reassemble in reverse order.
Fan
The injector pipe, condensate trap and gas valve can
be changed after the removal of
the fan.
The removal of the fan is necessary to enable the changing of
the injector pipe, condensate trap and gas valve (see section
13.6).
15.9Injector Pipe (Fig. 53)
1. Remove the injector pipe by pulling out from the ‘O’ ring
joint in the gas valve.
2. Fit the new injector pipe and reassemble in reverse order.
Injector Pipe
Boiler Side
Fig. 53
Gas Valve
Securing Screws
Aluminium
Spacer
Case Pressure Pipe
Gasket
‘O ring’
Electrical Plug
Gas Valve
Gas Tap
15.10Gas Valve (Fig. 53)
IMPORTANT: After replacing the valve the CO2must be
checked as detailed in Section 14.1.4 to 14.1.6. Only
change the valve if a suitable calibrated combustion
analyser is available, operated by a competent person see Section 14.1.3.
1. Isolate gas supply and disconnect the gas tap by removing
the four screws.
2. If required remove the condensate pump to increase access
(see Section 13.4) and undo the case pressure pipe from the
valve.
3. Disconnect the electrical plug from the gas valve.
4. Remove the fan (see Section 13.6) and injector pipe.
5. Remove the two gas valve securing screws from inside the
air box holding the gas valve, and remove the valve.
6. Remove the aluminium spacer and its gasket from the gas
valve.
7. Fit the aluminium spacer and its gasket to the new valve.
8. Fit the new gas valve and reassemble in reverse order.
NOTE: Check for gas tightness after replacing gas valve.
9. Check the CO
2
level. If the level is greater than that quoted,
telephone the Technical Enquiries for further advice.
15.11Condensate Trap (Fig. 54)
1. Disconnect the condensate trap from the base of the heat
exchanger.
2. Disconnect the condensate drain ‘O’ ring connection from
the condensate trap and condensate pump. For ease of access
also remove the pump.
3. Undo the condensate trap lock nut.
4. Remove the condensate trap from the boiler.
5. Disconnect the sensor leads.
6. Fit the new condensate trap and reassemble in reverse
order. When refitting the pipe from the trap to the pump
ensure that all seals and connections are made.
7. Prime the condensate trap (fill first chamber), check for leaks
(see Section 8.5).
Page 47
15.0Changing Components
Combustion Box
Door Panel
Burner
Fig. 55
Support
Bracket
Return
Connection
Fig. 57
The burner and heat exchanger can be changed after
removal of the combustion box door. To change the
heat exchanger, the fan and burner must be removed
first (see section 13.6 and 13.10).
1. Remove the combustion box door by removing the
four securing screws (Fig. 55).
IMPORTANT: On refitting the combustion box
door check the condition of the combustion box
door seals.
15.12Burner (Fig. 56)
1. Remove the two screws securing the burner to the
base of the combustion box.
2. Remove the burner carefully from the combustion
box base.
3. Check the burner seal on the heat exchanger base,
replace if necessary. Fit the new burner and reassemble
in reverse order.
Fig. 56
Securing Screws
Fig. 58
Heat Exchanger
Manifold
Flow
Switch
15.13Heat Exchanger
1. Drain the boiler (see section 13.1 paragraph 2 & 3).
2. Remove all components in the base of the airbox.
3. Undo the screws on the support bracket. Remove
the screws securing the flow switch and return
connections and remove the connections (Fig. 57).
4. Remove the screws securing the heat exchanger
manifold and remove the manifold (Fig. 58).
5. Ease the combustion box left hand side panel to clear
the stud, lift the heat exchanger assembly (Fig. 59) and
rotate the bottom upwards whilst pulling it forwards
out of the airbox.
6. Ensure that the heat exchanger is disengaged from
the flue elbow and clear of the stud in the left hand side
of the combustion box.
7. Fit the new heat exchanger and reassemble in reverse
Failure to install and commission according to the manufacturer’s instructions and complete this Benchmark Commissioning Checklist will invalidate the warranty. This
does not affect the customer’s statutory rights.
If yes, and if required by the manufacturer, has a water scale reducer been fitted?
CONDENSING BOILERS ONLY
The condensate drain has been installed in accordance with the manufacturer’s instructions and/or BS5546/BS6798 Yes
If the condensate pipe terminates externally has the pipe diameter been increased and weatherproof insulation fitted? Yes
58
Page 59
Service Record
Date:
Engineer Name:
Company Name:
Telephone No.
Gas Safe Register No.
Comments:
Signature:
Date:
Engineer Name:
Company Name:
Telephone No.
Gas Safe Register No.
Comments:
Signature:
It is recommended that your heating system is serviced regularly and that the appropriate Service Interval Record is completed.
Service Provider
Before completing the appropriate Service Record below, please ensure you have carried out the service as described in the
manufacturer’s instructions.
Always use the manufacturer’s specified spare part when replacing controls.
Service 1Service 2
Date:
Engineer Name:
Company Name:
Telephone No.
Gas Safe Register No.
Comments:
Date:
Engineer Name:
Company Name:
Telephone No.
Gas Safe Register No.
Comments:
Signature:
Service 3Service 4
Date:
Engineer Name:
Company Name:
Telephone No.
Gas Safe Register No.
Comments:
Signature:
Service 5Service 6
Date:
Engineer Name:
Company Name:
Telephone No.
Gas Safe Register No.
Comments:
Signature:
Signature:
Date:
Engineer Name:
Company Name:
Telephone No.
Operative ID No.
Comments:
Signature:
Service 7Service 8
Date:
Engineer Name:
Company Name:
Telephone No.
Gas Safe Register No.
Comments:
Signature:
Service 9Service 10
Date:
Engineer Name:
Company Name:
Telephone No.
Gas Safe Register No.
Comments:
Signature:
Date:
Engineer Name:
Company Name:
Telephone No.
Gas Safe Register No.
Comments:
Signature:
59
Page 60
All descriptions and illustrations provided in this leaflet have been carefully
prepared but we reserve the right to make changes and improvements in
our products which may affect the accuracy of the information contained in
this leaflet. All goods are sold subject to our standard Conditions of Sale
which are available on request.
POTTERTON
A Trading Division of Baxi Heating UK Ltd (3879156)