TH-VA-2X2-NEC X463
This display kit mounts the NEC X463UN
LCD monitor in a 2 wide by 2 deep landscape
configuration. The frame attaches to a wall and
receives the LCD monitors by way of four machined
fittings (per monitor) that thread into the monitor’s
VESA holes. These fittings then insert into the frame’s
channels. The monitor’s fittings secure to the frame
with locking arms that provide an easy way to remove
the monitors for service. A removable panel provides
access for media players behind the frame.
Important: Installing video displays is a serious
endeavor that requires experienced professionals.
Improperly prepared walls and other structures as
well as the equipment being installed can result in
property damage, injury and/or liability to the
installing contractor. Do not proceed if any part of
the installation is in doubt.
Installation Instructions
Video Wall 2x2
Caution: Due to the wide variety of structures,
environments, materials and installation methods, the
installing contractor must exercise good judgment in
selecting the proper mounting area. The mounting
structure must be capable of supporting at least 5
times the load of the installed equipment. Consult local
building codes for further guidance.
Follow these instructions for the most efficient and
safest mounting results.
Package Contents:
1 pc Frame w/ locking arms assembled
2 pcs Media player mounting bracket
1 pc Adjustment wrench
16 pcs M6 Threaded stand-off button (black)
9 pcs Wood Screw Hanger (Adjustable Lag bolts)
9 pcs Flat washer, 5/16
9 pcs Hex nuts, 5/16-18
1 pc Instruction sheet
Notes:
Hardware to mount frame to the wall are included.
Note:
The assembled frame weighs approximately 65 lb/29.5 Kg and requires just one installer. Two installers recommended for installing the
LCD monitors.
2 Wide x 2 Deep Video Wall Display (Rear View)
Rev.02-06/25/12

Step 1: Mount Frame to Wall
Scribe a horizontal line on the
wall showing the exact location
of the top edge of the upper left
LCD monitor will be. Measure
down 8.8” (223.5mm) from that
line and scribe another
horizontal line showing where
the first location of the
adjustable lag bolts for the
mounting frame will be. This is
for the top left keyhole slot
(Figure 1).
Scribe a vertical line showing
where the left side of the upper
LCD monitor will be. Measure to
the right and scribe another
vertical line 12.6” (320mm) to
locate the location of the first
adjustable lag bolts for the
mounting frame will be. This is for the top right keyhole slot
(Figure 1).
nd
Mark where the 2
horizontal line vertical lines meets.
Measure 55.7” (1414.8mm) to the right for next location of the
adjustable lag bolt. Use a level then mark the second location,
use level to make sure it Is horizontally level to the first hole
on the left side. Pre-drill the marked locations using a 3/16”
(5mm) drill (Figure 1).
Install the adjustable lag bolts to the pre-drilled holes then
hang the frame onto the two adjustable studs. Install the flat
washer and hex nut to secure frame to wall. Hand tighten hex
nut only (Figure 2).
Figure 1
Figure 3
Figure 2
Step 3:
Mark the location for the other adjustable lag
bolts, one upper center keyhole, three bottom
keyholes slots and three center middle holes
(Figure 3).
Step 4:
Remove the two nuts and washer securing the
frame to the wall and place the frame back on
the floor. Pre-drill all the marked locations
using 3/16” drill bit then install the adjustable
lag bolts (Figure 3 and 4).
Step 5:
Rev.02-06/25/12