Procédure de remplacement de la vanne de coupure Modulair 112
Modulair 112 shut-off valve replacement procedure
Page 3
Page 6
DE
IT
ES
NL
Austausch des Stoppventils Modulair 112
Page 9
Procedura di sostituzione della valvola di chiusura Modulair 112
Page 12
Procedimiento de sustitución de la válvula de corte Modular 112
Page 15
Page 18
(383 46 32)
MS-P710-11
765
10 9
8
4
321a
12
8
4
3
765
9
21a
10 12a
Modulair 112 shut-off valve replacement procedure
Modulair 112 shut-off valve replacement procedure
IDENTIFYING YOUR EQUIPMENT
Shut-off valve
machined body version
For disassembly, see Figure A For reassembly, see Figure B
Shut-off valve
moulded body version
For disassambly and reassembly, see Figure B
SHUT-OFF VALVE ONLY
DISASSEMBLY OF MACHINED
A B
BODY VERSION
8
4
321
5 6
Machined body with plain surface
4
Shut-off valve + soft-start valve
machined body version
For disassembly, see Figure C For reassembly, see Figure D
DISASSEMBLY/REASSEMBLY OF MOULDED BODY VERSION
Part 4 is to be returned to us
1
7
8
4
32
Moulded body with plastic cover
Part to be replaced: shut-off valve (4)
Parts (1, 3, 5 and 7) Replacement kit code: 343 03 075:
- 1 wide ring
- 1 narrow ring
- 2 seals (3 and 5)
- 4 short screws (1)
- 4 long screws
- 4 nuts (7)
Shut-off valve + soft-start valve
moulded body version
For disassambly and reassembly, see Figure E
7
5 6
+
SHUT-OFF VALVE + SOFT START VALVE
DISASSEMBLY OF MACHINED
C
BODY VERSION
Part 4 is to be returned to us
REASSEMBLY OF MOULDED AND MACHINED
D
BODY VERSIONS
DISASSEMBLY/REASSEMBLY OF MOULDED
E
BODY VERSION
8
4
321
Moulded body with plastic cover
Part 4 is to be
returned to us
Moulded body with plastic cover
9
10
Narrow ring (4.5 mm)
Wide ring (8 mm)
65
Machined body with plain surface
Moulded body with plastic cover
7
Parts to be replaced: shut-off valve (4) and seal (5) supplied with the valve
Parts (1a, 3, 10, 12 and 7) Replacement kit code: 343 03 075
- 1 wide ring
- 1 narrow ring (12)
- 2 seals (3 and 10)
- 4 short screws
- 4 long screws (1a)
- 4 nuts (7)
Parts to be replaced: shut-off valve (4) and seal (5) supplied with the valve
Parts (1a, 3, 10, 12a and 7) Replacement kit code: 343 03 075
- 1 wide ring (12a)
- 1 narrow ring
- 2 seals (3) and (10)
- 4 short screws
- 4 long screws (1a)
- 4 nuts (7)
+
+
5
4
32
8
5 6
7
1
Modulair 112 shut-off valve replacement procedure
FR
Procédure de remplacement de la vanne de coupure Modulair 112
DISASSEMBLY AND REASSEMBLY
SHUT-OFF VALVE ONLY
- Cut off the electrical and pneumatic power supplies, then vent the pneumatic system of the machine.
- Detach the solenoid valve (8) by undoing the two screws.
- Unscrew the silencer or the venting connection.
- Undo the four M5 nuts (7) and the four screws (1).
- Remove the shut-off valve (4) the seals (3 and 5) from the upstream (2) and downstream (6) flanges.
- Remove and discard the seals (3 and 5), the short screws (1) and the nuts (7).
- Clean the seal seatings.
- Take the seals (3 and 5), the four short screws (1) and the nuts (7) from the replacement kit.
- Lubricate the seals with Parker-O-Lube.
- Position the new shut-off valve (4) with the arrows correctly orientated.
- Position the upstream flange (T-groove downwards) with its seal (3) on the shut-off valve (4).
- Position the downstream flange (6) (T-groove downwards) with its seal (5) on the shut-off valve (4).
- Insert the four screws (1) through the components and fit the four M5 nuts (7) (screwing torque 2.5 Nm).
- Reinstall the solenoid pilot valve (8), be sure to orient it correctly (polarised).
- Screw the silencer or the venting connection back on.
- Carry out a functional test (pneumatic and electrical) of the shut-off valve.
SHUT-OFF VALVE + SOFT START VALVE
- Cut off the electrical and pneumatic power supplies, then vent the pneumatic system of the machine.
- Detach the solenoid valve (8) by undoing the two screws.
- Unscrew the silencer or the venting connection.
- Undo the four M5 nuts (7) and the four screws (1a).
- Remove the shut-off valve (4) from the upstream (2) and downstream (6) flanges and from the soft-start valve (9), and possibly the retaining ring (12) or (12a) for the seal (10).
- Remove and discard all the seals as well as the long screws (1a), the nuts (7) and, possibly, the ring (12) or (12a).
- Clean the seal seatings.
-
Take the seals (3) and (10), the long screws (1a), the nuts (7) and the corresponding ring (12) or (12a) from the replacement kit.
- Lubricate the seals (3, 5 and 10) with Parker-O-Lube.
- Position the new shut-off valve (4) on the soft-start valve (9), positioning the seal (10) and the retaining ring (12 or 12a) for the seal.
- Position the upstream flange (2) (T-groove downwards) with its seal (3) on the shut-off valve (4).
- Positioning the downstream flange (6) (T-groove downwards) with its seal (5) on the shut-off valve (9).
- Insert the four screws (1a) through the components and fit the four M5 nuts (7) (screwing torque 2.5 Nm).
- Reinstall the solenoid pilot valve (8), be sure to orient it correctly (polarised).
- Screw the silencer or the venting connection back on.
- Carry out a functional test (pneumatic and electrical) of the shut-off valve.
SHUT-OFF VALVE ON FRL LINE OR INSTALLATION WITH ASSEMBLY KIT
- Cut off the electrical and pneumatic power supplies, then vent the pneumatic system of the machine.
- Undo the socket head screws (A) of the upstream and/or downstream connecting pieces (B) to detach the valve from the FRL system, be sure to retain the O-rings (do not discard) , and proceed with replacement as indicated above.
IDENTIFICATION DE VOTRE MATERIEL
Vanne de coupure
modèle corps usiné
Démontage voir figure A Remontage voir figure B
Vanne de coupure
modèle corps moulé
Démontage et remontage voir figure B
VANNE DE COUPURE SEULE
DEMONTAGE MODELE CORPS USINE
A B
La pièce 4 est
à nous retourner
8
4
321
Vanne de coupure + démarreur
modèle corps usiné
Démontage voir figure C Remontage voir figure D
Vanne de coupure + démarreur
modèle corps moulé
Démontage et remontage voir figure E
DEMONTAGE/REMONTAGE MODELE CORPS MOULE
5 6
Corps usiné avec face lisse
A
B
A
B
ASCO JOUCOMATIC SA, After-sales service, 53 rue de Beauce, B.P. 17, 28111 Luce Cedex, France
6
FOR REPLACEMENT FREE OF CHARGE, THE SHUT-OFF VALVE (4)
MUST BE RETURNED TO US AT THE FOLLOWING ADDRESS:
7
Corps moulé avec cache plastique
Pièce à changer vanne de coupure (4)
+
Pièces (1, 3, 5, 7) Sachet de rechange code: 343 03 075
- 1 bague large
- 1 bague étroite
- 2 joints (3) et (5)
- 4 vis courtes (1)
- 4 vis longues
- 4 écrous (7)