FIGURE 2 - PlexPower Fiber Patch Panel With Gland Plate and Heater*
*NOTE: These figures are representative of all panels.
Appleton • 1.800.621.1506 • www.appletonelec.com
DOOR HIDDEN
504543-000 Rev. C 1/3/2020 • Page 2 of 19
Owner’s Responsibility:
• All installation instructions need to be followed.
• Users need to follow latest edition of the National Electrical Code® or the Canadian Electrical Code for installation guidelines.
• Inspect the panelboard thoroughly before operating.
• Understand how to operate all standard and accessory equipment.
• Ensure that anyone operating or maintaining the panelboard is qualied.
• Retain these instructions for reference during future inspections and maintenance.
Lifting & Moving Panel by Using an Eye Bolt
To lift the the panelboard, use M10 Eye Bolt and x it into both top mounting foot of panelboard enclosure and fasten it with nut. Lift panelboard
vertically with the help of a crane, wire rope, chain, sling belt etc. to enable movement/transfer of panel to mounting location.
FIGURE 3 - PlexPower Fiber Panelboard
Appleton • 1.800.621.1506 • www.appletonelec.com
504543-000 Rev. C 1/3/2020 • Page 3 of 19
Lifting & Moving Panel by Using Forklift Truck
1.
To transfer panel from one location to another by use of fork lift some additional
care to be taken.
2.Keep Panel board vertical on a stand/pallet etc. from which we can lift panel boardto transfer to desired location. Transferof panel with forklift without using anypallet or stand could damage Gland plateprovided on bottom side.
3.Ensure thatpanel board mounting location side is at front face of forklift truck.
4.For additional safety during transfer using forklift, it is necessary to securepanel
board to forklift truck with belt/wire rope/chain.
5.Ensure that operators will not get damaged during transfer.
Anchor Belt forAdditional Safety
Mounting Foot
Pallet to avoid any
damage to panel
board gland plate
Note:
In-case ofPlexPower Fiber Patch with
Roxtec cable Management System PanelTransfermake sure there is nodamageto RoxtecCable System andframe.
Follow the instructions/procedure below to transfer the panel from one location to another by using forklift.
• Keep the panelboard vertical on a stand/pallet from which we can lift it and transfer to desired location. Transfer of panel with
• Ensure that Panelboard mounting location is at front of forklift truck.
• For additional safety during transfer, it is necessary to secure Panelboard to forklift truck with belt/wire rope/chain.
• Actuation components should not get damaged during transfer.
forklift without using any pallet or stand could damage Gland plate provided on panel bottom.
Note: If you purchased a PlexPower Fiber Patch
with Roxtec Cable Management System, make
sure there is no damage to the Roxtec Cable
Management System during transit.
FIGURE 4
Appleton • 1.800.621.1506 • www.appletonelec.com
504543-000 Rev. C 1/3/2020• Page 4 of 19
Mounting:
3.4 Mounting:
1.Ensure mounting studs /bolts are in place on mounting frame, mounting strut,wall etc. according to dimensions specified on drawings included in Installationsection.
2.The panel board enclosure is intended to be mounted vertically. Use mountingfoot U-Slot for positioning and fasteningpanelboard.
3.Since upper mounting locations are tied with panel lifting accessories, usebottom mounting locations first for securing panelboard.
4.Once the bottom mounting locations are securely fastened then release liftingaccessories and fasten upper mounting locations with wall or frame etc.
5.All mounting locations must be secured properly to avoid any damage.
6.If you find mounting foot damaged, then consult factory.
Mounting Foot
U-Slot
PlexPower Fiber Patch Panel
• Ensure mounting studs/bolts are in place on mounting frame, mounting strut, wall etc.
• The panelboard is intended to be mounted vertically. Use mounting feet U-Slot for positioning and fastening panelboard.
• Since upper mounting locations are tied with panel lifting accessories, use bottom mounting feet rst for securing panelboard
• Once the bottom mounting locations are fastened, release lifting accessories and fasten upper mounting locations with
• All mounting locations must be secured properly to avoid any damage.
• If you nd any damaged mounting feet, consult tech support.
using M10 Bolt.
wall or frame.
FIGURE 5 - PlexPower Fiber Panelboard
Appleton • 1.800.621.1506 • www.appletonelec.com
504543-000 Rev. C 1/3/2020 • Page 5 of 19
Mounting Procedure:
• After both bottom and middle mounting feet are xed, remove the eye bolt from top mounting foot and x it with M10 bolt.
• Make sure that all the bolts are fully tight.
• The number of bolts required to mount the panel should be equal to the number of mounting feet of panel.
• Keep a 20" clearance to the left of the panel to facilitate the 120˚ door swing.
• Clearance between the oor and panelboard bottom is to be at least 1 foot.
Appleton • 1.800.621.1506 • www.appletonelec.com
FIGURE 6
504543-000 Rev. C 1/3/2020 • Page 6 of 19
Loading...
+ 13 hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.