Note: If floor anchoring and battery securing is required, read this section. If not, see “Prepare
for Cables” on page 5.
Note: Allow for enough working space behind the enclosure for electrical work to be carried
out (e.g. if you want to install a conduit box or if you want to connect an XR Battery Enclosure
at a later stage). Minimum rear clearance is 100 mm (3.93 in) and must comply with applicable
national and local codes. 600 mm (23.6 in) is recommended.
Note: The L-shaped floor anchoring brackets that secured the enclosure to the pallet during
shipment may be used for a stand-alone UPS enclosure to enhance stability. See this chapter for
hole positions and see also “Level the Enclosures (L-shaped Floor Anchoring Brackets) and
Install Batteries” on page 20. The L-shaped floor anchoring brackets are not necessary when
baying enclosures together. Instead, the three U-shaped floor anchoring brackets from the
baying kit are used.
Note: Hole positions are only intended as a guide.
System arrangements
APC recommends the following arrangements of UPS units and XR Battery Enclosures (XR) in parallel.
Examples with two parallel systems using baying kits.
Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation2
Hole positions for a stand-alone UPS enclosure with L-shaped anchoring brackets
523 mm (20.59 in)
352 mm (13.85 in ) enclosure
Conduit box (if applicable)
Floor anchoring hole
Minimum rear
clearance:
100 mm (3.93 in)
Note: Recommended minimum number of screws per enclosure for the L-shaped brackets is
four; one in each corner. Recommended floor bolt size: M8.
Model width: 352 mm (13.85 in) and 523 mm (20.59 in).
Note: Rear service clearance must comply with applicable national and local codes. 600 mm
(23.6 in) is recommended.
3Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation
Hole positions for up to four UPS units in parallel with U-shaped anchoring brackets.
Top view
90 mm (3.54 in)
160 mm (6.29 in)
60 mm (2.36 in)
60 mm (2.36 in)
60 mm (2.36 in)
60 mm (2.36 in)
160 mm (6.29 in)
90 mm (3.54 in)
352 mm (13.85 in)
0
323 mm
(12.71 in)
675 mm
(26.56 in)
1027 mm
(40.41 in)
1379 mm
(54.26 in)
Floor anchoring brackets
Top view
90 mm (3.54 in)
160 mm (6.29 in)
60 mm (2.36 in)
60 mm (2.36 in)
60 mm (2.36 in)
60 mm (2.36 in)
160 mm (6.29 in)
90 mm (3.54 in)
523 mm (20.59 in)
0
494.5 mm
(19.46 in)
1017.5 mm
(40.05 in)
1540.5 mm
(60.46 in)
2063.5 mm
(81.23 in)
Floor anchoring brackets
Note: Recommended minimum number of floor screws for the below two
configurations is 10.
Model width: 352 mm (13.85 in).
Model width: 523 mm (20.59 in).
Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation4
Prepare for Cables
UPS front viewXR Battery
Enclosure
Remove the front panel
1. Turn the screw to the
right to the unlocked
position.
2. Pull the top of the front
panel away from the
UPS.
3. Lift the front panel free
of the two slots at the
bottom of the enclosure.
4. Lift the battery
compartment cover free
of the two slots at the
bottom of the enclosures
(only in Japanese
configurations).
Remove the top cover
1. Loosen the six screws of the top
cover (four at the front and two at
the back).
2. Lift up from the back and push
forward to free the cover.
5Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation
Remove the cable landing cover and bottom plates
Bottom plate
Bottom plate
Conduit box
(bottom part)
Conduit
box (upper
part)
Cable
landing
cover plate
Conduit box
(bottom part)
Conduit
Box
(upper
part)
Cable
landing
cover
plate
To access the cable landing area in the UPS and the XR Battery Enclosure(s), follow this procedure:
+
N
1. Loosen the six M4 screws from the cable landing cover plate on the UPS and the XR Battery
Enclosure(s) and then remove the plates.
2. Remove the screws from the bottom plate on the UPS and the XR Battery Enclosure(s) and then
remove the plates.
3. Punch holes in the bottom of the conduit boxes (optional for 380/400/415 V) to fit the size of the
conduit pipes.
Note: The conduit box is not included in European and Japanese UPS units, but can be
purchased (SUVTOPT001: 10-20 kVA UPS, SUVTOPT002: 10-40 kVA UPS plus XR Battery
Enclosure).
4. Attach the bottom part of the conduit boxes to the back of the UPS and the back of the XR
Battery Enclosure, respectively with four screws each (if applicable). The bottom part of the
conduit box is secured to the enclosure with four screws.
Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation6