Security console installation should conform to local building codes
The installation instructions provided are for the Amico standard products. Slight
modi cations to the installations may be required. The product shipped to the job
site may not be exactly as shown on the installation drawings.
Before Installation
1. Review a copy of the nal approved shop drawing(s) and/or submittal package. These documents will
provide you with technical information speci c to your installation, such as:
- equipment types & quantities
- room numbers and location
- shop drawings of each unit type
2. Locate the console unit from the shipping boxes that you wish to install. The contents of each shipping
box are listed on the shipping document(s).
2 Amico Pipeline
Installation
1. Remove gas cover plates and devices by loosening any screws. Place everything in a safe and clean
location..
2. Remove the fascia by loosening the 2 screws (1 on each side) attaching it to the console. Place everything
in a safe and clean location.
www.amico.com 3
3. The console should be ush with the nished drywall after installation (see Fig. 1). Check the positioning
of the anges to determine if adjustment of the anges is necessary. If adjustment is not required, skip
steps 4 through 8, and proceed with step 9.
NOTE: The anges are preset for 5/8” drywall.
Fig. 1
NOTE 1:
Mounting hardware
(rivets or screws)
by others
STUD
CONSOLE BOX
END CAP
CONSOLE BOX
DRYWALL
FLANGE
NOTE: The anges are preset for 5/8” drywall.
4. Remove any aluminum device covers that are blocking access to the screws (2 per ange) holding the
ange to the console box. This is done by loosening the screws (typically 2 per cover) attaching it to the
console box. Place everything in a safe and clean location.
4 Amico Pipeline
5. Remove any devices that are blocking access to the ange
screws. Place everything in a safe and clean location.
6. Loosen the 2 ange screws and make necessary adjustments
on both sides.
7. Replace the devices removed in step 5.
8. Replace the aluminum device covers removed in step 4.
9. Mount the console box by using rivets or screws to attach
the anges (2 on each side) to the studs (See Fig. 1, NOTE 1).
See architectural drawings for mounting heights. Also coordinate mounting heights with contractor on site.
www.amico.com 5
10. Make all on-site gas and electrical connections, and perform any wiring required. If it is necessary to
remove an aluminum device plate to wire a device, do so by loosening the screws (typically 2 per cover)
attaching it to the console box.
11. Amico recommends additional backing strips to ensure security door is anchored securely, Note that the
screws used to mount the security door are approximately 1” above and below the console box. A
backing strip 2’ to 3’ wide will be adequate.
6 Amico Pipeline
12. Reassemble the fascia removed in step 2.
13. Reassemble the electrical and gas cover plates removed in step 1.
14. To mount the security door, place it against the wall such that
the console is centered both horizontally and vertically. Then,
use screws to secure it to the drywall, backing strips, or studs.
www.amico.com 7
Finished Product
8 Amico Pipeline
Other Installation Notes
1. Division 15 to connect gas stubs on console to building medical gas supply lines previously roughed in.
2. Division 16 to feed electrical conduits through top or back of consoles into ceiling space for connection to
normal, emergency and low voltage boxes provided in ceiling space by division 16 contractor.