Installation Instructions
Regal Series
Recessed Flatwall

Note
Flatwall installation should conform to local building codes
The installation instructions provided is for the Amico standard products.
Slight modications to the installations may be required. The product
shipped to the job site may not be exactly as shown on the installation
drawings.
Before Installation
Review a copy of the nal approved shop drawing(s) and/or submittal package. These
1.
documents will provide you with technical information specic to your installation, such as:
- equipment types and quantities
- room numbers and location
- shop drawings of each unit type
- wiring diagrams and rough-in locations
2.
Locate the atwall unit from the shipping boxes that you wish to install. The contents of each
shipping box are listed on the shipping document(s).
3.
Ensure that studs are located according to Figure 1 or Figure 2, depending on the width of the
atwall.
Figure 1 Figure 2
MAX 53”
19”
HEADWALL
MAX 48”
14”
HEADWALL
4.
Ensure that drywall thickness is 0.625”.
1 Amico Architectural

Installation
1.
Secure atwall to building structure using hardware (by others) compliant to applicable
building codes. Ensure mounting location corresponds to on-site location of rough-ins.
Fastening of studs to tracks by others.
nished ceiling
line
2.
Make all electrical and piping connections. Med gas piping is terminated as per shop drawings;
electrical services are terminated at boxes attached to upper framing in atwall structure.
Note
Remove all zip ties where applicable
medical gas piping
termination
electrical box
termination, divided
for each power (see
submittal drawings)
Install drywall. See following section for instructions. Note that the unit is shipped with a gap
3.
allowed between the atwall front lip and stud face; this is to allow clearance for drywall installation.
www.amico.com 2

Note
Store all parts removed from the headwall in a safe and clean location, to be reattached after
drywall has been installed.
Remove the 2 plastic snap-on end caps. Remove the 2 metal end plates by loosening the 4
1. 2.
screws attaching them to the rails.
remove remove
3 Amico Architectural

Remove the laminate strips by sliding them out of the rails.
3.
4.
Remove the rails by loosening the screws (4 on each side) attaching them to the console box.
www.amico.com 4

Install and nish drywall, including taping and painting.5.
Reattach the rails by replacing the screws
(4 on each side) that attach them to the
console box.
Replace the laminate by sliding it into the rails.6. 7.
5 Amico Architectural

3.
Reattach the 2 metal end plates by using
the 4 screws to attach them to the rails.
3.
Replace the 2 plastic snap-on end caps.
Other Installation Notes
3.
Division 15 to connect gas stubs on atwall to building medical gas supply lines previously
roughed in.
4.
Division 16 to do all electrical connections required.
www.amico.com 6

www.amico.com
Amico Architectural | www.amico.com
85 Fulton Way, Richmond Hill
Ontario, L4B 2N4, Canada
71 East Industry Court, Deer Park
NY 11729, U.S.A
Toll Free Tel: 1.877.264.2697
Toll Free Fax: 1.866.440.4986
Tel: 905.763.7778
Fax: 905.763.8587
Email: info@amico.com
C US LISTED
INSTALL INSTR. REGAL SERIES SURFACE MOUNTED FLATWALL 2011