Westinghouse PD06OD, PD070T, PD100T, PD116T, PDO75T Installation Booklet

...
Page 1
Page 2
Page 2
Inspection And Handling
When unit is received, it should be checked for visible or concealed damage. If damage has oc­curred it should be reported to the carrier im­mediately and claim filed.
Units are factory mounted on two permanent angle beam, carbon steel skids. Four
2-7/8”
lif­ting eyes are provided in the skids to allow rig­ging. Spreader bars must be used between rig­ging lines to prevent damage to the unit. Rollers may be used under the skids to facilitate moving the unit a short distance. Physical damage to the unit, after accep­tance, is not the responsibility of Westinghouse.
Location And Mounting
Westinghouse Model PD060 135 Air Cooled Packaged Water Chillers are designed for out­door application and may be mounted on roof or at ground level. Air flow through the con­denser is vertical and the unit may be located adjacent to outside of building or on roof without regard for prevailing wind direction.
Since these units are air cooled, the flow of air to and from the condenser coil must not be im-
peded. There must be no obstruction above the unit that would tend to deflect discharge air downward where it could be recirculated
back to the inlet of the unit. The required
overhead air space should be a minimum of 8
feet. Duct work must not be applied to the fan
outlets.
The unit must be installed with sufficient
clearance for air entrance to the condenser coil
and for servicing access. The unit should be
located not closer than four feet from any wall or other obstruction. Clearance must be provid­ed at either end of the unit to permit removal of tubes from the chiller.
Unit must be set on a solid and level founda­tion.
On roof installations the unit should be
mounted on subbeams which span load- bear-
ing walls to prevent excessive vibration.
On ground level installations the unit should be
mounted on a substantial base that will not
settle. A one piece concrete slab with footings
extended below the frost line is recommended. A space should be left between the slab and the building to prevent the transmission of sound and vibration.
Vibration mounts may be used for roof
mounted units or other locations where noise might be objectionable.
Wiring
A unit wiring diagram showing the required power supply characteristics and all factory supplied wiring details is provided with unit.
Separate, field supplied, disconnects must be installed in the power supply and should be
within the sight of the unit.
Separate 110 volt power source must be field supplied to provide power for control and
heater circuits.
Chiller Piping
The chiller inlet water pipe should be con­nected to the expansion valve end of the liquid chiller barrel and the outlet water pipe con­nected to the opposite end of the chiller barrel.
A flow switch must be installed in a straight horizontal section of the chilled water piping.
Chiller water pressure drop data for the PD units are shown in Table 2. Gauges should be installed in the piping to and from the chiller to measure the pressure drop and to insure the proper (GPM) flow rate.
A strainer should be installed in the piping on the inlet side of the chiller and vibration eliminators should be employed on both the in­let and outlet pipes. Air vents should be located at all high points in the piping system. Vents should be located to be accessible to servicing. Drain connections should be
provid­ed at all low points to permit complete drainage of chiller and piping system.
The chiller water piping should be insulated to reduce heat pickup and to prevent condensa­tion. If the system is for year round operation or it it will not be drained in the winter, the chilled water piping should be protected against freezing by electric heating cable or other suitable means.
Upon completion of chiller piping, start the system water pump and purge air from the system. Air purging should be done from the high points in the water circuit. Purging of the chiller barrel may be accomplished through the vent pipe located on the top of the chiller com-
partment. Failure to purge air from the water
circuit will result in inadequate water flow and
may cause the unit to cut out on low water
flow freeze protection.
Start-Up
Refer to start, test, and check list included
with this manual
Check all electrical and mechanical connections for shipping looseness and tighten all screws on electrical terminals.
Activate the 120 volt chiller and crankcase heater circuit 24 hours prior to unit start-up.
Rotate each fan prior to start-up. Fans should turn freely. On belt drive units check belt ten sion and pulley alignment. After two weeks of
operation, readjust belt tension to ac­commodate for belt stretching.
Check all control settings as specified in Table
1. Check the compressor oil level through
crankcase sight glass. The oil level should be
1/3
to
2/3
of the way up on the sight glass. If oil is low, add oil in accordance with the direc­tions in “Maintenance” instructions below.
Caution: The compressor suction and
discharge service valves must be open or
backseated before starting the compressor. Close the valves no more than two turns to give the pressure taps access to the system for
pressure readings, charging, etc. All receiver valves must also be open for sustained opera­tion.
All compressors are solid mounted on isopads,
therefore, compressor hold down bolts must
not be loosened. Loosening these bolts will
cause excessive vibration of the compressor
and may result in refrigerant line breakage.
Prior to start- up check all compressor hold
down bolts for tightness.
To start unit, throw main disconnects into
“ON” position and place system “OFF-ON”
switch
(S1)
in “ON” position. (Note: If unit is equipped with optional lock-out timer, unit will not start until timer has completed its cycle.) Once the main disconnect switches and system
“ON-OFF” switch (S1) have been energized and providing chiller water flow has been established, the unit will operate automatically
in response to the chiller water thermostat.
Maintenance
Condenser
Units equipped with direct drive fans have in-
herently protected motors and permanently
lubricated bearings, which do not require
lubrication.
Units equipped with belt drive fans have in-
herently protected motors. Fan belts, fan bear-
ings and motor bearings require periodic
maintenance as follows:
Fan Belts After two weeks operation, the belts will have nearly reached their perma­nent stretch, therefore, each belt should be checked again and proper adjustments made. To maintain good fan and motor operation, the belt tension should be check­ed at three month intervals.
Fan Bearings Each fan shaft is provided with ball bearings of the relubricable type. Each bearing is provided with grease fit­tings, accessible through the individual motor access panels. It is recommended the bearings be greased by adding 4 to 5 shots
Page 3
Installation Bulletin PDG4
Page 3
with a hand gun. The suggested greasing interval is indicated on a sticker attached to the unit.
3. Motor Bearings Each motor is equipped with ball bearings. Ball bearings consume a very small amount of lubricant, but enough
must be present at all times to prevent motor injury. The length of time a bearing
can run without having grease added or
replaced will depend upon the operating conditions. Under normal operating condi­tions the motor bearings should be
lubricated at 2000 hour operating intervals,
The lubricant should be from a clean closed
container and should be anti-friction type
bearing grease free from solid fillers or
other harmful ingredients. Lubricant should
have a safe operating temperature of
2OOO’=F.
The air inlet of the condenser coil should be kept clean through a regular preventative maintenance program.
Compressor
The oil level of the compressor(s) should be
checked periodically, with the unit shut off. If oil is needed, allow unit to
pumpdown
and
then place system “OFF-ON” switch
(S1)
in the off position. Close the suction and discharge valves at the compressor. Partially screw the pipe plug out of the filler hole (the filler hole is located just above and left of the crankcase sight glass on most compressors) and allow pressure to bleed from crankcase completely before removing plug.
Add oil through the filler hole, using only
Suniso G3 Refrigerant oil that has not been ex­posed to air or other contaminates.
(Do
not
overfill).
Replace and tighten filler hold pipe plug. Reopen compressor suction and discharge valves. (CAUTION: Do not run compressor when discharge valve is closed).
On systems equipped with the AC&R method of oil equalization, the oil may be added through the
1/4
SAE flare gage port of the up­per valve on the oil reservoir when the stem is in the front seated position. (The valve stem must be backseated when the unit is operating).
The oil level should be between the two sight ports. Check oil level after 2 hours of operation and again after 2 days of operation.
Winter Control Data
Due to the wide range of applications, it is sometimes necessary to operate the Chillers at ambients below summer conditions. Without proper control, when ambients drop below 60F the pressure differential between the condenser and the evaporator is below the level to insure proper thermal expansion valve operation. As a
result, the unit may cycle on low pressure con trol with the possibility of evaporator freezing. Westinghouse offers two types of system con­trol allowing the units to operate at the winter ambients indicated:
Fan Cycling Medium Ambient Control To
30°F
(STANDARD EQUIPMENT - FACTORY
INSTALLED)
A fan cycling control is standard on all Westinghouse Air Cooled Packaged Water
Chillers to provide proper operating head
pressures, in ambient conditions
to
30°F.
This is an automatic operation and is ac­complished by cycling one fan on two fan units; two fans, in sequence, on three fan units; and three fans, in sequence, on four fan units. The last fan on each unit is connected
directly to the load side of the fan contactor, which in turn is controlled by the operation of the fan cycling pressure control(s) and the
compressor contactor auxiliary
contact.
This
arrangement provides positive start-up control down to + 30F by delaying the condenser fan operation until a predetermined head pressure
is obtained.
Fan Cycling And Heated Receiver(s)
Low Ambient Control
0°F
(OPTIONAL EQUIPMENT FACTORY IN­STALLED)
A heated receiver lone for each refrigerant cir-
cuit) to be used in conjunction with the fan cycling control to assure compressor start in ambient temperatures down to
O’F
is offered
as an optional priced feature.
This, also, is an automatic operation and is ac­complished by a pressure cycling control (set to cut in at 180 PSI and set to cut out at 210 PSI),
sensing the receiver pressure and con­trolling a heater. A check valve, factory install­ed, in the refrigerant circuit between the receiver and the condenser prevents refrigerant migration from receiver to condenser during the off cycle. When the receiver pressure drops below 180 PSI, as would be encounted on the off cycle at low ambient conditions, the pressure switch would close and the receiver heater would be energized. With the refrigrant flow blocked from receiver to condenser by the check valve and prevented from flowing from receiver to evaporator by the liquid line solenoid valve receiver pressure would rise and be maintained sufficiently to allow expansion valve operation when the unit starts. If at any time, the receiver pressure would rise to 210 PSI the pressure control would open and the receiver heater would be de-energized. A back­up safety thermostat is provided to shut off the heater in the event the receiver temperature reaches 130F
Once the unit has started, head pressure would
be maintained by the fan cycling controls as
explained under heading “Fan Cycling Medium
Ambient Control” above.
Page 4
Page 4
PD060-135 Control Settings
Tskla ,
IrnYIW I
Pressure Actuated
Fan Cycling Pressure Control (Adjustable)
High Pressure Control (Manual Reset) Low Pressure Control (Auto Reset)
Oil Pressure Safety Control (Non-Adjustable) Manual Reset
Legend
Factory Setting
FCP 1
Cut-In 280 PSIG
FCP2
cut-out 170 PSIG
HP 1
Cut-In
300 PSIG HP2 cut-out 365 PSIG LP 1
Cut-In 25 PSIG
LP2 cut-out 5 PSIG
OP1 OP2
Cut-Out Pressure
OP3
Differential 9 PSIG
OP4
Receiver Pressure Control (Optional Heated Receiver)
Low Pressure Freeze Control
(Manual Reset)
P1 P2 LPF 1 LPF 2
Cut-In cut-out cut-out
180
PSIG
210 PSIG
48 Psig
Temperature Actuated
Chiller Low Water Temperature Thermostat
Legend Factory Setting
T1
cut-out 37°F
Chiller Water Cycling Thermostat (Adjustable) T2 Dial Set At
55’F
Fan Cycling Ambient Thermostat (Adjustable)
FCT 1 FCT 1
Cut-In
75’F
cut-out
72’F
FCT 2 FCT 2
Cut-In
55’F
cut-out
52’F
FCT 3 FCT 3
Cut-In
38°F
cut-out
35’F
Chiller Heater Thermostat (Non Adjustable)
Receiver Heater Thermostat (Optional Heated Receiver) (Optional Heated Receiver)
T3 Cut-In
40°F
cut-out 45’
F
T4
Cut-In
loOoF
T5 cut-out
13O“F
Unit Operating Limitations
1.
2.
3.
4.
5.
6.
Maximum ambient air to condenser is 1 loo.
For minimum ambient operation (see winter control data page
3).
Maximum allowable cooler water pressure is
150
PSIG.
Maximum allowable water temperature to cooler is
75O.
Units must not have leaving water temperatures of 42” or lower unless provided with
capacity
control or used with a
glycol
solution.
Unit must be allowed to pump down at the end of each operating cycle (except on safety control shut
down.)
Where timeclock shut down, low
ambient lock out or remote manual shut down is required consult factory.
Page 5
Page 6
Page 7
Sequence Of Operation
Starting Sequence Move control switch
"S1"
to the “On” posi-
tion. This will provide power for SSM
1-SSM4 (solid state motor protectors), through flow switch T 1 (low water temp. safety), cycling thermostat T2-Stage 1, through LLl (lead-lag switch). to energize R1 (non-recycle relay) and TD1 (stage
start relay). Contacts 1 and 3 of R1 close providing power through HP1 (high pressure safety), LPF1 (low pressure freeze safety),
SSM1
and SSM2,
OP1
(oil pressure
safety), contacts 4 and 6 of
R
1, to energize
SOL1 (liquid line solenoid).
When SOL 1 opens, low side pressure in­creases to the cut-in setting of LP1 (low pressure control), LP1 closes, energizing
com-
pressor
contactor Cl, which provides power to
compressor motor No.
1.
TD1 times out, closes contacts 2 and 4 of
TD1 If T2 Stage 2 is calling for cooling, power is provided through
LL1,
contacts 2 and 4 of TDI to energize R3 and TD2. Contacts 1 and 3 of R3 close providing power through OP2 to energize C3 which provides power to
com-
pressor
motor No. 2.
Compressor motors No. 3 and No. 4
(ref.
cir-
cuit No. 2). start in same sequences as No. 1
and No 2 through T2 Stage 3 and 4. TD2 and TD3, TD4 stages starting between compressor motors No. 3 and No. 2 when LL1 is in op­posite position.
The fan circuit is interlocked through auxiliary contacts
C1A,
C3A, C5A. C7A of contactors Cl, C3, C5, C7 respectively, to energize fan contactor
C9
when the high side pressure in-
creases to the cut-in setting of FCP1 or FCP2
(fan cycling pressure controll. Fan Motor M2 and M3 are energized through their respective ambient thermostats
FCT1
and FCT2.
Pump-Down Sequence
T2 Stage 4 is satisfied and opens, R4
de-
energizes, contacts 1 and 3 of R4 opens
de-
energizing C7. Compressor Motor No. 4 drops
off the line.
T2 Stage 3 is satisfied and opens, R2
de­energizes, Contacts 1 and 3 and 4 and 6 of R2 open,
SOL1
de-energizes and closes. Contactor
C5 remains energized through
auxiliary
contact C5B until the low side pressure drops to the cut-out setting of LP2. When LP2 opens, C5 de-energizes and compressor Motor No. 3 drops off the line.
Installation Bulletin PD-G4
Page 7
Circuit No. 1 de-energizes in the same se­quence as circuit No. 2 through T2 Stages 2 and 1, in response to return water temperature.
Optional Accessory Sequence
Part Winding Start (208/230 Volt Units
Only)
A time delay relay is wired in series with compressor contractor C2 and delays energizing of C2 for 1 second after Cl is energized.
Unloading solenoids(s) mounted on compressor head is energized in response to return water temperature by cycling thermostat T2.
Non-Short Cycling
Non-short cycling relay (TD5) is energiz­ed through N. C contacts of R7 at start­up and immediately following pump­down. TD5 times out closing contacts 3 and 4 of TD5. This allows R1 to become energized on cooling demand anytime unit has been off for 5 minutes.
Page 8
Page 9
Installation Bulletin PD-G4
Page 9
Sequence Of Operation
Starting Sequence
Move control switch
"S1"
to the “On” posi-
tion. This will provide power for
SSM1-SSM4
(solid state motor protectors), through flow
switch
T1
(low water temp. safety), cycling thermostat T2 Stage 1, through LL1 (lead-lag switch), to energize R1 (non-recycle
relay)
and
TD1
(stage start relay). Contacts 1 and 3 of R1
close providing power through HP1
(high pressure safety), LPF1 (low pressure freeze safety),
SSM1
and SSM2,
OP1
(oil pressure
safety). contacts 4 and 6 of
RR1,
to
energize
SOL1
(liquid line solenoid).
When SOL1 opens, low side pressure Increases to the cut-in setting of LP1 flow pressure con­trol). LP1 closes, energizing compressor con tactor Cl, which provides power to compressor motor No. 1.
TD1
times
out, closes contacts 2 and 4 of
TD1.
If T2 Stage 2 is calling for
cooling,
power is
provided through
LL1,
contacts 2 and 4 of TDI to energize R3 and TD2. Contacts 1 and 3 of R3 close providing power through OP2 to energize C3 which provides power to
com-
pressor
Motor No. 2.
Compressor motors No. 3 and No. 4 (ref. cir­cuit No. 21, start in same sequence as No. 1
and No. 2 through T2 Stage 3 and 4, TD2 and TD3 TD4 stages starting between compressor motors No. 3 and No. 2 when
LL1 is in
op-
posite position.
The fan circuit is interlocked through auxiliary contacts CIA, C3A.
C5A, C7A of contactors Cl, C3, C5, C7 respectively. to energize fan contactor
C9
when the high side pressure in creases to the cut-in setting of FCP1 or FCP2 (fan
cycling pressure control). Fan Motor M2 and M3 are energized through their respective ambient thermostats FCT1 and
FCT2.
Pump-Down Sequence
T2 Stage 4 is satisfied and opens, R4
de­energizes, contacts 1 and 3 of R4 opens de­energizing C7. Compressor Motor No 4 drops off the line.
T2 Stage 3 is satisfied and opens, R2
de­energizes, Contacts 1 and 3 and 4 and 6 of
R2 open, SOL1 de-energizes and closes. Contactor C5 remains energized through auxiliary contact C5B until the low side pressure drops to the cut-out setting of LP2. When LP2 opens, C5 de-energizes and compressor Motor No.3 drops off the line.
Circuit No. 1 de-energizes in the same se­quence as circuit No. 2 through T2 Stages 2 and 1. in response to return water temperature.
Optional Accessory Sequence
Part Winding Start
(208/230 Volt Units
Only)
A time delay relay is wired in series with compressor contractor C2 and delays energizing of C2 for 1 second after Cl is energized.
Unloading
solenoid(s)
mounted on com­pressor head is energized in response to return water temperature, by cycling thermostat T2.
Non-Short Cycling
Non-short cycling relay
(TD5) is energiz­ed through N. C. contacts of R7 at start-up and immediately following pump-down. TD5 times out closing con­tacts 3 and 4 of TD5. This allows
R1 to become energized on cooling demand anytime unit has been off for 5 minutes.
Page 10
Page 11
Packaged Air Cooled Water Chiller
Start Up Procedure
Check Points
Yes No
Equipment Inspection: a. Unit damaged on arrival
b. Material received agrees with shipping
papers
Setting Unit:
Wiring:
Piping
Alignment:
(Belt Drive Units)
Before Start-up:
After start-up:
a. Vibration isolator used b.Spring isolator adjusted for equal height c. If rubber in sheer isolators are used, is
unit levelled by shimming
a. Power wiring complete b. Control wiring complete c.Electric service adequate for load d. Power source voltage correct for
motor(s)
used
e.
Motor circuit has proper size fusetrons f. System wired per diagram g. All lead connections tight
h. Wiring complies with local codes
a.
Piping complies with applicable codes
b. External piping independently supported c. Chilled water lines insulated
a. All belts adjusted and checked for
tautness
b. All pulleys checked and adjusted for
proper pitch, tightness and alignment
a.
Check compressor for proper oil level
b. Open compressor suction and discharge
service valves.
c. Open receiver liquid
valve(s)
d. Open suction, oil and discharge valves
to pressure gauges (if supplied)
e. Check rotation of all fan and blower
motors
f. All motors and bearings lubricated
(Belt
Drive Units)
g. Start auxiliary equipment (Pumps. fans,
etc.)
h. Is crankcase heater operating?
a. Check oil pressure. Is pressure at Mfg’s
recommendation? b. Re-check oil level in crankcase c. Check high pressure control
Page 12
Start Up Procedure
Check Points
Yes
No
d. Check oil pressure safety switch e. Check and adjust low pressure or
temperature freeze control f. Check and adjust operating thermostat g. Check and adjust low pressure operating
control h. Check and adjust expansion valve
superheat
Operating Data
Chiller
Voltage: L-l _ L-2 _ L-3 _
Pressure gauge readings:
a. Suction b. Discharge c. Oil
~
d.
Net oil Pressure
c-b = High pressure switch setting: (cut in) Checked setting
Yes
Low pressure switch setting: (cut
in)
Checked setting
Yes
Low oil pressure switch checked
Yes Low pressure freeze control If part winding start, time delay is
Temperature of air entering condenser
Temperature of air leaving condenser Temperature of Chilled Water entering chiller
~_
Temperature of Water (Chilled) leaving chiller Chilled water pressure entering chiller Chilled water pressure leaving chiller
psig psig psig
psig
psig _
psig (out) No psig
psig (out)
_ No
No Cut in
~__~
_
cut out seconds.
OF.
OF. OF. OF
psig psig
0
e
Westinghouse 0 Commercial - Industrial Air Conditioning Division 0 Staunton, VA. 24401 In Canada:
Westinghouse Canada Ltd. 492 Speers Road, Oakville, Ontario
World wide: Westinghouse Air Conditioning International
Westinghouse
Bld,
Gateway Center, Pittsburgh, PA. 16222
V8/77/6M
Loading...