Lochinvar KBN080 Installation Manual

0 (0)

KB-I-O-16

Installation & Operation Manual

Models: 80 - 285

Starting Serial #H07H10040039

WARNING This manual must only be used by a qualified heating installer / service

technician. Read all instructions, including this manual and the Knight Boiler Service Manual, before installing. Perform steps in the order given. Failure to comply could result in severe personal injury, death, or substantial property damage.

Save this manual for future reference.

Contents

HAZARD DEFINITIONS . . . . . . . . . . . . . . . . . . . . . . . . . .

2

PLEASE READ BEFORE PROCEEDING . . . . . . . . . . . .

3

THE KNIGHT BOILER -- HOW IT WORKS . . . . . . . . . . .

4-6

RATINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

7

1. DETERMINE BOILER LOCATION

 

Provide Clearances . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 Provide Air Openings to Room . . . . . . . . . . . . . . . . . . . . 10 Flooring and Foundation . . . . . . . . . . . . . . . . . . . . . . . . 10 Residential Garage Installation . . . . . . . . . . . . . . . . . . . . 10 Vent and Air Piping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 Prevent Combustion Air Contamination . . . . . . . . . . . . . . 10 Corrosive Contaminants and Sources . . . . . . . . . . . . . . . 11 Using an Existing Vent System to Install a New Boiler . . 11 Removing a Boiler from Existing Common Vent . . . . . . . 12

2. PREPARE BOILER

Remove Boiler from Wood Pallet . . . . . . . . . . . . . . . . . . 13 Gas Conversions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 Leveling the Boiler . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

3. GENERAL VENTING

Direct Venting Options . . . . . . . . . . . . . . . . . . . . . . . . . . . 14-15 Install Vent and Combustion Air Piping . . . . . . . . . . . . . . 16

PVC/CPVC Vent and Air Piping Materials . . . . . . . . . 16 Requirements for Installation in Canada . . . . . . . . . . . . . 16 Installing Vent and Air Piping . . . . . . . . . . . . . . . . . . . . . . 16 PVC/CPVC Air Intake/Vent Connections . . . . . . . . . . . . . 18 Air Inlet Pipe Materials . . . . . . . . . . . . . . . . . . . . . . . . . . 18 Stainless Steel Vent . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18 Stainless Steel Air Intake/Vent Connections . . . . . . . . . . 19 Min./Max. Combustion Air & Vent Piping Lengths . . . . . . 19 Vent and Air Piping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 Optional Room Air . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

4. SIDEWALL DIRECT VENTING

Vent/Air Termination - Sidewall . . . . . . . . . . . . . . . . . . . . 21-24 Determine Location . . . . . . . . . . . . . . . . . . . . . . . . . . 21-23 Prepare Wall Penetrations . . . . . . . . . . . . . . . . . . . . . 23 Termination and Fittings . . . . . . . . . . . . . . . . . . . . . . . 24

Multiple Vent/Air Terminations . . . . . . . . . . . . . . . . . . . . . 24 Sidewall Termination - Optional Concentric Vent . . . . . . 25-27

5. VERTICAL DIRECT VENTING

Vent/Air Termination - Vertical . . . . . . . . . . . . . . . . . . . . . 28-29 Determine Location . . . . . . . . . . . . . . . . . . . . . . . . . . 28 Prepare Roof Penetrations . . . . . . . . . . . . . . . . . . . . . 29

Termination and Fittings . . . . . . . . . . . . . . . . . . . . . . . . . 29

Multiple Vent/Air Terminations . . . . . . . . . . . . . . . . . . . . . 29

Vertical Termination - Optional Concentric Vent . . . . . . . 30-31

6. HYDRONIC PIPING

System Water Piping Methods . . . . . . . . . . . . . . . . . . . . 32

Low Water Cutoff Device . . . . . . . . . . . . . . . . . . . . . . . . . 32

Chilled Water System . . . . . . . . . . . . . . . . . . . . . . . . . . . 32

Freeze Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32

General Piping Information . . . . . . . . . . . . . . . . . . . . . . . 32

Relief Valve / T & P Installation . . . . . . . . . . . . . . . . . . . . 32-33

Circulator Sizing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33

Near Boiler Piping Connections . . . . . . . . . . . . . . . . . . . 33

Near Boiler Piping Components . . . . . . . . . . . . . . . . . . . 35

7. GAS CONNECTIONS

Connecting Gas Supply Piping . . . . . . . . . . . . . . . . . . . . 42

Natural Gas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43

Pipe Sizing for Natural Gas . . . . . . . . . . . . . . . . . . . . 43

Natural Gas Supply Pressure Requirements . . . . . . . 43

Propane Gas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43

Pipe Sizing for Propane Gas . . . . . . . . . . . . . . . . . . . 43

Propane Supply Pressure Requirements . . . . . . . . . . 43

Check Inlet Gas Supply . . . . . . . . . . . . . . . . . . . . . . . . . . 44

Gas Pressure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45

Gas Valve Replacement . . . . . . . . . . . . . . . . . . . . . . . . . 45

8. FIELD WIRING

Line Voltage Connections . . . . . . . . . . . . . . . . . . . . . . . . 46

Low Voltage Connections . . . . . . . . . . . . . . . . . . . . . . . . 47

Wiring of the Cascade . . . . . . . . . . . . . . . . . . . . . . . . . . . 48

9. CONDENSATE DISPOSAL

 

Condensate Drain . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

50

10. STARTUP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

51-56

11. OPERATING INFORMATION

 

General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57

Cascade . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59-60

Sequence of Operation . . . . . . . . . . . . . . . . . . . . . . . . . . 61-62

Knight Boiler Control Module . . . . . . . . . . . . . . . . . . . . . . 63-64

Status Display Screens . . . . . . . . . . . . . . . . . . . . . . . . . . 65-68

12. MAINTENANCE

 

Maintenance and Annual Startup . . . . . . . . . . . . . . . . . .

69-73

13. DIAGRAMS

 

Ladder Diagram . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74

Wiring Diagram . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75

Revision Notes . . . . . . . . . . . . . . . . . . . . . . . . . Back Cover

Hazard definitions

The following defined terms are used throughout this manual to bring attention to the presence of hazards of various risk levels or to important information concerning the life of the product.

DANGER

WARNING

CAUTION

CAUTION

NOTICE

DANGER indicates an imminently hazardous situation which, if not avoided, will result in death or serious injury.

WARNING indicates a potentially hazardous situation which, if not avoided, could result in death or serious injury.

CAUTION indicates a potentially hazardous situation which, if not avoided, may result in minor or moderate injury.

CAUTION used without the safety alert symbol indicates a potentially hazardous situation which, if not avoided, may result in property damage.

NOTICE indicates special instructions on installation, operation, or maintenance that are important but not related to personal injury or property damage.

2

Installation & Operation Manual

Please read before proceeding

WARNING Installer – Read all instructions, including this manual and the Knight Boiler Service Manual, before installing. Perform steps in the order given.

NOTICE

WARNING

WARNING

User – This manual is for use only by a qualified heating installer/service technician. Refer to the User’s Information Manual for your reference.

Have this boiler serviced/inspected by a qualified service technician, at least annually.

Failure to comply with the above could result in severe personal injury, death or substantial property damage.

When calling or writing about the boiler – Please have the boiler model and serial number from the boiler rating plate.

Consider piping and installation when determining boiler location.

Any claims for damage or shortage in shipment must be filed immediately against the transportation company by the consignee.

Factory warranty (shipped with unit) does not apply to units improperly installed or improperly operated.

Failure to adhere to the guidelines on this page can result in severe personal injury, death, or substantial property damage.

If the information in this manual is not followed exactly, a fire or explosion may result causing property damage, personal injury or loss of life.

This appliance MUST NOT be installed in any location where gasoline or flammable vapors are likely to be present.

WHAT TO DO IF YOU SMELL GAS

Do not try to light any appliance.

Do not touch any electric switch; do not use any phone in your building.

Immediately call your gas supplier from a near by phone. Follow the gas supplier’s instructions.

If you cannot reach your gas supplier, call the fire department.

Installation and service must be performed by a qualified installer, service agency, or the gas supplier.

When servicing boiler –

To avoid electric shock, disconnect electrical supply before performing maintenance.

To avoid severe burns, allow boiler to cool before performing maintenance.

Boiler operation –

Do not block flow of combustion or ventilation air to the boiler.

Should overheating occur or gas supply fail to shut off, do not turn off or disconnect electrical supply to circulator. Instead, shut off the gas supply at a location external to the appliance.

Do not use this boiler if any part has been under water. The possible damage to a flooded appliance can be extensive and present numerous safety hazards. Any appliance that has been under water must be replaced.

Boiler water –

Thoroughly flush the system (without boiler connected) to remove sediment. The high-efficiency heat exchanger can be damaged by build-up or corrosion due to sediment.

Do not use petroleum-based cleaning or sealing compounds in the boiler system. Gaskets and seals in the system may be damaged. This can result in substantial property damage.

Do not use “homemade cures” or “boiler patent medicines”. Serious damage to the boiler, personnel, and/or property may result.

Continual fresh make-up water will reduce boiler life. Mineral buildup in the heat exchanger reduces heat transfer, overheats the stainless steel heat exchanger, and causes failure. Addition of oxygen carried in by makeup water can cause internal corrosion in system components. Leaks in boiler or piping must be repaired at once to prevent makeup water.

Freeze protection fluids –

NEVER use automotive antifreeze. Use only inhibited propylene glycol solutions, which are specifically formulated for hydronic systems. Ethylene glycol is toxic and can attack gaskets and seals used in hydronic systems.

3

Installation & Operation Manual

The Knight Boiler - How it works...

1.Stainless steel heat exchanger

Allows system water to flow through specially designed coils for maximum heat transfer, while providing protection against flue gas corrosion. The coils are encased in a jacket that contains the combustion process.

2.Heat exchanger access cover

Allows access to the combustion side of the heat exchanger coils.

3.Blower

The blower pulls in air and gas through the venturi (item 5). Air and gas mix inside the blower and are pushed into the burner, where they burn inside the combustion chamber.

4.Gas valve

The gas valve senses the negative pressure created by the blower, allowing gas to flow only if the gas valve is powered and combustion air is flowing.

5.Venturi

The venturi controls air and gas flow into the burner.

6.Flue gas sensor

This sensor monitors the flue gas exit temperature. The control module will modulate and shut down the boiler if flue gas temperature gets too hot. This protects the flue pipe from overheating.

7.Boiler outlet temperature sensor

This sensor monitors boiler outlet water temperature (system supply). If selected as the controlling sensor, the control module adjusts boiler firing rate so the outlet temperature is correct.

8.Boiler inlet temperature sensor

This sensor monitors return water temperature (system return). If selected as the controlling sensor, the control module adjusts the boiler firing rate so the inlet temperature is correct.

9.Temperature and pressure gauge (field installed, not shown)

Monitors the outlet temperature of the boiler as well as the system water pressure.

10.Electronic display

The electronic display consists of 7 buttons and a dual line 32character liquid crystal display.

11.Flue pipe adapter

Allows for the connection of the PVC vent pipe system to the boiler.

12.Burner (not shown)

Made with metal fiber and stainless steel construction, the burner uses pre-mixed air and gas and provides a wide range of firing rates.

13. Water outlet (system supply)

NPT water connection that supplies hot water to the system, either 1" or 1-1/4", depending on the model.

14.Water inlet (system return)

NPT water connection that returns water from the system to the heat exchanger, either 1" or 1-1/4", depending on the model.

15.Gas connection pipe

Threaded pipe connection, either 1/2" or 3/4", depending on the model. This pipe should be connected to the incoming gas supply for the purpose of delivering gas to the boiler.

16.SMART Control Module

The SMART Control responds to internal and external signals and controls the blower, gas valve, and pumps to meet the heating demand.

17.Automatic air vent

Designed to remove trapped air from the heat exchanger coils.

18.Air intake adapter

Allows for the connection of the PVC air intake pipe to the boiler.

19.High voltage junction box

The junction box contains the connection points for the line voltage power and all pumps.

20.Boiler drain port

Location from which the heat exchanger can be drained.

21.Low voltage connection board

The connection board is used to connect external low voltage devices.

22.Low voltage wiring connections (knockouts)

Conduit connection points for the low voltage connection board.

23.Condensate drain connection

Connects the condensate drain line to a 1/2" PVC union.

24.Access cover - front

Provides access to the gas train and the heat exchanger.

25.Ignition electrode

Provides direct spark for igniting the burner.

26.Flame inspection window

The quartz glass window provides a view of the burner surface and flame.

27.Gas shutoff valve

Manual valve used to isolate the gas valve from the gas supply.

28.High limit sensor

Device that monitors the outlet water temperature. If the temperature exceeds its setting, it will break the control circuit, shutting the boiler down.

29.Relief valve

Protects the heat exchanger from an over pressure condition. The relief valve may be set at 30 psi.

30.Flame sensor

Used by the control module to detect the presence of burner flame.

31.Line voltage wiring connections (knockouts)

Conduit connection points for the high voltage junction box.

32.Top panel

Removable panel to gain access to the internal components.

33.Power switch

Turns 120 VAC ON/OFF to the boiler.

34.Leveling legs

Used to allow the heat exchanger to be leveled. This is needed for the proper draining of the condensate from the combustion chamber.

35.Air pressure switch

The air pressure switch detects blocked inlet conditions.

4

Lochinvar KBN080 Installation  Manual

Installation & Operation Manual

The Knight Boiler - How it works... (continued)

Models 80 - 210

Front View - Models 80 - 210

Rear View - Models 80 - 210

 

10

19

21

 

35

 

 

18

27

16

 

15

4

 

5

 

8

28

 

 

3

 

7

14

 

 

 

29

 

 

25

 

1

13

2

 

 

 

12

 

17

20

 

 

34

 

 

23

26

 

30

 

 

 

Left Side (inside unit) - Models 80 - 210

Right Side (inside unit) - Models 80 - 210

 

 

 

5

Installation & Operation Manual

The Knight Boiler - How it works...

Model 285

 

18

10

15

 

24

Front View - Model 285

Rear View - Model 285

 

35

27

4

5

Left Side (inside unit) - Model 285

Right Side (inside unit) - Model 285

6

Installation & Operation Manual

Ratings

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Knight Boiler

 

 

 

 

Other Specifications

 

 

 

 

 

 

 

I=B=R Rating

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Net

 

 

 

 

 

 

 

 

 

Model Number

 

Input

 

 

Gross

I=B=R

 

Boiler

 

 

 

 

 

 

 

 

MBH

 

 

Output

Ratings

 

 

 

 

Air

 

Vent

 

 

 

 

 

 

 

Water

Water

 

Gas

 

 

 

 

 

 

 

 

 

MBH

Water,

 

 

 

 

 

 

Note: Change “N” to

 

 

 

 

 

 

Content

Connections

Connections

Size

 

Size

 

 

(Note 5)

 

 

 

MBH

 

 

 

“L” for L.P. gas models.

 

 

 

 

Gallons

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Note 2,7)

(Note 3,7)

 

 

 

 

 

 

 

(Note 4)

 

 

 

 

Min

 

Max

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

KBN080

 

16

 

80

 

72

63

 

 

 

 

 

 

 

 

 

 

 

 

 

0.6

1"

1/2"

3"

 

3"

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

KBN105

 

21

 

105

 

94

82

 

 

 

 

 

 

 

 

 

 

 

 

 

0.7

1"

1/2"

3"

 

3"

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

KBN150

 

30

 

150

 

135

117

 

 

 

 

 

 

 

 

 

 

 

 

 

1.3

1"

1/2"

3"

 

3"

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

KBN210

 

42

 

210

 

190

165

 

 

 

 

 

 

 

 

 

 

 

 

1.7

1"

1/2"

3"

 

3"

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

KBN285

 

57

 

285

 

260

226

 

 

 

 

 

 

 

 

 

 

 

 

 

2.4

1-1/4"

3/4"

4"

 

4"

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Maximum allowed working pressure is located on the rating plate.

 

 

 

 

 

 

 

NOTICE

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Notes:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1. As an Energy Star Partner, Lochinvar has determined that Knight boilers meet the Energy Star guidelines for energy efficiency.

2. The ratings are based on standard test procedures prescribed by the United States Department of Energy.

3. Net I=B=R ratings are based on net installed radiation of sufficient quantity for the requirements of the building and nothing need be added for normal piping and pickup. Ratings are based on a piping and pickup allowance of 1.15.

4. Knight boilers require special gas venting. Use only the vent materials and methods specified in the Knight Installation and Operation Manual.

5.Standard Knight boilers are equipped to operate from sea level to 4,500 feet only with no adjustments. The boiler will

de-rate by 4% for each 1,000 feet above sea level up to 4,500 feet.

6. High altitude Knight boilers are equipped to operate from 3,000 to 12,000 feet only with no field adjustments. The boiler will de-rate by 2% for each 1,000 feet above 3,000

feet. High altitude models are manufactured with a Figure A High Altitude Label Location different control module for altitude operation, but the

operation given in this manual remains the same as the standard boilers. A high altitude label (as shown in FIG. A) is also affixed to the unit.

7.Ratings have been confirmed by the Hydronics Institute, Section of AHRI.

UNIT EQUIPPED FOR

HIGH ALTITUDE

3,000 FT. TO 12,000 FT.

7

Installation & Operation Manual

1Determine boiler location

Installation must comply with:

Local, state, provincial, and national codes, laws, regulations, and ordinances.

National Fuel Gas Code, ANSI Z223.1 – latest edition.

Standard for Controls and Safety Devices for Automatically Fired Boilers, ANSI/ASME CSD-1, when required.

National Electrical Code.

For Canada only: B149.1 Installation Code, CSA C22.1 Canadian Electrical Code Part 1 and any local codes.

NOTICE

The Knight boiler gas manifold and

controls met safe lighting and other

 

 

performance criteria when the boiler

 

underwent tests specified in ANSI Z21.13

 

– latest edition.

Before locating the boiler, check:

1.Check for nearby connection to:

System water piping

Venting connections

Gas supply piping

Electrical power

2.Locate the appliance so that if water connections should leak, water damage will not occur. When such locations cannot be avoided, it is recommended that a suitable drain pan, adequately drained, be installed under the appliance. The pan must not restrict combustion air flow. Under no circumstances is the manufacturer to be held responsible for water damage in connection with this appliance, or any of its components.

3.Check area around the boiler. Remove any combustible materials, gasoline and other flammable liquids.

Failure to keep boiler area clear and free ofWARNING combustible materials, gasoline, and other flammable liquids and vapors can result in severe personal injury, death, or

substantial property damage.

4.The Knight boiler must be installed so that gas control system components are protected from dripping or spraying water or rain during operation or service.

5.If a new boiler will replace an existing boiler, check for and correct system problems, such as:

System leaks causing oxygen corrosion or heat exchanger cracks from hard water deposits.

Incorrectly-sized expansion tank.

Lack of freeze protection in boiler water causing system and boiler to freeze and leak.

WARNING This appliance is certified as an indoor appliance. Do not install the appliance

outdoors or locate where the appliance will be exposed to freezing temperatures or to temperatures that exceed 100°F.

Failure to install the appliance indoors could result in severe personal injury, death, or substantial property damage.

This appliance requires a special ventingWARNING system. The vent connection to the

appliance must be made with the starter CPVC pipe section provided with the appliance. The field provided vent fittings must be cemented to the CPVC pipe section. Use only the vent materials, primer and cement specified in this manual to make the vent connections. Failure to follow this warning could result in fire, personal injury, or death.

Closet and alcove installations

A closet is any room the boiler is installed in which is less than 67 cubic feet for KBN080 and KBN105 models, 86 cubic feet for KBN150 models, 107 cubic feet for KBN210 models, and 120 cubic feet for KBN285 models.

An alcove is any room which meets the criteria for a closet with the exception that it does not have a door.

Example: Room dimensions = 4 feet long, 3 feet wide, and 8 foot ceiling = 4 x 3 x 8 = 96 cubic feet. This would be considered a closet for a Knight Boiler.

WARNING

For closet and alcove installations as

 

shown in FIG.’s 1-1 and 1-2, CPVC or

 

stainless steel vent material must be used

 

inside the structure. The ventilating air

 

openings shown in FIG.’s 1-1 and 1-2 are

 

required for this arrangement. Failure to

 

follow this warning could result in fire,

 

personal injury, or death.

Provide clearances:

Clearances from combustible materials

1.Hot water pipes—at least 1" from combustible materials.

2.Vent pipe – at least 1" from combustible materials.

3.See FIG.’s 1-1 and 1-2 on page 9 for other clearance minimums.

Clearances for service access

1.See FIG.’s 1-1 and 1-2 on page 9 for recommended service clearances. If you do not provide the minimum clearances shown, it may not be possible to service the boiler without removing it from the space.

8

Installation & Operation Manual

1Determine boiler location (continued)

Figure 1-1 Closet Installation - Minimum Required Clearances

WARNING For closet installations, CPVC or stainless steel material MUST BE

used in a closet structure due to elevated temperatures. Failure to follow this warning could result in fire, personal injury, or death.

RECOMMENDED SERVICE CLEARANCES:

FRONT

-

24”

TOP

-

24”

LEFT SIDE -

24”

REAR

-

24”

Figure 1-2 Alcove Installation - Minimum Required Clearances

WARNING

For alcove installations, CPVC or stainless steel material MUST BE used in an alcove structure due to elevated temperatures. Failure to follow this warning could result in fire, personal injury, or death.

RECOMMENDED SERVICE CLEARANCES:

FRONT

-

24”

TOP

-

24”

LEFT SIDE -

24”

REAR

-

24”

9

Installation & Operation Manual

1Determine boiler location

Provide air openings to room:

Knight boiler alone in boiler room

1.No air ventilation openings into the boiler room are needed when clearances around the Knight boiler are at least equal to the SERVICE clearances shown in FIG.’s 1-1 and 1-2. For spaces that do NOT supply this clearance, provide two openings as shown in FIG. 1-1. Each opening must provide one square inch free area per 1,000 Btu/hr of boiler input.

Knight boiler in same space with other gas or oilfired appliances

1.Follow the National Fuel Gas Code (U.S.) or CSA B149.1 (Canada) to size/verify size of the combustion/ventilation air openings into the space.

WARNING The space must be provided with combustion/ventilation air openings

correctly sized for all other appliances located in the same space as the Knight boiler.

Do not install the boiler in an attic.

Failure to comply with the above warnings could result in severe personal injury, death, or substantial property damage.

2.Size openings only on the basis of the other appliances in the space. No additional air opening free area is needed for the Knight boiler because it takes its combustion air from outside (direct vent installation).

Flooring and foundation

Flooring

The Knight boiler is approved for installation on combustible flooring, but must never be installed on carpeting.

WARNING Do not install the boiler on carpeting even if foundation is used. Fire can result,

causing severe personal injury, death, or substantial property damage.

If flooding is possible, elevate the boiler sufficiently to prevent water from reaching the boiler.

10

Residential garage installation

Precautions

Take the following precautions when installing the appliance in a residential garage. If the appliance is located in a residential garage, it should be installed in compliance with the latest edition of the National Fuel Gas Code, ANSI Z223.1 and/or CAN/CGA-B149 Installation Code.

Appliances located in residential garages and in adjacent spaces that open to the garage and are not part of the living space of a dwelling shall be installed so that all burners and burner ignition devices are located not less than 18 inches (46 cm) above the floor.

The appliance shall be located or protected so that it is not subject to physical damage by a moving vehicle.

Vent and air piping

The Knight boiler requires a special vent system, designed for pressurized venting.

The boiler is to be used for either direct vent installation or for installation using indoor combustion air. When room air is considered, see Section 3, General Venting. Note prevention of combustion air contamination below when considering vent/air termination.

Vent and air must terminate near one another and may be vented vertically through the roof or out a side wall, unless otherwise specified. You may use any of the vent/air piping methods covered in this manual. Do not attempt to install the Knight boiler using any other means.

Be sure to locate the boiler such that the vent and air piping can be routed through the building and properly terminated. The vent/air piping lengths, routing and termination method must all comply with the methods and limits given in this manual.

Prevent combustion air contamination

Install air inlet piping for the Knight boiler as described in this manual. Do not terminate vent/air in locations that can allow contamination of combustion air. Refer to Table 1A, page 11 for products and areas which may cause contaminated combustion air.

WARNING You must pipe combustion air to the boiler air intake. Ensure that the

combustion air will not contain any of the contaminants in Table 1A, page 11. Contaminated combustion air will damage the boiler, resulting in possible severe personal injury, death or substantial property damage. Do not pipe combustion air near a swimming pool, for example. Also, avoid areas subject to exhaust fumes from laundry facilities. These areas will always contain contaminants.

Installation & Operation Manual

1Determine boiler location (continued)

When using an existing vent system to install a new boiler:

WARNING Failure to follow all instructions can result in flue gas spillage and carbon monoxide

emissions, causing severe personal injury or death.

Check the following venting components before installing:

Material - For materials listed for use with this appliance, see Section 3 - General Venting, Table 3A. For stainless steel venting, an adapter of the same manufacturer (Table 3B) must be used at the flue collar connection.

Size - To ensure proper pipe size is in place, see Table 3C. Check to see that this size is used throughout the vent system.

Manufacturer - For a stainless steel application, you must use only the listed manufacturers and their type product listed in Table 3A for CAT IV positive pressure venting with flue producing condensate.

Supports - Non-combustible supports must be in place allowing a minimum 1/4" rise per foot. The supports should adequately prevent sagging and vertical slippage, by distributing the vent system weight. For additional information, consult the vent manufacturer’s instructions for installation.

Terminations - Carefully review Sections 3 through 5 to ensure requirements for the location of the vent and air terminations are met and orientation of these fit the appropriate image from the Sidewall or Vertical options listed in the General Venting Section. For stainless steel vent, only use terminations listed in Table 3B for the manufacturer of the installed vent.

Seal - With prior requirements met, the system should be tested to the procedure listed in parts (c) through (f) of the Removal of an Existing Boiler Section on page 12.

With stainless steel vent, seal and connect all pipe and components as specified by the vent manufacturer used; with PVC/CPVC vent, see the Installing Vent or Air Piping Section on page 16.

If any of these conditions are not met, theWARNING existing system must be updated or

replaced for that concern. Failure to follow all instructions can result in flue gas spillage and carbon monoxide emissions, causing severe personal injury or death.

Table 1A Corrosive Contaminants and Sources

Products to avoid:

Spray cans containing chloro/fluorocarbons

Permanent wave solutions

Chlorinated waxes/cleaners

Chlorine-based swimming pool chemicals

Calcium chloride used for thawing

Sodium chloride used for water softening

Refrigerant leaks

Paint or varnish removers

Hydrochloric acid/muriatic acid

Cements and glues

Antistatic fabric softeners used in clothes dryers

Chlorine-type bleaches, detergents, and cleaning solvents found in household laundry rooms

Adhesives used to fasten building products and other similar products

Areas likely to have contaminants

Dry cleaning/laundry areas and establishments

Swimming pools

Metal fabrication plants

Beauty shops

Refrigeration repair shops

Photo processing plants

Auto body shops

Plastic manufacturing plants

Furniture refinishing areas and establishments

New building construction

Remodeling areas

Garages with workshops

11

Installation & Operation Manual

1Determine boiler location

When removing a boiler from existing common vent system:

DANGER

Do not install the Knight boiler into a

 

common vent with any other appliance.

 

This will cause flue gas spillage or

 

appliance malfunction, resulting in

 

possible severe personal injury, death, or

 

substantial property damage.

 

Failure to follow all instructions can result

WARNING

 

in flue gas spillage and carbon monoxide

 

emissions, causing severe personal injury

 

or death.

At the time of removal of an existing boiler, the following steps shall be followed with each appliance remaining connected to the common venting system placed in operation, while the other appliances remaining connected to the common venting system are not in operation.

a.Seal any unused openings in the common venting system.

b.Visually inspect the venting system for proper size and horizontal pitch and determine there is no blockage or restriction, leakage, corrosion, or other deficiencies, which could cause an unsafe condition.

c.Test vent system – Insofar as is practical, close all building doors and windows and all doors between the space in which the appliances remaining connected to the common venting system are located and other spaces of the building. Turn on clothes dryers and any appliance not connected to the common venting system. Turn on any exhaust fans, such as range hoods and bathroom exhausts, so they will operate at maximum speed. Do not operate a summer exhaust fan. Close fireplace dampers.

d.Place in operation the appliance being inspected. Follow the lighting instructions. Adjust thermostat so appliance will operate continuously.

e.Test for spillage at the draft hood relief opening after 5 minutes of main burner operation. Use the flame of a match or candle, or smoke from a cigarette, cigar, or pipe.

f.After it has been determined that each appliance remaining connected to the common venting system properly vents when tested as outlined herein, return doors, windows, exhaust fans, fireplace dampers, and any other gas-burning appliance to their previous conditions of use.

g.Any improper operation of the common venting system should be corrected so the installation conforms with the National Fuel Gas Code, ANSI Z223.1/NFPA 54 and/or CAN/CSA B149.1, Natural Gas and Propane Installation Code. When resizing any portion of the common venting system, the common venting system should be resized to approach the minimum size as determined using the appropriate tables in Part 11 of the National Fuel Gas Code, ANSI Z223.1/NFPA and/or CAN/CSA B149.1, Natural Gas and Propane Installation Code.

12

2Prepare boiler

Remove boiler from wood pallet

1.After removing the outer shipping carton from the boiler, remove the parts box.

2.Remove the front door to access the lag bolts in front of the unit (FIG. 2-1).

3.To remove the boiler from the pallet (after removing the front door):

a.Remove the two lag bolts from the wood pallet inside the boiler (FIG. 2-1).

b.Detach the boiler from the lag bolts in the rear of the unit, see FIG. 2-1.

NOTICE

Do not drop the boiler or bump the jacket on the floor or pallet. Damage to the boiler can result.

Figure 2-1 Boiler Mounted on Shipping Pallet

Gas conversions

WARNING For a boiler already installed, you must turn off gas supply, turn off power and

allow boiler to cool before proceeding. You must also completely test the boiler after conversion to verify performance as described under Start-up, Section 10 of this manual. Failure to comply could result in severe personal injury, death, or substantial property damage.

You must install a propane orifice to operate the Knight boiler on propane gas. Verify when installing that the orifice size marking matches boiler size (Table 2A).

1.Remove the top and front access covers from the unit (no tools required for removal).

2.Remove the three screws securing the gas valve to the venturi (FIG. 2-2).

3.Locate the propane orifice disk from the conversion kit bag. Verify that the stamping on the orifice disk matches the boiler size (see Table 2A).

Place the orifice into the black rubber grommet in the side of the gas valve and secure in the valve (FIG. 2-2).

4.Reposition the gas valve against the venturi and replace the screws (FIG. 2-2) securing the valve to the venturi.

Installation & Operation Manual

5.After installation is complete, attach the propane conversion label (in the conversion kit bag) next to the boiler rating plate. Attach the LP caution label (in the conversion kit bag) to the left side of the unit in the lower left corner.

6.Replace the top and front access covers.

Table 2A LP Conversion Table

 

 

 

LP Conversion Table

 

Model

 

LP Orifice Stamping

 

80

 

 

 

80

 

105

 

 

105

 

150

 

 

150

 

210

 

 

210 / W150

 

285

 

 

285

 

 

 

After converting to LP, check combustion per

 

WARNING

 

 

 

 

the Start-up procedure in Section 10 of this

 

 

 

manual.

Failure to check and verify

combustion could result in severe personal injury, death, or substantial property damage.

Figure 2-2 Installing Propane Orifice

Leveling the boiler

1.Set the boiler in place and check level.

a)Adjust legs if necessary to level boiler, see FIG. 2-3 below.

Figure 2-3 Leveling Legs on the Boiler

13

Installation & Operation Manual

3General venting

Direct venting options - Sidewall Vent

Figure 3-1 PVC/CPVC Two-Pipe Sidewall Termination - See page 21 for more details

Figure 3-2 Stainless Steel Two-Pipe - See page 22 for more details

Figure 3-3 PVC/CPVC Concentric Sidewall

Termination - See page 25 for more details

14

Installation & Operation Manual

3General venting (continued)

Direct venting options - Vertical Vent

Figure 3-4 PVC/CPVC Two-Pipe Vertical Termination - See page 28 for more details

Figure 3-5 Stainless Steel TwoPipe Vertical Termination - See page 28 for more details

Figure 3-6 PVC/CPVC Concentric Vertical Termination - See page 30 for more details

Direct venting options - Vertical Vent, Sidewall Air

Figure 3-7 PVC/CPVC Vertical Vent, Sidewall Air - See page 20 for more details

Figure 3-8 Stainless Steel Vertical Vent, Sidewall Air - See page 20 for more details

NOTICE Stainless steel vent/air design and terminations will vary slightly by manufacturer.

15

Installation & Operation Manual

3General venting

Install vent and combustion air piping

DANGER The Knight boiler must be vented and supplied with combustion and ventilation

air as described in this section. Ensure the vent and air piping and the combustion air supply comply with these instructions regarding vent system, air system, and combustion air quality. See also Section 1 of this manual.

Inspect finished vent and air piping thoroughly to ensure all are airtight and comply with the instructions provided and with all requirements of applicable codes.

Failure to provide a properly installed vent and air system will cause severe personal injury or death.

PVC/CPVC vent piping materials

WARNING

NOTICE

Use only the materials listed in Table 3A for vent pipe, and fittings. Failure to comply could result in severe personal injury, death, or substantial property damage.

Installation must comply with local requirements and with the National Fuel Gas Code, ANSI Z223.1 for U.S. installations or CSA B149.1 for Canadian installations.

WARNING

NOTICE

For closet and alcove installations, CPVC or stainless steel material MUST BE used in a closet/alcove structure. Failure to follow this warning could result in fire, personal injury, or death.

All PVC vent pipes must be glued, properly supported, and the exhaust must be pitched a minimum of a 1/4 inch per foot back to the boiler (to allow drainage of condensate).

WARNING

16

This appliance requires a special venting system. The vent connection to the appliance must be made with the starter CPVC pipe section provided with the appliance if PVC/CPVC vent is to be used. For stainless steel venting use an adapter from Table 3B (pg. 19) that corresponds with the intended vent manufacturer to be used and discard the CPVC starter piece. The field provided vent fittings must be cemented to the CPVC pipe section using an “All Purpose Cement” suitable for PVC and CPVC pipe. Use only the vent materials, primer, and cement specified in this manual to make the vent connections. Failure to follow this warning could result in fire, personal injury, or death.

Requirements for installation in Canada

1. Installations must be made with a vent pipe system certified to ULC-S636.

IPEX is an approved vent manufacturer in Canada supplying vent material listed to ULC-S636.

2. The first three (3) feet of plastic vent pipe from the appliance flue outlet must be readily accessible for visual inspection.

3. The components of the certified vent system must not be interchanged with other vent systems or unlisted pipe/fittings. For concentric vent installations, the inner vent tube must be replaced with field supplied certifiedvent material to comply with this requirement.

4. The 3" Concentric Vent Kit available from Lochinvar (see Section 4 – Sidewall Termination – Optional Concentric Vent) and the 3" Concentric Vent Kit available from IPEX are both approved for use on the Knight boiler. Both kits are listed to the ULC-S636 standard for use in Canada.

CAUTION Improper installation of PVC or CPVC systems may result in injury or death.

Installing vent and air piping

NOTICE

Use only cleaners, primers, and solvents that are approved for the materials which are joined together.

1.Work from the boiler to vent or air termination. Do not exceed the lengths given in this manual for the air or vent piping.

2.Cut pipe to the required lengths and deburr the inside and outside of the pipe ends.

3.Chamfer outside of each pipe end to ensure even cement distribution when joining.

4.Clean all pipe ends and fittings using a clean dry rag. (Moisture will retard curing and dirt or grease will prevent adhesion.)

5.Dry fit vent or air piping to ensure proper fit up before assembling any joint. The pipe should go a third to two-thirds into the fitting to ensure proper sealing after cement is applied.

Installation & Operation Manual

3 General venting (continued)

6.Priming and Cementing:

a.Handle fittings and pipes carefully to prevent contamination of surfaces.

b.Apply a liberal even coat of primer to the fitting socket.

c.Apply a liberal even coat of primer to the pipe end to approximately 1/2" beyond the socket depth.

d.Apply a second primer coat to the fitting socket.

e.While primer is still wet, apply an even coat of approved cement to the pipe equal to the depth of the fitting socket.

f.While primer is still wet, apply an even coat of approved cement to the fitting socket.

g.Apply a second coat of cement to the pipe.

h.While the cement is still wet, insert the pipe into the fitting, if possible twist the pipe a 1/4 turn as you insert it. NOTE: If voids are present, sufficient cement was not applied and joint could be defective.

i.Wipe excess cement from the joint removing ring or beads as it will needlessly soften the pipe.

Table 3A Vent Pipe, and Fittings

All vent pipe materials and fittings must comply with the following:

Item

 

Material

Standards for installation in:

 

 

 

 

United States

Canada

 

 

 

 

 

PVC schedule 40

ANSI/ASTM D1785

CPVC and PVC venting must be ULC-

 

 

 

 

S636 Certified. IPEX is an approved

 

 

PVC-DWV

ANSI/ASTM D2665

Vent pipe and fittings

 

manufacturer in Canada supplying vent

 

CPVC schedule 40/80

ANSI/ASTM F441

 

 

material listed to ULC-S636.

 

 

 

 

 

 

 

AL29-4C

UL1738

ULC-S636

Pipe cement/primer

 

PVC

ANSI/ASTM D2564

IPEX System 636

 

 

 

Cements & Primers

 

CPVC

ANSI/ASTM F493

 

 

 

 

NOTICE: DO NOT USE CELLULAR (FOAM) CORE PIPE

 

 

 

 

 

Approved Stainless Steel Vent Manufacturers

 

 

 

 

 

 

 

Make

 

Model

ProTech Systems (Simpson Dura-Vent Co.)

 

FasNSeal Vent / FasNSeal Flex* Vent

 

 

 

 

Z-Flex (Nova Flex Group)

 

 

Z-Vent

 

 

 

Heat Fab (Selkirk Corporation)

 

Saf-T Vent

 

 

 

 

 

*Use of FasNSeal Flex smooth inner wall vent is to be used in vertical or near vertical sections only, taking precaution to ensure no sagging occurs of the vent system. Connect to the FasNSeal rigid vent using specially designed adapters and sealing method, see manufacturer’s instructions.

PVC/CPVC air intake/vent connections

1.Combustion Air Intake Connector (FIG.’s 3-9 and 3-10) - Used to provide combustion air directly to the unit from outdoors. A fitting is provided on the unit for final connection. Combustion air piping must be supported per guidelines listed in the National Mechanical Code, Section 305, Table 305.4 or as local codes dictate.

2.Vent Connector (FIG.’s 3-9 and 3-10) - Used to provide a passageway for conveying combustion gases to the outside. A transition fitting is provided on the unit for final connection. Vent piping must be supported per the National Building Code, Section 305, Table 305.4 or as local codes dictate.

Figure 3-9 Near Boiler PVC/CPVC Venting Models Figure 3-10 Near Boiler PVC/CPVC Venting Model 285 80 - 210

AIR

VENT

3” CPVC PIPE SUPPLIED WITH BOILER MUST BE USED FOR VENT CONNECTION

NOTE: CPVC VENT PIPE AND VENT FITTINGS MUST BE USED IN CLOSET AND ALCOVE INSTALLATIONS.

4” CPVC PIPE SUPPLIED WITH BOILER MUST BE USED FOR VENT CONNECTION

NOTE: CPVC VENT PIPE AND VENT FITTINGS MUST BE USED IN CLOSET AND ALCOVE INSTALLATIONS.

17

3General venting

Air inlet pipe materials:

The air inlet pipe(s) must be sealed. Choose acceptable combustion air inlet pipe materials from the following list:

PVC, CPVC or ABS

Dryer Vent or Sealed Flexible Duct (not recommended for rooftop air inlet)

Galvanized steel vent pipe with joints and seams sealed as specified in this section.

Type “B” double-wall vent with joints and seams sealed as specified in this section.

AL29-4C, stainless steel material to be sealed to specification of its manufacturer.

*Plastic pipe may require an adapter (not provided) to transition between the air inlet connection on the appliance and the plastic air inlet pipe.

WARNING Using vent or air intake materials other than those specified, failure to properly seal

all seams and joints or failure to follow vent pipe manufacturer’s instructions can result in personal injury, death or property damage. Mixing of venting materials will void the warranty and certification of the appliance.

NOTICE

The use of double-wall vent or insulated material for the combustion air inlet pipe is recommended in cold climates to prevent the condensation of airborne moisture in the incoming combustion air.

Sealing of Type “B” double-wall vent material or galvanized vent pipe material used for air inlet piping on a sidewall or vertical rooftop Combustion Air Supply System:

a.Seal all joints and seams of the air inlet pipe using either Aluminum Foil Duct Tape meeting UL Standard 723 or 181A-P or a high quality UL Listed silicone sealant such as those manufactured by Dow Corning or General Electric.

b.Do not install seams of vent pipe on the bottom of horizontal runs.

c.Secure all joints with a minimum of three sheet metal screws or pop rivets. Apply Aluminum Foil Duct Tape or silicone sealant to all screws or rivets installed in the vent pipe.

d.Ensure that the air inlet pipes are properly supported.

The PVC, CPVC, or ABS air inlet pipe should be cleaned and sealed with the pipe manufacturer’s recommended solvents and standard commercial pipe cement for the material used. The PVC, CPVC, ABS, Dryer Vent or Flex Duct air inlet pipe should use a silicone sealant to ensure a proper seal at the appliance connection and the air inlet cap connection. Dryer vent or flex duct should use a screw type clamp to seal the vent to the appliance air inlet and the air inlet cap. Proper sealing of the air inlet pipe ensures that combustion air will be free of contaminants and supplied in proper volume.

18

Installation & Operation Manual

When a sidewall or vertical rooftop combustion air supply system is disconnected for any reason, the air inlet pipe must be resealed to ensure that combustion air will be free of contaminants and supplied in proper volume.

DANGER

Failure to

properly seal all joints and

seams as required in the air inlet piping

 

 

 

may result in flue gas recirculation,

 

spillage of flue products and carbon

 

monoxide

emissions causing severe

 

personal injury or death.

Stainless steel vent

This product has been approved for use with stainless steel using the manufacturers listed in Table 3A.

WARNING Use only the materials, vent systems, and terminations listed in Table 3B. DO NOT

mix vent systems of different types or manufacturers, unless listed in this manual. Failure to comply could result in severe personal injury, death, or substantial property damage.

NOTICE

Installations must comply with applicable

national, state, and local codes. Stainless

 

 

steel vent systems must be listed as a

 

UL-1738 approved system for the United

 

States and a ULC-S636 approved system

 

for Canada.

 

Installation of a stainless steel vent system

NOTICE

should adhere to the stainless steel vent

 

 

manufacturer’s installation instructions

 

supplied with the vent system.

 

The installer must use a specific vent

NOTICE

starter adapter at the flue collar

 

 

connection, supplied by the vent

 

manufacturer to adapt to its vent system.

 

See Table 3B for approved vent adapters.

 

Discard CPVC starter piece.

Installation & Operation Manual

3General venting (continued)

Stainless

steel

air

intake/vent

Figure 3-11 Near Boiler Stainless Steel Venting Model 285

connections

 

 

 

 

1. Combustion Air Intake Connector (FIG. 3-11) - Used to provide combustion air directly to the unit from outdoors. A fitting is provided on the unit for final connection. Combustion air piping must be supported per guidelines listed in the National Mechanical Code, Section 305, Table 305.4 or as local codes dictate.

2. Vent Connector (FIG. 3-11) - Used to provide a passageway for conveying combustion gases to the outside. A transition fitting is provided on the unit for final connection. Vent piping must be supported per the National Building Code, Section 305, Table 305.4 or as local codes dictate.

 

 

 

 

 

 

 

 

 

 

 

3" S.S. ADAPTER

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3" S.S. INTERMEDIATE

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(FOR SAF-T VENT ONLY)

 

Table 3B Approved Stainless Steel Terminations and Adapters

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

ProTech

 

Heat Fab

 

 

 

 

 

Z Flex

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

FasNSeal

 

Saf-T Vent

 

 

 

 

 

Z-Vent

 

Model

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Boiler

Flue

Intake

Boiler

Intermediate

Flue

Intake

Boiler

Flue

 

Intake Air

 

 

 

Air

Air

 

 

Adapter

Termination

Adapter

Adapter

Termination

Adapter

Termination

 

Termination

 

Termination

Termination

 

80 - 210

300715

FSBS3

303889

KB80210

9353BUREZ-1*

9392

9314TERM

2SVSLA03

2SVSTP03

 

2SVSTEX0390

FSRC3(R.C)

5300CI

2SVSRCX03

 

285

F303759

FSBS4

FSAIH04

KB285600

9454BUREZ-1*

9492

9414TERM

2SVSLA04

2SVSTP04

 

2SVSTEX0490

FSRC4(R.C.)

303888

5400CI

2SVSRCX04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

* = This adapter must be used in addition to the boiler adapter for Saf-T vent pipe as shown in FIG. 3-11, unless approved vent other than standard diameter is used. Consult a Heat Fab representative for questions.

The Knight boiler uses model specific combustion air intake and vent piping sizes as detailed in Table 3C below.

Table 3C Air Intake/Vent Piping Sizes

 

Model

 

Air Intake

Vent

 

 

 

 

 

 

80 - 210

 

3 inches

3 inches

 

 

 

 

 

 

285

 

4 inches

4 inches

 

 

 

 

 

 

 

Increasing or decreasing combustion air

 

NOTICE

 

or vent piping is not authorized.

 

 

Minimum / Maximum allowable combustion air and vent piping lengths are as follows:

Combustion Air = 12 equivalent feet minimum / 100 equivalent feet maximum

Vent = 12 equivalent feet minimum / 100 equivalent feet maximum

When determining equivalent combustion air and vent length, add 5 feet for each 90° elbow and 3 feet for each 45° elbow.

EXAMPLE: 20 feet of PVC pipe + (4) 90° elbows + (2) 45° elbows + (1) concentric vent kit (CVK3003) = 49 equivalent feet of piping.

NOTICE

The appliance output rating will reduce by

up to 1.5% for each 25 feet of vent length.

 

19

Installation & Operation Manual

3General venting

Table 3D Concentric Vent Kit Equivalent Vent Lengths

Model

Kit Number

Equivalent Vent

Length

 

 

80 - 210

CVK3003

3 feet

 

 

 

285

CVK3007

3 feet

 

 

 

Removing from existing vent

Follow the instructions in Section 1, page 12 of this manual when removing a boiler from an existing vent system.

Vent and air piping

Vent and air system:

NOTICE

Installation must comply with local requirements and with the National Fuel Gas Code, ANSI Z223.1 for U.S. installations or CSA B149.1 for Canadian installations.

You must also install air piping from outside to the boiler air intake adapter. The resultant installation is direct vent (sealed combustion).

You may use any of the vent/air piping methods covered in this manual. Do not attempt to install the Knight boiler using any other means.

WARNING

DO NOT mix components from different

 

systems. The vent system could fail, causing

 

leakage of flue products into the living

 

space. Use only approved stainless steel,

 

PVC or CPVC pipe and fittings. For

 

PVC/CPVC use with primer and cement

 

specifically designed for the material used.

Vent, air piping and termination:

The Knight boiler vent and air piping can be installed through the roof or through a sidewall. Follow the procedures in this manual for the method chosen. Refer to the information in this manual to determine acceptable vent and air piping length.

Optional room air

NOTICE

Optional room air is intended for commercial applications. Combustion air piping to the outside is recommended for residential applications.

Commercial applications utilizing the Knight boiler may be installed with a single pipe carrying the flue products to the outside while using combustion air from the equipment room. In order to use the room air venting option the following conditions and considerations must be followed.

The unit MUST be installed with the appropriate room air kit (Table 3E).

The equipment room MUST be provided with properly sized openings to assure adequate combustion air. Please refer to instructions provided with the room air kit.

20

There will be a noticeable increase in the noise level during normal operation from the inlet air opening.

Using the room air kit makes the unit vulnerable to combustion air contamination from within the building. Please review Section 1, Prevent Combustion Air Contamination, to ensure proper installation.

Vent system and terminations must comply with the standard venting instructions set forth in this manual.

When utilizing the single pipe method, WARNING provisions for combustion and ventilation air must be in accordance with Air for Combustion and Ventilation, of the latest edition of the National Fuel Gas Code, ANSI Z223.1, in Canada, the latest edition of CGA Standard B149 Installation Code for Gas Burning Appliances and Equipment, or applicable provisions of the local building

codes.

Table 3E Optional Room Air Kit

Model

Kit Number

80 - 210

KIT30052

 

 

285

KIT30053

 

 

Air contamination

Pool and laundry products and common household and hobby products often contain fluorine or chlorine compounds. When these chemicals pass through the boiler, they can form strong acids. The acid can eat through the boiler wall, causing serious damage and presenting a possible threat of flue gas spillage or boiler water leakage into the building.

Please read the information given in Table 1A, page 11, listing contaminants and areas likely to contain them. If contaminating chemicals will be present near the location of the boiler combustion air inlet, have your installer pipe the boiler combustion air and vent to another location, per this manual.

WARNING

If the boiler combustion air inlet is located

 

in a laundry room or pool facility, for

 

example, these areas will always contain

 

hazardous contaminants.

 

To prevent the potential of severe personal

WARNING

 

injury or death, check for areas and products

 

listed in Table 1A, page 11 before installing

 

the boiler or air inlet piping.

 

If contaminants are found, you MUST:

 

• Remove contaminants permanently.

 

—OR—

 

• Relocate air inlet and vent terminations

 

to other areas.

Installation & Operation Manual

4Sidewall direct venting

Vent/air termination – sidewall

WARNING

Follow

instructions

below

when

 

determining vent location to avoid

 

possibility of severe personal injury, death,

 

or substantial property damage.

 

 

A gas vent extending through an exterior

WARNING

 

wall shall not terminate adjacent to a wall or

 

below building extensions such as eaves,

 

parapets, balconies, or decks. Failure to

 

comply could result in severe personal

 

injury, death, or substantial property

 

damage.

 

 

 

WARNING Do not connect any other appliance to the vent pipe or multiple boilers to a common

vent pipe. Failure to comply could result in severe personal injury, death, or substantial property damage.

NOTICE

Installation must comply with local

requirements and with the National Fuel

 

 

 

Gas Code, ANSI Z223.1 for U.S.

 

installations or CSA B149.1 for Canadian

 

installations.

Determine location

Locate the vent/air terminations using the following guidelines:

1.The total length of piping for vent or air must not exceed the limits given in the General Venting Section on page 19 of this manual.

2.You must consider the surroundings when terminating the vent and air:

a.Position the vent termination where vapors will not damage nearby shrubs, plants or air conditioning equipment or be objectionable.

b.The flue products will form a noticeable plume as they condense in cold air. Avoid areas where the plume could obstruct window views.

c.Prevailing winds could cause freezing of condensate and water/ice buildup where flue products impinge on building surfaces or plants.

d.Avoid possibility of accidental contact of flue products with people or pets.

e.Do not locate the terminations where wind eddies could affect performance or cause recirculation, such as inside building corners, near adjacent buildings or surfaces, window wells, stairwells, alcoves, courtyards, or other recessed areas.

WARNING Sidewall vent and air inlet terminations must terminate in the same pressure zone.

f.Do not terminate above any door or window. Condensate can freeze, causing ice formations.

g.Locate or guard vent to prevent condensate damage to exterior finishes.

Figure 4-1A PVC/CPVC Sidewall Termination of Air

and Vent

TO BOILER

INTAKE AIR

CONNECTION

FROM BOILER

VENT PIPE

CONNECTION

12"

POSSIBLE ORIENTATIONS

MIN

TO

OVER-

HANG

 

VENT / AIR

 

 

TERMINATION

 

 

 

12"

 

 

MIN

 

 

GRADE OR

 

 

SNOW LINE

Table 4A Sidewall Vent Kits

 

Model

Kit Number

Vent Size

80 - 210

KIT30045

3 inch vent

285

KIT30046

4 inch vent

If using the alternate sidewall termination:

3.The air piping must terminate in a down-turned elbow as shown in FIG. 4-1B. This arrangement avoids recirculation of flue products into the combustion air stream.

4.The vent piping must terminate in an elbow pointed outward or away from the air inlet, as shown in FIG. 4-1B.

WARNING Do not exceed the maximum lengths of the outside vent piping shown in FIG. 4-1B.

Excessive length exposed to the outside could cause freezing of condensate in the vent pipe, resulting in potential boiler shutdown.

Figure 4-1B Alternate PVC/CPVC Sidewall Termination of Air and Vent w/Field Supplied Fittings

21

4Sidewall direct venting

Vent/air termination – sidewall

Figure 4-1C Alternate PVC/CPVC Venting Arrangement (if Space Allows) w/Field Supplied Fittings

TO BOILER

INTAKE AIR COUPLING

CONNECTION

12” MIN

15” MAX FROM BOILER

VENT PIPE CONNECTION

BIRD SCREEN

12”

MIN

BIRD

SCREEN

ALTERNATE VENTING ARRANGEMENT

(IF SPACE PERMITS)

Figure 4-1D Alternate PVC/CPVC/SS Venting Arrangement - Typical Stainless Steel Sidewall Termination of Air and Vent w/Field Supplied Fittings, Utilizing 90° Elbow Intake

TO BOILER

INTAKE AIR 12" MIN CONNECTION

15" MAX

FROM BOILER

VENT PIPE

CONNECTION

12" MIN

BIRD SCREEN

MODELS 80 - 285

Figure 4-1E Alternate SS Venting Arrangement - Typical Stainless Steel Sidewall Termination of Air and Vent w/Field Supplied Fittings, Utilizing FasNSeal’s Hood Intake

BIRD SCREEN

TO BOILER

INTAKE AIR

CONNECTION

12" (305 MM) MIN 15" (381 MM) MAX

FROM BOILER

VENT PIPE

CONNECTION

12" (305 MM) MIN

MODEL 285 WITH FASNSEAL ONLY

22

Installation & Operation Manual

5.Maintain clearances as shown in FIG.’s 4-1A thru 4-3B, pages 21 and 23. Also maintain the following:

a.Vent must terminate:

At least 6 feet from adjacent walls.

No closer than 12 inches below roof overhang.

At least 7 feet above any public walkway.

At least 3 feet above any forced air intake within 10 feet.

No closer than 12 inches below or horizontally from any door or window or any other gravity air inlet.

b.Air inlet must terminate at least 12 inches above grade or snow line; at least 12 inches below the vent termination; and the vent pipe must not extend more than 24 inches vertically outside the building as shown in FIG. 4-1B.

c.Do not terminate closer than 4 feet horizontally from any electric meter, gas meter, regulator, relief valve, or other equipment. Never terminate above or below any of these within 4 feet horizontally.

6.Locate terminations so they are not likely to be damaged by foreign objects, such as stones or balls, or subject to buildup of leaves or sediment.

Figure 4-2A Clearance to Gravity Air Inlets

12"

MIN.

VENT / AIR

TERMINATION

12" MIN.

12" MIN.

Figure 4-2B Alternate Clearance to Gravity Air Inlets w/Field Supplied Fittings

12”

MIN.

BIRD

SCREEN (TYPICAL)

12” MIN.

12” MIN.

Installation & Operation Manual

4Sidewall direct venting (continued)

Figure 4-3A Clearance to Forced Air Inlets

IF LESS

THAN 10’

VENT / AIR

TERMINATION 36"

MIN.

FORCED AIR

INLET

7' MIN. ABOVE ANY PUBLIC WALKWAY

4.Assemble the vent cap to the vent plate (see FIG. 4-4A). Insert the stainless steel screws into the vent cap screw hole openings and securely attach the vent cap to the vent plate.

5.Seal all wall cavities.

Figure 4-4A Sidewall Termination Assembly

 

AIR PIPING

VENT PIPING

 

 

VENT PLATE

WALL PLATE

VENT CAP

 

GALVANIZED

 

THIMBLE

 

Figure 4-3B Alternate Clearance to Forced Air Inlets w/Field Supplied Fittings

IF LESS

THAN 10’

36”

MIN.

FORCED AIR

INLET

BIRD

SCREEN

(TYPICAL)

7’ MIN. ABOVE ANY

PUBLIC WALKWAY

Prepare wall penetrations

1.Use the factory supplied wall plate as a template to locate the vent and air intake holes and mounting holes.

Air pipe penetration:

a.Cut a hole for the air pipe. Size the air pipe hole as close as desired to the air pipe outside diameter.

Vent pipe penetration:

a.Cut a hole for the vent pipe. For either combustible or noncombustible construction, size the vent pipe hole with at least a 1/2 inch clearance around the vent pipe outer diameter:

4½ inch hole for 3 inch vent pipe

5½ inch hole for 4 inch vent pipe

Drill 3/16" diameter holes for inserting the plastic anchors into the wall.

2.Install the vent and air intake piping through the wall into the vent plate openings. Seal all gaps between the pipes and wall. Use RTV silicone sealant to seal the air pipe. Use the cement/primer listed in Table 3A on page 17 to seal the vent pipe.

3.Mount and secure the vent plate to the wall using stainless steel screws. Seal around the plate to the wall assuring no air gaps.

Prepare wall penetrations (Alternate - Field Supplied Option)

1.Air pipe penetration:

a.Cut a hole for the air pipe. Size the air pipe hole as close as desired to the air pipe outside diameter.

2.Vent pipe penetration:

a.Cut a hole for the vent pipe. For either combustible or noncombustible construction, size the vent pipe hole with at least a 1/2 inch clearance around the vent pipe outer diameter:

4½ inch hole for 3 inch vent pipe

5½ inch hole for 4 inch vent pipe

b.Insert a galvanized metal thimble in the vent pipe hole as shown in FIG. 4-4B.

3.Use a sidewall termination plate as a template for correct location of hole centers.

4.Follow all local codes for isolation of vent pipe when passing through floors or walls.

5.Seal exterior openings thoroughly with exterior caulk.

Figure 4-4B Alternate Sidewall Termination Assembly w/Field Supplied Fittings

ELBOW

AIR PIPING

VENT PIPING

BIRD SCREEN

GALVANIZED

 

ELBOW

THIMBLE

 

 

 

 

SIDEWALL

BIRD SCREEN

 

 

 

TERMINATION PLATE

 

23

Loading...
+ 53 hidden pages