Nortel Networks 1000M User Manual

5 (1)

Nortel Communication Server 1000

Nortel Communication Server 1000 Release 5.5

Communication Server 1000M and

Meridian 1

Large System Installation and Commissioning

Document Number: NN43021-310

Document Release: Standard 02.01

Date: December 2007

Copyright © 2007, Nortel Networks. All rights reserved.

Sourced in Canada

LEGAL NOTICE While the information in this document is believed to be accurate and reliable, except as otherwise expressly agreed to in writing. NORTEL PROVIDES THIS DOCUMENT "AS IS" WITHOUT WARRANTY OR CONDITION OF ANY KIND, EITHER EXPRESS OR IMPLIED. The information and/or products described in this document are subject to change without notice.

Nortel, Nortel (Logo), the Globemark, SL-1, Meridian 1, and Succession are trademarks of Nortel Networks. All other trademarks are the property of their respective owners.

10

Page 3 of 456

Contents

Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

3

New in this release . . . . . . . . . . . . . . . . . . . . . . . . .

11

Features . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

11

Other . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

11

List of Procedures . . . . . . . . . . . . . . . . . . . . . . . . . .

13

How to get help . . . . . . . . . . . . . . . . . . . . . . . . . . . .

19

Getting help from the Nortel Web site . . . . . . . . . . . . . . . . . . . . . . . . .

19

Getting help over the telephone from a Nortel Solutions Center . . . . .

19

Getting help from a specialist by using an Express Routing Code . . . .

20

Getting help through a Nortel distributor or reseller .. . . . . . . . . . . . . .

20

Finding the latest updates

 

on the Nortel web site . . . . . . . . . . . . . . . . . . . . . . .

21

System information . . . . . . . . . . . . . . . . . . . . . . . . .

23

Subject .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

23

Applicable systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

24

Intended audience . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

25

Conventions .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

26

NTP feedback . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

26

Related information .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

27

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 4 of 456 Contents

 

Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

31

Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

31

Overview .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

31

Summary of procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

33

Preparing for installation . . . . . . . . . . . . . . . . . . . .

37

Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

37

Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

37

System equipment – UEMs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

38

System options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

45

Cable routing guidelines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

54

Equipment handling precautions . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

58

Preparing the equipment for installation .. . . . . . . . . . . . . . . . . . . . . . .

62

Placing the fourth module on a column . . . . . . . .

65

Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

65

Overview .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

65

Placing the fourth module on a column . . . . . . . . . . . . . . . . . . . . . . . .

65

Positioning and leveling equipment . . . . . . . . . . .

71

Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

71

Positioning and leveling the equipment . . . . . . . . . . . . . . . . . . . . . . . .

71

Installing AC power . . . . . . . . . . . . . . . . . . . . . . . .

77

Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

77

AC-powered systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

77

Safety ground/protective earth and logic return wiring . . . . . . . . . . . .

78

Installing safety ground/protective earth and logic return wiring .. . . .

82

Installing UPS ground cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

85

Installing overhead cable tray kits . . . . . . . . . . . .

89

Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

89

NN43021-310 Standard 02.01 December 2007

 

Contents Page 5 of 456

Installing overhead cable tray kits .. . . . . . . . . . .

. . . . . . . . . . . . . . . . . 89

Installing DC power . . . . . . . . . . . .

. . . . . . . . . . . . . 93

Contents .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . 93

DC-powered systems .. . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . 93

Candeo DC power systems . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . 94

Planning and designating a

Main Distribution Frame . . . . . . . . . . . . . . . . . . . . . 133

Contents .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 About terminations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 Installation and designation .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 Terminal block requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 134 Installing the BIX cross-connect terminal .. . . . . . . . . . . . . . . . . . . . . . 134 Installing the Krone cross-connect system (UK) . . . . . . . . . . . . . . . . . 138

Installing Power Failure Transfer Units . . . . . . . . . 145

Contents .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 145 PFTU configurations .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 145 Installing a PFTU . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 148 Connecting trunks and telephones .. . . . . . . . . . . . . . . . . . . . . . . . . . . . 149 Installing QUA6 PFTUs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 150

Configuring the system monitor . . . . . . . . . . . . . . 151

Contents .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151 System monitor cabling .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151 Configuring the System Monitor .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 153 Cabling the System Monitor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 157 Alarm interfacing to Candeo .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 165 Configuring the alarm ports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 168 Customizing alarms .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 169

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 6 of 456 Contents

 

Connecting a system terminal or modem . . . . . .

171

Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

171

About the system terminal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

171

Connecting a terminal .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

173

Connecting a terminal to a COM port . . . . . . . . . . . . . . . . . . . . . . . . .

174

Connecting a switch box and terminal to

 

COM1 and COM2 ports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

175

Connecting a switch box and terminal to

 

SDI and COM1 ports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

177

Connecting a modem . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

178

Configuring a modem . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

180

Connecting a modem to an SDI port . . . . . . . . . . . . . . . . . . . . . . . . . .

181

Connecting a modem to switch box, COM2 ports, SDI ports . . . . . . .

183

Cabling Common Equipment in a

 

Single Group system . . . . . . . . . . . . . . . . . . . . . . .

187

Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

187

Cabling guidelines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

187

Core/Net module .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

189

Cabling the Core side . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

193

Cabling the I/O panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

195

Cabling the Network side . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

197

Configuring and cabling the Clock Controllers . . . . . . . . . . . . . . . . . .

198

Network Group 0: Shelf 0 to Shelf 1 . . . . . . . . . . . . . . . . . . . . . . . . . .

199

Connecting the 3PE faceplates in the Core/Net modules . . . . . . . . . . .

199

Inspecting CNI to 3PE factory installed cables . . . . . . . . . . . . . . . . . .

200

Connecting the Core/Net backplanes . . . . . . . . . . . . . . . . . . . . . . . . . .

202

Optioning the System Utility Card . . . . . . . . . . . . . . . . . . . . . . . . . . . .

203

Connecting Core modules to a LAN .. . . . . . . . . . . . . . . . . . . . . . . . . .

204

NN43021-310 Standard 02.01 December 2007

Contents Page 7 of 456

Cabling Common Equipment in a

Multi Group system . . . . . . . . . . . . . . . . . . . . . . . . . 207

Contents .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 207 Cabling guidelines .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 207 Core/Net module . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 209 Cabling the Core/Net module backplane . . . . . . . . . . . . . . . . . . . . . . . 212 Disconnecting cables from the Core/Net module backplane . . . . . . . . 213 Optioning the System Utility Card . . . . . . . . . . . . . . . . . . . . . . . . . . . . 215 Core shelf cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 216 Installing the CP PIV to I/O panel cables . . . . . . . . . . . . . . . . . . . . . . . 220 Connecting the Core module to a LAN .. . . . . . . . . . . . . . . . . . . . . . . . 223 Cabling a Dual Ring Fiber Network . . . . . . . . . . . . . . . . . . . . . . . . . . . 224 FIJI card cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 228 Installing the Shelf 0 fiber optic ring (ascending) .. . . . . . . . . . . . . . . . 231 Installing the Shelf 1 fiber optic ring (descending) .. . . . . . . . . . . . . . . 232 FIJI to FIJI cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 234 Connecting the Clock Controller cables . . . . . . . . . . . . . . . . . . . . . . . . 235

Cabling network modules and loops . . . . . . . . . . . 239

Contents .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 239 Network-to-network cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 239 Network module connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 240 Network Group 0: Shelf 0 to Shelf 1 .. . . . . . . . . . . . . . . . . . . . . . . . . . 240 Connecting the 3PE faceplates in the Core/Net modules . . . . . . . . . . . 240 Connecting the Core/Net backplanes . . . . . . . . . . . . . . . . . . . . . . . . . . 241 Connecting Groups 1 through 7: Shelf 0 to Shelf 1 . . . . . . . . . . . . . . . 242 Connecting the Network modules to the Core/Net modules .. . . . . . . . 245 Connecting the 3PE cables to the 3PE fanout panels . . . . . . . . . . . . . . 250 Cabling a Superloop Network Card – single column . . . . . . . . . . . . . . 252 Cabling a Superloop Network Card – multiple columns . . . . . . . . . . . 256

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 8 of 456 Contents

 

Cabling lines and trunks . . . . . . . . . . . . . . . . . . . .

261

Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

261

Overview .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

261

Cabling an IPE Module or Media Gateway . . . . . . . . . . . . . . . . . . . . .

263

Connecting lines and trunks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

266

Powering up the system and initial loading . . . . .

299

Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

299

Overview .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

299

Installing the Security Device .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

299

Preparing to power up – AC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

302

Connecting the AC power source . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

302

Turning AC power ON . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

303

Resetting the main circuit breakers (AC power) . . . . . . . . . . . . . . . . .

304

Preparing to power up – DC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

306

Turning DC power ON . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

306

Installing software .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

308

Testing Core/Net 1 and Core/Net 0 . . . . . . . . . . . . . . . . . . . . . . . . . . .

330

Performing acceptance tests . . . . . . . . . . . . . . . .

335

Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

335

Acceptance tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

335

Testing the module power supply .. . . . . . . . . . . . . . . . . . . . . . . . . . . .

336

Testing the blower unit and thermal sensor . . . . . . . . . . . . . . . . . . . . .

337

Testing the sysload . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

339

Testing the system terminal and system monitor . . . . . . . . . . . . . . . . .

340

Testing the PFTU . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

341

Installing earthquake bracing . . . . . . . . . . . . . . . .

343

Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

343

Seismic-approved applications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

343

NN43021-310 Standard 02.01 December 2007

Contents Page 9 of 456

Installing seismic bracing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 344 Drilling concrete floors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 347 Installing Kit A and Kit B anchor plates .. . . . . . . . . . . . . . . . . . . . . . . 349 Installing earthquake rods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 351 Positioning and leveling the system . . . . . . . . . . . . . . . . . . . . . . . . . . . 357 Installing non-seismic bracing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 358 Installing a non-seismic anchor kit . . . . . . . . . . . . . . . . . . . . . . . . . . . . 359

Adding a module to a column . . . . . . . . . . . . . . . . 363

Contents .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 363 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 363 Adding a module to the base of a column .. . . . . . . . . . . . . . . . . . . . . . 364 Adding a module between two other modules . . . . . . . . . . . . . . . . . . . 370 Adding a module to the top of a column .. . . . . . . . . . . . . . . . . . . . . . . 374

Installing a Signaling Server . . . . . . . . . . . . . . . . . 383

Contents .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 383 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 384 Readiness checklist . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 385 Installing the CP PM Signaling Server hardware . . . . . . . . . . . . . . . . . 387 Connections .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 389 Installing the Signaling Server software . . . . . . . . . . . . . . . . . . . . . . . . 399 First boot of a new Nortel CP PM Signaling Server .. . . . . . . . . . . . . . 426 Unpacking Help files for Virtual Terminal Emulator . . . . . . . . . . . . . . 445 Logging in to the Signaling Server . . . . . . . . . . . . . . . . . . . . . . . . . . . . 445 Verifying a successful configuration .. . . . . . . . . . . . . . . . . . . . . . . . . . 447 Testing the Leader Signaling Server . . . . . . . . . . . . . . . . . . . . . . . . . . . 447

Index . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 449

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 10 of 456 Contents

NN43021-310 Standard 02.01 December 2007

12

Page 11 of 456

New in this release

Features

There are no new features in this NTP for CS 1000 Release 5.5.

Other

Revision History

December 2007

Standard 02.01. This document is up-issued for Communication Server 1000

Release 5.5.

July 2007

Standard 01.03. This document is up-issued for Communication Server 1000

Release 5.0.

July 2007

Standard 01.02. This document is up-issued for Communication Server 1000

Release 5.0.

May 2007

Standard 01.01. This document is up-issued for Communication Server 1000 Release 5.0. This document contains information previously contained in the following legacy document, now retired: Communication Server 1000M and Meridian 1: Large System Installation and Configuration (553-3021-210).

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 12 of 456 New in this release

April 2006

Standard 4.00. This document is up-issued with corrections from CR Q01311083. The corrections appear in the “Configuring the System Monitor' section (page 153 to page 157).

August 2005

Standard 3.00. This document is up-issued to support Communication

Server 1000 Release 4.5.

September 2004

Standard 2.00. This document is up-issued to support Communication

Server 1000 Release 4.0.

October 2003

Standard 1.00. This document is a new NTP for Succession 3.0. It was created to support a restructuring of the Documentation Library, which resulted in the merging of multiple legacy NTPs. This new document consolidates information previously contained in the following legacy documents, now retired:

Cabling Guide (553-3001-109)

System Installation Procedures (553-3001-210)

NN43021-310 Standard 02.01 December 2007

18

Page 13 of 456

List of Procedures

Procedure 1

Preparing the equipment for installation . . . . . . . . . . . . . . . . . . . . . 62

Procedure 2

Placing the fourth module on a column . . . . . . . . . . . . . . . . . . . . . . 66

Procedure 3

Positioning and leveling the equipment . . . . . . . . . . . . . . . . . . . . . . 71

Procedure 4

Installing safety ground/protective earth and logic return wiring . 82

Procedure 5

 

Installing the UPS ground cabling . . . . . . . . . . . . . . . . . . . . . . . . . .

86

Procedure 6

Installing the overhead cable tray kits . . . . . . . . . . . . . . . . . . . . . . . 90

Procedure 7

Installing and connecting the power plant frame ground leads . . . 113

Procedure 8

Installing safety ground/protective earth wiring . . . . . . . . . . . . . . . 123

Procedure 9

Connecting power from the power plant to the PDU (NT4N49AA) . 125

Procedure 10

Connecting UK power to the Four-Feed PDU . . . . . . . . . . . . . . . . . 129

Procedure 11

Installing the BIX cross-connect terminal . . . . . . . . . . . . . . . . . . . . 135

Procedure 12

Installing the Krone Test Jack Frame (UK) . . . . . . . . . . . . . . . . . . . . 138

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 14 of 456

Procedure 13

 

Installing a PFTU . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

148

Procedure 14

Connecting trunks and telephones . . . . . . . . . . . . . . . . . . . . . . . . . 149

Procedure 15

Configuring the System Monitor (NT8D22) . . . . . . . . . . . . . . . . . . . 153

Procedure 16

Cabling the System Monitor (NT8D22) . . . . . . . . . . . . . . . . . . . . . . . 158

Procedure 17

 

Configuring the alarm ports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

169

Procedure 18

Connecting a terminal to a COM port . . . . . . . . . . . . . . . . . . . . . . . . 174

Procedure 19

 

Connecting a switch box and terminal to COM1 and COM2 ports

175

Procedure 20

 

Connecting a switch box and terminal to the SDI and COM1 ports 177

Procedure 21

 

Configuring a modem . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

180

Procedure 22

 

Connecting a modem to an SDI port . . . . . . . . . . . . . . . . . . . . . . . .

181

Procedure 23

Connecting a modem to a switch box, COM2 and SDI ports . . . . . 183

Procedure 24

Installing the CP PIV to I/O panel cables . . . . . . . . . . . . . . . . . . . . . 196

Procedure 25

Connecting the Clock Controller cables . . . . . . . . . . . . . . . . . . . . . 199

Procedure 26

Connecting the 3PE faceplates in the Core/Net modules . . . . . . . . 200

Procedure 27

Inspecting NT4N29AA factory installed cables . . . . . . . . . . . . . . . . 200

Procedure 28

Connecting the Core/Net backplanes . . . . . . . . . . . . . . . . . . . . . . . . 202

NN43021-310 Standard 02.01 December 2007

Page 15 of 456

Procedure 29

Connecting the Core module to a LAN . . . . . . . . . . . . . . . . . . . . . . . 205

Procedure 30

Cabling the Core/Net module backplane . . . . . . . . . . . . . . . . . . . . . 213

Procedure 31

Disconnecting cable connectors from the backplane . . . . . . . . . . . 214

Procedure 32

Installing the CP PIV to I/O panel cables . . . . . . . . . . . . . . . . . . . . . 221

Procedure 33

Connecting the Core module to a LAN . . . . . . . . . . . . . . . . . . . . . . . 223

Procedure 34

Installing the Shelf 0 fiber optic ring (ascending) . . . . . . . . . . . . . . 231

Procedure 35

Installing the Shelf 1 fiber optic ring . . . . . . . . . . . . . . . . . . . . . . . . . 232

Procedure 36

Connecting the FIJI to FIJI cables . . . . . . . . . . . . . . . . . . . . . . . . . . . 234

Procedure 37

Connecting the Clock Controller cables . . . . . . . . . . . . . . . . . . . . . . 236

Procedure 38

Connecting the 3PE faceplates in the Core/Net modules . . . . . . . . 240

Procedure 39

Connecting the Core/Net backplanes . . . . . . . . . . . . . . . . . . . . . . . . 241

Procedure 40

Connecting Groups 1 through 7: Shelf 0 to Shelf 1 . . . . . . . . . . . . . 243

Procedure 41

Connecting the Network Shelf 0 3PE cards to Core/Net 0 . . . . . . . 251

Procedure 42

Connecting the Network Shelf 1 3PE cards to Core/Net 1 . . . . . . . 251

Procedure 43

Basic cabling for single-row network connections . . . . . . . . . . . . . 252

Procedure 44

Basic cabling for multiple-row network connections . . . . . . . . . . . 256

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 16 of 456

Procedure 45

Cabling an IPE Module (NT8D37) or Media Gateway . . . . . . . . . . . 264

Procedure 46

 

Connecting lines and trunks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

266

Procedure 47

 

Installing the Security Device . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

300

Procedure 48

 

Preparing to power up – AC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

302

Procedure 49

Option 1: Using the installed power plug (recommended) . . . . . . . 302

Procedure 50

Option 2: Hard-wiring the power connections (optional) . . . . . . . . 303

Procedure 51

 

Turning AC power on . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

303

Procedure 52

Resetting the main circuit breakers (AC power) . . . . . . . . . . . . . . . 304

Procedure 53

 

Preparing to power up – DC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

306

Procedure 54

 

Turning DC power ON . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

307

Procedure 55

 

Installing the software . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

309

Procedure 56

 

Testing Core/Net 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

330

Procedure 57

 

Switching call processing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

332

Procedure 58

 

Testing Core/Net 0 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

333

Procedure 59

 

Testing module power supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

336

Procedure 60

 

Testing blower unit and thermal sensor . . . . . . . . . . . . . . . . . . . . .

337

NN43021-310 Standard 02.01 December 2007

Page 17 of 456

Procedure 61

Sysload test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 339

Procedure 62

Testing system terminal and system monitor . . . . . . . . . . . . . . . . . 340

Procedure 63

Testing the PFTU and its interface . . . . . . . . . . . . . . . . . . . . . . . . . . 341

Procedure 64

 

Drilling concrete floors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

348

Procedure 65

Installing Kit A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 349

Procedure 66

Installing Kit B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 351

Procedure 67

Installing earthquake rods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 352

Procedure 68

Leveling the system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 357

Procedure 69

Installing a Floor Mounting Kit (NT8D64BF) . . . . . . . . . . . . . . . . . . . 359

Procedure 70

Adding a module to the base of a column . . . . . . . . . . . . . . . . . . . . 365

Procedure 71

Adding a module between two other modules . . . . . . . . . . . . . . . . 370

Procedure 72

Adding a module to the top of the column . . . . . . . . . . . . . . . . . . . . 374

Procedure 73

Connecting a Nortel CP PM Signaling Server . . . . . . . . . . . . . . . . . 392

Procedure 74

Connecting a CP PM Signaling Server to the ELAN and TLAN subnets of a CS 1000E system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 393

Procedure 75

 

Connecting a CP PM Signaling Server to the ELAN and TLAN subnets of

a CS 1000M system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

395

Procedure 76

 

Connecting an IBM X306m Signaling Server . . . . . . . . . . . . . . . . . .

396

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 18 of 456

Procedure 77

Connecting an HP DL320-G4 Signaling Server . . . . . . . . . . . . . . . . 398

Procedure 78

Installing Signaling Server software . . . . . . . . . . . . . . . . . . . . . . . . . 400

Procedure 79

Entering basic system configuration parameters . . . . . . . . . . . . . . 427

Procedure 80

Adding a Follower Signaling Server to an IP Telephony node . . . 441

Procedure 81

Logging in to the Signaling Server . . . . . . . . . . . . . . . . . . . . . . . . . . 446

Procedure 82

Verifying the Signaling Server Ethernet connection . . . . . . . . . . . . 447

NN43021-310 Standard 02.01 December 2007

20

Page 19 of 456

How to get help

This section explains how to get help for Nortel products and services.

Getting help from the Nortel Web site

The best way to get technical support for Nortel products is from the Nortel

Technical Support Web site:

www.nortel.com/support

This site provides quick access to software, documentation, bulletins, and tools to address issues with Nortel products. More specifically, the site enables you to:

download software, documentation, and product bulletins

search the Technical Support Web site and the Nortel Knowledge Base for answers to technical issues

sign up for automatic notification of new software and documentation for Nortel equipment

open and manage technical support cases

Getting help over the telephone from a Nortel Solutions Center

If you don’t find the information you require on the Nortel Technical Support Web site, and have a Nortel support contract, you can also get help over the phone from a Nortel Solutions Center.

In North America, call 1-800-4NORTEL (1-800-466-7835).

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 20 of 456 How to get help

Outside North America, go to the following Web site to obtain the phone number for your region:

www.nortel.com/callus

Getting help from a specialist by using an Express Routing Code

To access some Nortel Technical Solutions Centers, you can use an Express Routing Code (ERC) to quickly route your call to a specialist in your Nortel product or service. To locate the ERC for your product or service, go to:

www.nortel.com/erc

Getting help through a Nortel distributor or reseller

If you purchased a service contract for your Nortel product from a distributor or authorized reseller, contact the technical support staff for that distributor or reseller.

NN43021-310 Standard 02.01 December 2007

22

Page 21 of 456

Finding the latest updates on the Nortel web site

The content of this documentation was current at the time the product was released. To check for updates to the latest documentation and software for CS 1000 Release 5.5, click one of the links below.

Latest Software

Takes you directly to the Nortel

 

page for CS 1000 Release 5.5

 

software.

 

 

Latest Documentation

Takes you directly to the Nortel

 

page for CS 1000 Release 5.5

 

documentation.

 

 

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 22 of 456 Finding the latest updates on the Nortel web site

NN43021-310 Standard 02.01 December 2007

Nortel Networks 1000M User Manual

30

Page 23 of 456

System information

This document is a global document. Contact your system supplier or your Nortel representative to verify that the hardware and software described are supported in your area.

Subject

WARNING

Before a Large System can be installed, a network assessment must be performed and the network must be VoIP-ready.

If the minimum VoIP network requirements are not met, the system will not operate properly.

For information on the minimum VoIP network requirements and converging a data network with VoIP, refer to Converging the Data Network with VoIP

(NN43001-260).

This document provides installation and acceptance testing procedures for

Meridian 1 Large Systems and Communication Server 1000M Large

Systems.

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 24 of 456 System information

For this document, the CP PIV processor is assumed in the case of the CS 1000M SG, Meridian 1 PBX 61C, CS 1000M MG, and Meridian 1

PBX 81C. If you are installing a system with a CP PII processor, please refer to the CS 1000 Release 5.0 version of this document, available on the web at:

www.nortel.com/support

To access the NTP from the Technical Support page, go to the content listing page for Communication Server 1000M:

1Select the Browse product support tab on the main page.

2Select Product Families from the drop-down menu, and then

Enterprise Communication Servers in the first window.

3Select Communication Server 1000M Cabinet/Chassis from the second window.

4Select Documentation from the third window and click the Go button on the right.

5Use the filter provided under the Documentation tab to search for

Communication Server 1000M 4.0.

Note on legacy products and releases

This NTP contains information about systems, components, and features that are compatible with Nortel Communication Server 1000 Release 5.5 software. For more information on legacy products and releases, click the

Technical Documentation link under Support & Training on the Nortel home page:

www.nortel.com/

Applicable systems

This document applies to the following systems:

Communication Server 1000M Half Group (CS 1000M HG)

Communication Server 1000M Single Group (CS 1000M SG)

Communication Server 1000M Multi Group (CS 1000M MG)

NN43021-310 Standard 02.01 December 2007

System information Page 25 of 456

Meridian 1 Option 51

Meridian 1 PBX 51C

Meridian 1 PBX 61C

Meridian 1 Option 71

Meridian 1 PBX 81

Meridian 1 PBX 81C

Note: When upgrading software, memory upgrades may be required on the Signaling Server, the Call Server, or both.

System migration

When particular Meridian 1 systems are upgraded to run CS 1000 Release 5.5 software and configured to include a Signaling Server, they become CS 1000M systems. Table 1 lists each Meridian 1 system that supports an upgrade path to a CS 1000M system.

Table 1

Meridian 1 systems to CS 1000M systems

This Meridian 1 system...

Maps to this CS 1000M system

 

 

Meridian 1 PBX 51C

CS 1000M Half Group

 

 

 

Meridian 1

PBX 61C

CS 1000M Single Group

 

 

 

Meridian 1

PBX 81

CS 1000M Multi Group

 

 

 

Meridian 1

PBX 81C

CS 1000M Multi Group

 

 

 

For more information, see Communication Server 1000M and Meridian 1 Large System Upgrade NTPs (NN43021-458NN43021-475).

Intended audience

This document is intended for individuals responsible for installing and configuring Large Systems. To use this document, you should have a basic knowledge of Large System equipment and operation. Contact Nortel for information on installation courses. You should also read and fully

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 26 of 456 System information

understand the Communication Server 1000M and Meridian 1: Large System Overview (NN43021-110) before you install a system.

Conventions

Terminology

The following systems are referred to generically as “Large System”:

Communication Server 1000M Half Group (CS 1000M HG)

Communication Server 1000M Single Group (CS 1000M SG)

Communication Server 1000M Multi Group (CS 1000M MG)

Meridian 1 Option 51

Meridian 1 PBX 51C

Meridian 1 PBX 61C

Meridian 1 Option 71

Meridian 1 PBX 81

Meridian 1 PBX 81C

NTP feedback

Nortel strives to provide accurate documentation for our customers. However, if you feel there are errors or omissions in this document, your feedback is welcome.

Send comments via e-mail to gntsdoc@nortel.com or open a problem report via the normal procedures.

Please provide as much information as possible including the NTP number, standard version and date of the document, as well as the page, problem description, and any supporting documentation and capture files.

NN43021-310 Standard 02.01 December 2007

System information Page 27 of 456

Related information

This section lists information sources that relate to this document.

NTPs

The following NTPs are referenced in this document:

Circuit Card: Description and Installation (NN43001-311)

Signaling Server: Installation and Commissioning (NN43001-312)

System Security Management (NN43001-602)

Software Input/Output: Administration (NN43001-611)

Telephones and Consoles: Description, Installation, and Operation

(NN43001-567)

Software Input/Output: System Messages (NN43001-712)

Communication Server 1000M and Meridian 1: Large System Overview

(NN43021-110)

Communication Server 1000M and Meridian 1: Large System Planning and Engineering (NN43021-220)

CS 1000M and Meridian 1 Large System Upgrades Overview

(NN43021-458)

CS 1000M and Meridian 1 51C to CS 1000M SG CP PIV Upgrade

(NN43021-459)

CS 1000M and Meridian 1 Option 51C to CS 1000M MG (CP PIV FNF) Upgrade (NN43021-460)

CS 1000M and Meridian 1 61C to CS 1000M SG CP PIV Upgrade

(NN43021-461)

CS 1000M and Meridian 1 61C CP PII to CS 1000M SG CP PIV Upgrade (NN43021-462)

CS 1000M and Meridian 1 61C to CS 1000M MG CP PIV FNF Upgrade

(NN43021-463)

CS 1000M and Meridian 1 61C CP PII to CS 1000M MG CP PII FNF Upgrade (NN43021-464)

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 28 of 456 System information

CS 1000M and Meridian 1 61C CP PII to CS 1000M MG CP PIV FNF Upgrade (NN43021-465)

CS 1000M and Meridian 1 CS1000M SG CP PIV to CS 1000M MG CP PIV FNF Upgrade (NN43021-466)

CS 1000M and Meridian 1 71 to CS 1000M MG CP PIV FNF Upgrade

(NN43021-467)

CS 1000M and Meridian 1 81 to CS 1000M MG CP PII FNF Upgrade

(NN43021-468)

CS 1000M and Meridian 1 81C IGS to CS 1000M MG CP PII FNF Upgrade (NN43021-469)

CS 1000M and Meridian 1 81C FNF to CS 1000M MG CP PII FNF Upgrade (NN43021-470)

CS 1000M and Meridian 1 81C IGS to CS 1000M MG CP PIV FNF Upgrade (NN43021-471)

CS 1000M and Meridian 1 CS 1000M MG CP PII IGS to CS 1000M MG CP PII FNF Upgrade (NN43021-472)

CS 1000M and Meridian 1 CS 1000M MG CP PII IGS to CS 1000M MG CP PIV FNF Upgrade (NN43021-473)

CS 1000M and Meridian 1 CS 1000M MG CP PII FNF to CS 1000M MG CP PIV FNF Upgrade (NN43021-474)

Other documentation

The following documentation is referenced in this document:

Candeo Power System User Guide (P0914425)

Candeo Power System Installation Guide (P0914426)

Candeo SP 48300 Power System AP6C55AA User Manual (P7000154)

Candeo SP 48300 Power System AP6C55AA Installation Manual

(P7000289)

NN43021-310 Standard 02.01 December 2007

System information Page 29 of 456

Online

To access Nortel documentation online, click the Technical Documentation link under Support & Training on the Nortel home page:

www.nortel.com

CD-ROM

To obtain Nortel documentation on CD-ROM, contact your Nortel customer representative.

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 30 of 456 System information

NN43021-310 Standard 02.01 December 2007

Loading...
+ 428 hidden pages